< Previous | Contents | Next >
A Review into Exam Results Issues Concerning the Scottish
Qualifications Authority
8. RECOMMENDATIONS
8.1 Introduction
Recommendations to ensure that the problems encountered do
not recur in future years depend for their success on a number of factors,
but most critically the ability of the individuals within the organisation
to implement the recommendations effectively.
Moreover, implementation of the recommendations to address
the perceived weaknesses within the SQA needs to be viewed in the context
of both the current situation within the SQA and the requirement to progress
Diet 2001 effectively.
At the present time, the SQA is in a fragile condition, with
management and staff both feeling extremely bruised and demoralised following
recent criticisms. This is likely to be compounded with the publication of
this report and the reports of the two parliamentary inquiries. It is important
to recognise this context in making and implementing recommendations. Equally,
it is important to acknowledge that the vast majority of staff worked exceptionally
hard over long days during a lengthy period of time in a desperate attempt
to ensure that Diet 2000 successfully achieved its 10 August objective. That
the failure was not greater is due to the diligence of the vast majority of
staff who were involved in the process.
At the same time, the management and staff are already under
tremendous pressure in respect of next year's Diet. Since mid-August 2000,
the SQA has been focused on the clear-up and appeals processes for Diet 2000
and has deliberately delayed commencing data processing of registrations and
entries for Diet 2001 with the aim of resolving some of the existing problems.
Whilst this has been necessary and unavoidable, it means that delays are already
evident in Diet 2001.
Given the above, it is essential that the identification
and implementation of recommendations are sensitive to the current context
and business pressures, and that the timeframe is also realistic. In the light
of current circumstances, the recommendations contained in the sections that
follow are split between those that need to be implemented immediately with
a view to assisting in the successful administration of Diet 2001 and those
that should be regarded as secondary objectives, in the sense only that whilst
essential they are less constrained by time.
We have not proposed an allocation of responsibilities for
implementing these recommendations because of current uncertainties in management
structure and future remits. Indeed, the Acting Chief Executive has already
recognised the need to strengthen existing management by tapping external
resources and skills.
The SQA is currently implementing a number of initiatives
in order to address some of the problems highlighted in chapter
4, chapter 5 and chapter
6 of this report. Appendix V summarises the
action that the SQA has taken to date and these actions address some of the
recommendations made below.
8.2 Management and Organisation
8.2.1 Immediate
Based on the information available to date, it is sensible
to be concerned about the ability of the SQA to administer Diet 2001 successfully
and appropriate to recognise achievement of that objective as the biggest
challenge and, therefore, the main priority for the SQA in the immediate future.
The Scottish Executive, the SQA Board and the senior management of the SQA
need, therefore, to balance the need for desired management and organisational
change with the ability of the organisation to implement change whilst focused
on the challenge of Diet 2001.
In terms of successfully administering Diet 2001, it is recommended
that the Acting Chief Executive should:
- develop a detailed understanding of the requirements of Diet 2001 and
a detailed operational plan for achieving a successful administration of
the Diet. This plan must prioritise actions and should:
- detail the requirements against the timeframe, specifying the critical
path;
- assess the ability of the organisation to handle the changed / increased
workload and produce a risk assessment;
- detail the additional resources, for example people, facilities, hardware,
services and funding that are required to achieve the Diet 2001 objective;
- communicate the plan, requirements and risks to the SQA Board and the
Scottish Executive and secure commitment to proceed, including assistance
where required, or obtain alternative instructions;
- review his Senior Management Team to ensure that he has the necessary
skills and experience to lead the organisation through Diet 2001 successfully,
and gain their commitment to the challenge ahead. If additional skills and
experience are required they must be sourced immediately;
- clearly define the roles and responsibilities of the Senior Management
Team against the detailed plan for the year;
- working with his Senior Management Team, make such changes to the organisational
structure and operating process that are viewed as essential to achieve
the Diet 2001 objective;
- as part of the above, produce a detailed plan for deploying / redeploying
existing and new staff resources including the handling of any outstanding
personnel issues;
- establish appropriate communication channels, including regular meetings
where required with the SQA Board, the Senior Management Team, the wider
management team and the staff of the SQA;
- ensure clear and effective communications with all stakeholders to ensure
a common understanding of the developing situation, including arrangements
for feedback from stakeholders;
Finally, the Scottish Executive and the SQA Board need to
give immediate consideration to the current interim management arrangements.
