8.8 Option D: Gourock/Dunoon service closed
Under this option, the Gourock/Dunoon service is closed altogether, leaving the McInroy's Point/Hunter's Quay route as the only service across the Upper Clyde.
We assume that this option carries the following costs for the Gourock/Dunoon service operator:
There are assumed to be no net costs associated with the mothballing of Dunoon Pier. The pier owner would lose berthing dues of £0.27 million a year, but this loss would be offset by reductions in pier operation and maintenance costs. We are advised that the cost of demolishing Dunoon Pier, should this become necessary, would be £5 million, which would need to be added onto the NPVs calculated here.
We make the following assumptions about the financial impact of this option on the McInroy's Point/Hunter's Quay service operator:
The implications of the closure of the Gourock/Dunoon service on the two operators are shown in the tables which follow labelled Option D. This option has a NPV of negative £4.6 million for the Gourock/ Dunoon service operator, owing to the ongoing costs which cannot be reallocated, compared to the status quo which was minus £7.8 million.
The McInroy's Point/Hunter's Quay service increases its NPV to £9.3 million at 6%, an increase on the status quo of £1.7 million.
In principle, therefore, the McInroy's Point/Hunter's Quay service provider could be in a position to meet the closure costs of around £1 million of the Gourock/Dunoon service from the additional surplus it makes by securing exclusive rights to the route. It could also meet the costs of a dedicated bus service to meet the needs of foot passengers travelling between Gourock and Dunoon. Whether it could, in addition, offer real tariff reductions to passengers compared to the status quo is debateable, since the increased NPV of £1.7 million would, on the face of it, be inadequate. However, a private sector operator in a monopoly position might be willing and able to take steps to increase revenues.
There is an issue as to whether the service could deal with service peaks. Our analysis suggests that it could. During the period of the brief CalMac strike in July 1997, the service absorbed the additional demands made on it with no queuing delays, although CalMac takes the view that customers chose not to travel during that period. However, the capability of the service to meet rising demand, either through increased deck capacity or through increased service frequency, needs to be confirmed.
Western Ferries has confirmed that pre-determined performance standards were acceptable to it in exchange for a monopoly of the route.
Gourock Closure
|
Year |
||||||||||||||||
|
0 |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 et seq |
|
|
Gourock/Dunoon Service Operator |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
|
Revenues |
||||||||||||||||
|
Tariff revenues |
||||||||||||||||
|
Non-tariff revenues |
||||||||||||||||
|
Sub-total, operating revenues: |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Costs |
||||||||||||||||
|
Direct ship costs |
200 |
200 |
200 |
200 |
200 |
200 |
200 |
200 |
200 |
200 |
200 |
200 |
200 |
200 |
200 |
200 |
|
Indirect ship costs |
||||||||||||||||
|
Direct shore costs - |
||||||||||||||||
|
Indirect shore costs |
400 |
300 |
200 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
|
Sub-total, operating costs: |
600 |
500 |
400 |
300 |
300 |
300 |
300 |
300 |
300 |
300 |
300 |
300 |
300 |
300 |
300 |
300 |
|
Operating surplus (deficit) |
-600 |
-500 |
-400 |
-300 |
-300 |
-300 |
-300 |
-300 |
-300 |
-300 |
-300 |
-300 |
-300 |
-300 |
-300 |
-300 |
|
Investment Profile |
||||||||||||||||
|
Ships |
||||||||||||||||
|
Overhaul of existing vessels |
||||||||||||||||
|
Purchase of new vessels |
||||||||||||||||
|
Decommissioning of vessels |
||||||||||||||||
|
Sale proceeds from surplus vessels |
-70 |
|||||||||||||||
|
Sub-total, ships: |
-70 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Piers |
||||||||||||||||
|
Gourock - Linkspans |
||||||||||||||||
|
