Graphical version

SCOTTISH EXECUTIVE

[Previous] [Contents] [Next]

Final Report: Options for the Ferry Services Between Gourock and Dunoon

8.6 Option B/1: enhanced Gourock/Dunoon Service

This option, which was put forward by CalMac, makes some radical proposals and is at a very early stage of conceptual development. Accordingly, neither Western Ferries nor Deloitte & Touche are able to comment on its feasibility although Western Ferries does have strong reservations about this proposal's feasibility. However, it will be seen that the option results in significant savings to the public purse, which are worthy of further investigation and the Government have asked CalMac to prepare a more detailed analysis of costs and revenues upon which comments will be invited from those being consulted about these options.

Under this option, the Gourock/Dunoon service operator would invest in two new bow-and-stem roll-on roll-off vessels to enable quicker turnaround times for vehicles on either end of the crossing. These vessels would be second-hand, refurbished vessels, not dissimilar to those presently operated by Western Ferries. The service would also adopt a low cost structure, very different from its present one. Finally, the Dunoon Pier would not be refurbished: instead, a low-cost concrete slipway would be installed at a suitable location yet to be decided, near to the Pier.

This option varies from the status quo in the following detailed respects:

The effect of these changes on the two service operators is shown in the tables which follow. In summary, the reduction in costs and the gain in market share turns the operating deficit of the Gourock/Dunoon service operator to a positive cash flow of £600-900,000 over the 15 year period as tariff revenues grow. However, to achieve this result5 an investment of £8 million is required on Dunoon Pier and on new vessels in the first three years of service delivery. An investment of £0.5 million in redundancy costs is also required. The Net Present Value of this option over the period to the Gourock/ Dunoon service operator, applying a 6% discount rate, is consequently reduced to £1.8 million (negative). This represents a saving of £6 million NPV on the status quo. It should, however, be stressed that this result may change if any of the assumptions fail to occur as planned. In particular:

The NPV of service delivery also falls for the McInroy's Point/Hunter's Quay service operator. It loses market share and hence revenues but, on the model assumptions, is unable to reduce its operating and investment costs compared to the status quo. Consequently, the NPV of its operation falls to £5.8 million under this option, or about £2 million less than under the status quo.

 

Enhanced G-D Service £3.8m Ship

 

Year

0

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15 et seq

Gourock/Dunoon Service Operator

£000

£000

£000

£000

£000

£000

£000

£000

£000

£000

£000

£000

£000

£000

£000

£000

Revenues

                               

Tariff revenues

1,617

1,770

1,811

1,853

1,871

1,890

1,909

1,928

1,947

1,966

1,986

2,006

2,026

2,046

2,067

2,087

Non-tariff revenues

190

190

190

190

190

190

190

190

190

190

190

190

190

190

190

190

Sub-total, operating revenues:

1,807

1,960

2,001

2,043

2,061

2,080

2,099

2,118

2,137

2,156

2,176

2,196

2,216

2,236

2,257

2,277

Costs

                               

Direct ship costs

895

895

895

895

895

895

895

895

895

895

895

895

895

895

895

895

Indirect ship costs

100

100

100

100

100

100

100

100

100

100

100

100

100

100

100

100

Direct shore costs

250

250

250

250

250

250

250

250

250

250

250

250

250

250

250

250

Indirect shore costs

260

260

260

260

260

260

260

260

260

260

260

260

260

260

260

260

Sub-total, operating costs:

1,505

1,505

1,505

1,505

1,505

1,505

1,505

1,505

1,505

1,505

1,505

1,505

1,505

1,505

1,505

1,505

Operating surplus (deficit)

302

455

496

538

556

575

594

613

632

651

671

691

711

731

752

772

Investment Profile

                               

Ships

                               

Overhaul of existing vessels

                               

Purchase of new vessels

 

7,600

                           

Decommissioning of vessels

                               

Redundancies among crew and terminal staff

 

500

                           

Sale proceeds from surplus vessels

 

-140

                           

Sub-total, ships:

0

7,960

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Piers

                               

Gourock - Linkspans

                               

Gourock - Terminals

                               

Gourock - Breakwaters

                               

Sub-total, Gourock Pier:

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Dunoon - Linkspans

600

                             

Dunoon - Terminals

                               

Dunoon - Breakwaters

                               

Sub-total, Dunoon Pier:

600

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Total investment requirements

600

7,960

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Total cashflow

-298

-7,505

496

538

556

575

594

613

632

651

671

691

711

731

752

772

Discount rate

6%

                             

Net Present Value

(£1,810)

                             

 

Enhanced G-D Service £3.8m Ship

Mclnroy's Point / Hunter's Quay Service Operator

                               

Revenues

£000

£000

£000

£000

£000

£000

£000

£000

£000

£000

£000

£000

£000

£000

£000

£000

Tariff revenues

2,603

2,676

2,738

2,801

2,829

2,858

2,886

2,915

2,944

2,974

3,003

3,033

3,064

3,094

2,974

3,004

Non-tariff revenues

60

61

62

63

64

65

66

67

68

69

70

71

72

73

74

75

Sub-total, operating revenues:

2,663

2,737

2,800

-2,864

2,893

2,923

2,952

2,982

3,012

3,043

3,073

3,104

3,136

3,167

3,048

3,079

Costs

                               

Direct ship costs

1,190

1,190

1,190

1,190

1,190

1,190

1,190

1,190

1,190

1,190

1,190

1Y190

1,190

1,190

1,190

1,190

Indirect ship costs

290

290

290

290

290

290

290

290

290

290

290

290

290

290

290

290

Direct shore costs

320

320

320

320

320

320

320

320

320

320

320

320

320

320

320

320

Indirect shore costs

305

305

305

305

305

305

305

305

305

305

305

305

305

305

305

305

Sub-total, operating costs:

2,105

2,105

2,105

2,105

2,105

2,105

2,105

2,105

2,105

2,105

2,105

2,105

2,105

2,105

2,105

2,105

Operating surplus (deficit)

558

632

695

759

788

818

847

877

907

938

968

999

1,031

1,062

943

974

Investment Profile

                               

Ships

                               

Overhaul of existing vessels

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Purchase of new vessels

0

0

1,500

0

0

0

0

0

0

0

0

0

0

0

0

0

Decommissioning of vessels

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Sale proceeds from surplus vessels

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Sub-total, ships:

0

0

1,500

0

0

0

0

0

0

0

0

0

0

0

0

0

Piers

                               

Hunter's Quay - Linkspans

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Hunter's Quay - Terminals

0

1,500

0

0

0

0

0

0

0

0

0

0

0

0

0-

0

Hunter's Quay - Breakwaters

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Sub-total, Hunter's Quay Pier:

0

1,500

0

0

0

0

0

0

0

0

0

0

0

0

0

0

McInroy's Point - Linkspans

                               

McInroy's Point - Terminals

                               

McInroy's Point - Breakwaters

                               

Sub-total, McInroy's Point:

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Total investment requirements

0

1,500

1,500

0

0

0

0

0

0

0

0

0

0

0

0

0

Total cashflow

558

-868

-805

759

788

818

847

877

907

938

968

999

1,031

1,062

943

974

Discount rate

6%

                             

Net Present Value

£5,757

                             

Net Present Value @ 9%

£4,305

                             

 

[Previous] [Contents] [Next]