The Acting Chief Executive is on secondment for an initial period of six months,
extendable by agreement of both parties. A serious crisis could be created
if the Acting Chief Executive were to decide to terminate his secondment at
the end of the six month period.
8.2.2 Secondary
Beyond the immediate actions necessary to achieve Diet 2001,
there are a number of recommendations in respect of the management and organisation
of the SQA that arise out of this review. These are as follows:
- review the Management Statement and Financial Memorandum relating to the
SQA to clarify and remove anomalies, such as the respective responsibilities
of the Chairman and Chief Executive with regard to overall management of
the SQA;
- review the number of members of the SQA Board of Management with a view
to reducing this number from 25 to a smaller number that will facilitate
more effective Board management;
- notwithstanding the above, we do not recommend a radical overhaul of the
structural arrangements for the corporate management of the SQA. Similar
arrangements apparently work effectively within other NDPBs and we see no
reason in principle or design why they should not work effectively for the
SQA;
- develop a more effective operational planning regime to bridge the gap
between the Corporate Plan and operational management and implementation,
which was a significant weakness during 1999/2000;
- review both the management and wider organisational structures of the
SQA. Both are historical amalgams of the predecessor organisations. The
current directorate structure does not represent a sensible or effective
allocation of responsibilities in terms of either staff numbers or functions,
whilst the management structure has too large a management team (21 Heads
of Unit). Similarly, the wider organisational structure is the embodiment
of the predecessor organisations and does not match the changed operational
requirements of the business;
- there are differing views of the effect of the current split-site arrangements
on both the operational and cultural aspects of the organisation. The SQA
should consider the feasibility of a reduced site, including single-site,
operation and develop a business case for consideration. However, the difficulties
of moving to a single-site operation need to be fully considered together
with the potential benefits. The timeframe for achieving a single-site operation
also needs to be considered in detail given the on-going operational expectations
on the SQA;
- cultural change is a medium-to-long-term objective rather than a short-term
one. However, it is essential that the SQA starts to improve the management
style and individual and group behaviours within it, such that an SQA identity
and culture develops from the still prevalent SEB and SCOTVEC identities
that contribute to some of the organisational tensions;
- the EFQM Business Excellence Model should be considered as a template
for quality improvement and change management within the SQA, and a self-assessment
of the organisation against criteria within the model should be carried
out to establish the current position and areas for improvement;
- ISO Quality Management Systems should be considered as a framework for
ensuring that processes and procedures are documented and systematically
audited, both internally by trained auditors and externally by independent
assessors;
- Investors in People accreditation should also be considered
in order to co-ordinate the development of people to meet the future needs
of the organisation; and
- best practice benchmarking against leading organisations should be initiated
to gain knowledge of world-class systems and processes.
8.3 Operational Processes
8.3.1 Immediate
The following immediate recommendations are made in respect
of staffing and facilities:
- undertake an assessment of the level of staff resources required for Diet
2001, taking into consideration the ongoing delays and the timing and volume
of data processing. The assessment of staff requirements needs to take into
consideration the ongoing resources required to address the outstanding
issues in respect of Diet 2000;
- take steps to address the low morale and fatigue within the Operations
Unit given the sustained effort needed throughout Diet 2000;
- review the working practices within the Operations Unit and take steps
to ensure that there is adequate supervision of all core business activities
and where possible that multi-skilling is encouraged where practical;
- if deficiencies in the staff complement are identified, take steps to
ensure that new and/or temporary staff are given adequate training;
- consider the introduction of shift patterns during peak processing periods;
- establish stronger links between Centres and the SQA in order that any
queries can be resolved in an efficient and effective manner; and
- undertake a review of the physical layout of the Dalkeith site and take
steps to improve the data handling and data processing areas.
