Non-Graphical version
Scottish Executive Previous page Contents page Next Page

Final Report: Options for the Ferry Services Between Gourock and Dunoon

10. IMPLEMENTATION ISSUES AND NEXT STEPS

10.1 The Base Case

The results of the financial model of future options suggest that the status quo option. or "do nothing" alternative is not an inexpensive or easy option, for the following reasons:

The fundamental problem is that there is currently substantial excess capacity on the route, which would be most cost-effectively served by a single ferry operator.

The financial model suggests that it is cheaper to run a service between McInroy's Point and Hunter's Quay than between Gourock and Dunoon, largely because of the investment required to adapt Dunoon to front-end loading roll-on, roll-off ferries. However, there may be a corresponding public benefit from developing Dunoon Pier in this way, in order to draw visitors through the town. Whether this is the case, and if so, how great the external benefit is, are questions which lie beyond the remit of this study.

10.2 The Implementation of Change

10.2.1 The Cost Reduction Option

Option B presents issues of both technical and financial feasibility which make 'it difficult to assess at this stage against other, more concrete, options. Its implementation issues can be summarised as follows:

Each of these is significant and requires investigation before any definitive opinion on this option could be drawn.

10.2.2 The Single Operator Options

A 'single operator/single route' solution represents the most cost-effective method of service delivery in the medium term, resulting in savings to the taxpayer of up to £7 million compared to the status quo over a 15 year period on our calculation. If this is accepted, then the next step in the consideration of future service delivery would involve the development of an implementation plan:

We modelled the 'single operator' options: D, E and F. In practice, there may be constraints on the implementation of each of them.

10.2.3 Option D : withdrawal of the Gourock/Dunoon service

Option D might be regarded as a weakening of the Secretary of State's previous commitment to a passenger service between Gourock and Dunoon. Service users would, therefore, need to be consulted before this option could be implemented. It would also, under current ownership arrangements, leave the route in the hands of a private sector operator who would effectively have a monopoly on it.

The possible abuse of such a monopoly position was a cause of concern among route users in the early 1980s, and to provide comfort, enforceable assurances would need to be secured that the service operator would not act in an anti-competitive manner. The question of how this could be done in law rests outside the scope of this study, as does the specification of a detailed service agreement in consultation with service users and other interested parties.

10.2.4 Option E : retention and upgrading of Dunoon

Option E involves upgrading Dunoon Pier to accommodate a ferry service from McInroy's Point (or, under Option F, from Gourock). This is Pot the least cost option - a ferry terminating at Hunter's Quay would involve significantly lower investment in pier infrastructure. This additional cost can only be justified if there is an external public benefit from routing ferries through Dunoon rather than Hunter's Quay. The calculation of the value of such a benefit lies outside the scope of this report.

If an independent assessment concluded that the volume of the external benefit was sufficient, on reasonable assumptions, to outweigh the extra costs associated with a Dunoon option, the next issue would be how such an option could, in practice, be implemented. There is no way that Western Ferries, as a private sector operator, could be forced to close the McInroy's Point/Hunter's Quay service. It would do so only by agreement. The question is whether, and under what conditions, such agreement would be forthcoming, and what premium would be fair and reasonable for the purchase of Western Ferries' route rights and assets.

One potential method by which such a solution could be implemented is through a Public/ Private Partnership (PPP) service agreement.

The PPP makes a distinction between the public sector as a client responsible for commissioning a service, and the private sector concessionaire responsible for its delivery. The Inverclyde-Cowal ferry service could be procured under the PPP by. means of an explicit Service Agreement which would set minimum standards for service safety, regularity and quality, and might also regulate the tariffs charged to passengers together with procedures for their adjustment.13 A private sector concessionaire would then be selected following a competitive tender and given responsibility for service design, financing, investment and operation.

A possible framework for such a Service Agreement is set out in Figure 10. 1 overleaf.

Figure 10.1 DELIVERY OF FERRY SERVICES ON THE GOUROCK/ DUNOON ROUTE A POSSIBLE PFI MODEL

fig 10.1

Source: Deloitte and Touche

Figure 10. 1 shows that the existing service providers would vest their route rights and assets into a client organisation14 in return for a payment which would reflect their value. The client organisation would then package these rights and assets into a tender for the overall right to operate the route over a period of perhaps 20 - 30 years. The period would have to be of sufficient duration to enable any concessionaire to recoup their investment costs on upgrading the vessels and pier infrastructure necessary to meet their service obligations.

If this method of providing ferry services were selected, then it would only be implemented if the two existing service operators agreed to rest their route rights in a client organisation. Whether, and in what terms, they would be prepared to contemplate this are questions which lie outside the scope of this study.

10.2.5 Option F : closure of McInroy's Point/Hunter's Quay

Option F could be achieved by two methods:

The alternative, of allowing CalMac to win a competitive battle against Western Ferries by pumping in route subsidies so that CalMac could undercut Western Ferries, would be unfair, costly and economically inefficient.

The question is whether CalMac could compete with Western Ferries on these terms. If it could, the likely consequence of complete liberalisation would be an intense competitive war between the two operators to gain dominance on the route. Our route analysis suggests that the market is not big enough to support two operators, so eventually one of them would be driven out or become insolvent.

10.3 Conclusions

We were not required to arrive at a single recommended option, and have not done so. However, the logic of the analysis is clear - namely, that the towns of Gourock and Dunoon could be linked most cost-effectively by a single operator, and the costs of the status quo are likely to increase as new investment to sustain it becomes unavoidable. However, a single service will lose the benefits of consumer choice and competition.

For this reason, there may be merit in further examining the more radical option presented by CalMac. as Option B from both the technical and commercial aspects. It should also be noted that none of the options are able to meet the refurbishment of Dunoon Pier to the scale envisaged by Argyll & Bute Council and that work remains to be done on the economic impact on the town of Dunoon of the pier no longer being used by CalMac.

 

  Previous page Contents page Next Page