Gourock - Terminals |
1,000 |
redundancies |
||||||||||||||
|
Gourock - Breakwaters |
|
|
||||||||||||||
|
Sub-total, Gourock Pier: |
1,000 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Dunoon - Linkspans |
||||||||||||||||
|
Dunoon - Terminals |
140 |
redundancies |
||||||||||||||
|
Dunoon - Breakwaters |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Sub-total, Dunoon Pier: |
140 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Total investment requirements |
1,070 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0
|
|
Total cashflow |
-1,670 |
-500 |
-400 |
-300 |
-300 |
-300 |
-300 |
-300 |
-300 |
-300 |
-300 |
-300 |
-300 |
-300 |
-300 |
-300 |
|
Discount rate |
6% |
|||||||||||||||
|
Net Present Value |
(£4,586) |
|||||||||||||||
Gourock Closure
|
Year |
||||||||||||||||
|
0 |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 et seq | |
|
McInroy's Point 1 Hunter's Quay Service Operator |
||||||||||||||||
|
Revenues |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
|
Tariff revenues |
3,798 |
3,885 |
3,975 |
4,066 |
4,107 |
4,148 |
4,190 |
4,232 |
4,274 |
4,317 |
4,360 |
4,403 |
4,447 |
4,492 |
4,537 |
4,582 |
|
Non-tariff revenues |
130 |
130 |
130 |
130 |
130 |
130 |
130 |
130 |
130 |
130 |
130 |
130 |
130 |
130 |
130 |
130 |
|
Sub-total, operating revenues: |
3,928 |
4,015 |
4,105 |
4,196 |
4,237 |
4,278 |
4,320 |
4,362 |
4,404 |
4,447 |
4,490 |
4,533 |
4,577 |
4,622 |
4,667 |
4,712 |
|
Costs |
||||||||||||||||
|
Direct ship costs- |
1,656 |
1,656 |
1,656 |
1,656 |
1,656 |
1,656 |
1,656 |
1,656 |
1,656 |
1,656 |
1,656 |
1,656 |
1,656 |
1,656 |
1,656 |
1,656 |
|
Indirect ship costs |
403 |
403 |
403 |
403 |
403 |
403 |
403 |
403 |
403 |
403 |
403 |
403 |
403 |
403 |
403 |
403 |
|
Direct shore costs |
445 |
445 |
445 |
445 |
445 |
445 |
445 |
445 |
445 |
445 |
445 |
445 |
445 |
445 |
445 |
445 |
|
Indirect shore costs |
405 |
405 |
405 |
405 |
405 |
405 |
405 |
405 |
405 |
405 |
405 |
405 |
405 |
405 |
405 |
405 |
|
Sub-total, operating costs: |
2,909 |
2,909 |
2,909 |
2,909 |
2,909 |
2,909 |
2,909 |
2,909 |
2,909 |
2,909 |
2,909 |
2,909 |
2,909 |
2,909 |
2,909 |
2,909 |
|
Operating surplus (deficit) |
1,019 |
1,106 |
1,195 |
1,287 |
1,328 |
1,369 |
1,410 |
1,452 |
1,494 |
1,537 |
1,580 |
1,624 |
1,668 |
1,713 |
1,757 |
1,803 |
|
Investment Profile |
||||||||||||||||
|
Ships |
||||||||||||||||
|
Overhaul of existing vessels |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Purchase of new vessels |
0 |
0 |
1,500 |
1,500 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Decommissioning of vessels |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Sale proceeds from surplus vessels |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Sub-total, ships: |
0 |
0 |
1,500 |
1,500 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Piers |
||||||||||||||||
|
Hunter's Quay - Linkspans |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0. |
0 |
0 |
0 |
|
Hunter's Quay - Terminals |
0 |
1500 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Hunter's Quay - Breakwaters |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Sub-total, Hunter's Quay Pier: |
0 |
1500 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
McInroy's Point - Linkspans |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
McInroy's Point - Terminals |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
McInroy's Point - Breakwaters |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Sub-total, McInroy's Point: |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0
|
|
Bus operation |
200 |
150 |
75 |
75 |
75 |
75 |
75 |
75 |
200 |
150 |
75 |
75 |
75 |
75 |
75 |
75 |
|
Total investment requirements |
200 |
1,650 |
1,575 |
1,575 |
75 |
75 |
75 |
75 |
200 |
150 |
75 |
75 |
75 |
75 |
75 |
75 |
|
Total cashflow |
819 |
-544 |
-380 |
-288 |
1,253 |
1,294 |
1,335 |
1,377 |
1,294 |
1,387 |
1,505 |
1,549 |
1,593 |
1,638 |
1,682 |
1,728 |
|
Discount rate |
6% |
|||||||||||||||
|
Net Present Value |
£9,298 |
|||||||||||||||
|
Net Present Value @ 9% |
£7,026 |
|||||||||||||||