The following immediate recommendations are made in respect
of data management:
- prepare a detailed resource and time plan to identify how and when the
remaining steps required to complete Diet 2000 will be concluded and at
what stage APS will be updated with all the data required to prepare amended
award certificates;
- prepare a detailed plan and processing timetable for all the core business
activities for Diet 2001. Nominate a project manager to monitor each stage
and ensure that immediate action is taken to address any problems or processing
delays;
- hold briefing sessions with all Centres to address matters where difficulties
arose during Diet 2000 in respect of the provision of data;
- implement procedures to deal with errors identified during data validation
routines to ensure that all SQA staff and Centres clearly understand their
respective responsibilities;
- advise Centres of the dates by which internal assessment and estimation
data need to be submitted. The dates set should provide sufficient time
for data to be processed and missing assessment information to be followed
up prior to the start of the final examinations;
- introduce robust data control and handling procedures for each business
activity to ensure that data is received and processed in a controlled manner.
The following immediate recommendations are made in respect
of examination procedures:
- contact all markers employed during Diet 2000 immediately to acknowledge
their contribution this year and to ask for their continued support in future
diets;
- re-evaluate the basis of remuneration of markers in the light of the experience
of Diet 2000;
- take steps to ensure that marker invitations are issued no later than
January 2001. Contingency plans should be made to address any difficulties
that may occur during the recruitment process and to ensure that the process
is not delayed in the event of continued processing difficulties over registration
and entry information;
- review the examination and marking timetables to determine whether the
reduction in the time made available for markers can be sustained; and
- review the administration arrangements for marker meetings and take steps
to ensure that the difficulties encountered during Diet 2000 are not repeated.
8.3.2 Secondary
The following additional recommendations are made:
- consider options to simplify the actual data that has to be submitted
by Centres for internal assessments such as:
- a default for unit assessments with exception notification of different
combinations;
- one final end date for internal assessments as opposed to an end date
for each unit; and
- submission of failed assessments only with the default being a pass;
- on the introduction of any new developments, ensure staff within Operations
Unit are adequately briefed on the requirements;
- re-consider the job specification for the Head of Operations and give
consideration to the benefits of employing a person with a background in
data management; and
- improve the design of forms used to provide data at all stages.
8.4 Information Systems
8.4.1 Immediate
The following recommendations are made in respect of APS:
- focus on high priority APS amendments and SQAnet this year and limit other
systems development projects;
- prioritise feedback from units on APS according to the business benefit
and risks involved and only undertake changes viewed as critical this year.
Examples of amendments which are likely to be a high priority for this year
are:
- improved data processing controls and sense checks;
- the improvement and creation of key operational and management reports;
and
- the migration of Standard Grade results processing to APS;
- ensure that APS can provide management information to support each stage
of the awards procedures including appointment of markers, identification
of duplicate units, and completeness of internal and external assessment
data. An exercise should be undertaken to specify all online enquiries and
standard reports that are required by users, unit managers and the SMT.
This must include cross-unit and cross-divisional reporting requirements.
As with changes to APS, these report requests should be prioritised;
- produce a formal testing plan as part of the planning stage of APS enhancements
and test scripts for the complete system. A dedicated testing team should
be nominated by the business and IT Unit should be responsible for briefing
them with regards to good testing practice. Testing should be undertaken
on the complete system, not just changes, and it is important that full
end to end testing is undertaken by users;
- set up a dedicated test environment with a copy of the live data so that
load and volume testing can be undertaken to a degree which actually tests
the real-life situation;
- specify the level of system performance and resilience needed to deliver
Diet 2001 successfully and undertake a thorough test of performance against
this specification. The performance assessment should cover optimisation
of the database design and queries and may require further external assistance,
including the possible use of Compuware to undertake some automated testing;
- limit system maintenance to outside of normal working hours so that it
does not impact on users and give the impression of an unreliable system;
and
- ensure that the current versions of the APS database platform and software
tools remain supported and, if necessary, agree special terms with vendors
in order to provide this (as upgrades should not be attempted during Diet
2001).
The following recommendations are made in respect of project
management:
- appoint a project manager with responsibility over all aspects of the
APS project and the authority to carry out that role effectively. This project
manager should be suitably trained and experienced in order to minimise
the risk to delivery. If necessary, skills should be seconded in order to
provide the appropriate level of expertise;
- undertake effective risk management and apply the Prince methodology throughout
the project lifecycle;
- appoint a lead user for each process supported by APS and ensure they
have the authority and responsibility for gathering feedback, specifying
and prioritising requests and working with IT Unit on an ongoing basis to
deliver and test improvements; and
- ensure that appropriate refresher training on APS is undertaken by all
staff and that adequate training on all future enhancements is scheduled
and executed prior to such enhancements going 'live';
The following recommendations are made in respect of data
quality, input and controls:
- ensure the accuracy of the existing data prior to adding to it this year.
A thorough and complete data cleansing exercise should be carried out to
remove all duplicates and ensure accuracy of the core data;
- establish clear ownership of and responsibility for data:
- responsibility for the accuracy of candidate, entry, internal assessment
results and estimates data should reside with the submitting Centres;
- data owners should be appointed within the relevant SQA departments with
each having responsibility for ensuring the accuracy and completeness of
their particular data set;
- revisit validation rules in order to produce a clear set of checks agreed
between the business units and IT Unit to ensure only 'hard' or business
critical errors are rejected. The revised validation rules need to be communicated
to the Centres and their suppliers and tested prior to live use;
- revisit system controls and checks to define more practical rules, for
example around the generation of duplicate unit entries, and to ensure there
are adequate completeness of data checks for each of the core business activities;
- improve enquiry and reporting to provide visibility of processing status
within and between units and to the Centres. For example:
- send automatic electronic confirmation reports to Centres;
- undertake exception reporting on data which is late in being submitted;
- introduce better quality error messages; and
- report back to Centres on all data submitted so that estimates and
results are confirmed as well as entries; and
- establish automatic file tracking procedures for the SEEMIS data uplift
so that both receipt of a file and processing of a file by the SQA are acknowledged.
The following recommendations are made in respect of Centres
and their MIS suppliers:
- produce a user guide for Centres to explain what is being done at each
stage in the process and why, and to inform Centres on the action they should
be taking. This must include dates for data submission, and the preferred
frequency and format of submissions; and
- participate in more open discussion with Centres and suppliers and provide
clearer statements of requirements. Examples of where this needs to take
place are on the revised validation checks, the possible simplification
of course and assessment data, and the layout and functionality of SQAnet.
8.4.2 Secondary
The following secondary recommendations are made in respect
of APS:
- undertake a formal review of APS, reconsidering the existing functionality
and user-friendliness of the system and challenging the original specification;
and
- ensure that APS is properly documented both at a user and a technical
level.
Considering the strategic importance of information systems
to the SQA, the following recommendations are made:
- make IS/IT strategy and systems delivery a priority for the SMT and the
Board. This should include ensuring there is a reasoned business case for
projects;
- consider appointing a Director of IT given the current and growing importance
of this area to the SQA's business;
- develop an IT/IS strategy in line with the business strategy and maintain
the strategy in order to support the business objectives;
- view systems projects holistically, considering the business change involved;
- place increased emphasis on forward planning of both strategic and operational
IT/IS requirements; and
- make better use of technology, for example scanning and SQAnet in the
short term. Longer-term options such as IT based assessment should involve
full consideration of business benefits and risks prior to making informed
decisions.
The following additional recommendations are made in respect
of data input and controls:
- redesign forms so that hand-written results are not required, for example
by using checkboxes with marks for pass/fail/defer unit assessment results;
- introduce scanning of forms such as the assessment results, estimates
and EX6 forms to ensure still greater accuracy of data input as well as
a higher throughput;
- provide an electronic option for all data and incentivise Centres to submit
data using this option as opposed to using paper forms; and
- provide an electronic delivery mechanism (SQAnet) for all Centres and,
again, incentivise Centres to use this method for submission as opposed
to providing files on disk.
The following additional recommendations are made in respect
of Centres and MIS suppliers:
- all Centres should be able to access SQAnet, perhaps with the exception
of some smaller employers, but certainly all schools should ensure that
they have the facility (i.e. a computer and an internet connection) to use
this; and
- service level agreements should be considered with Centres, for example
the undertaking to process and report within one week of electronic data
submission, and two weeks for hard copy data submission. This will assist
in establishing standards of service and confidence in the SQA.
< Previous | Contents | Next > |