8.6 Option B/1: enhanced Gourock/Dunoon Service
This option, which was put forward by CalMac, makes some radical proposals and is at a very early stage of conceptual development. Accordingly, neither Western Ferries nor Deloitte & Touche are able to comment on its feasibility although Western Ferries does have strong reservations about this proposal's feasibility. However, it will be seen that the option results in significant savings to the public purse, which are worthy of further investigation and the Government have asked CalMac to prepare a more detailed analysis of costs and revenues upon which comments will be invited from those being consulted about these options.
Under this option, the Gourock/Dunoon service operator would invest in two new bow-and-stem roll-on roll-off vessels to enable quicker turnaround times for vehicles on either end of the crossing. These vessels would be second-hand, refurbished vessels, not dissimilar to those presently operated by Western Ferries. The service would also adopt a low cost structure, very different from its present one. Finally, the Dunoon Pier would not be refurbished: instead, a low-cost concrete slipway would be installed at a suitable location yet to be decided, near to the Pier.
This option varies from the status quo in the following detailed respects:
The effect of these changes on the two service operators is shown in the tables which follow. In summary, the reduction in costs and the gain in market share turns the operating deficit of the Gourock/Dunoon service operator to a positive cash flow of £600-900,000 over the 15 year period as tariff revenues grow. However, to achieve this result5 an investment of £8 million is required on Dunoon Pier and on new vessels in the first three years of service delivery. An investment of £0.5 million in redundancy costs is also required. The Net Present Value of this option over the period to the Gourock/ Dunoon service operator, applying a 6% discount rate, is consequently reduced to £1.8 million (negative). This represents a saving of £6 million NPV on the status quo. It should, however, be stressed that this result may change if any of the assumptions fail to occur as planned. In particular:
The NPV of service delivery also falls for the McInroy's Point/Hunter's Quay service operator. It loses market share and hence revenues but, on the model assumptions, is unable to reduce its operating and investment costs compared to the status quo. Consequently, the NPV of its operation falls to £5.8 million under this option, or about £2 million less than under the status quo.
Enhanced G-D Service £3.8m Ship
|
Year |
||||||||||||||||
|
0 |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 et seq |
|
|
Gourock/Dunoon Service Operator |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
|
Revenues |
||||||||||||||||
|
Tariff revenues |
1,617 |
1,770 |
1,811 |
1,853 |
1,871 |
1,890 |
1,909 |
1,928 |
1,947 |
1,966 |
1,986 |
2,006 |
2,026 |
2,046 |
2,067 |
2,087 |
|
Non-tariff revenues |
190 |
190 |
190 |
190 |
190 |
190 |
190 |
190 |
190 |
190 |
190 |
190 |
190 |
190 |
190 |
190 |
|
Sub-total, operating revenues: |
1,807 |
1,960 |
2,001 |
2,043 |
2,061 |
2,080 |
2,099 |
2,118 |
2,137 |
2,156 |
2,176 |
2,196 |
2,216 |
2,236 |
2,257 |
2,277 |
|
Costs |
||||||||||||||||
|
Direct ship costs |
895 |
895 |
895 |
895 |
895 |
895 |
895 |
895 |
895 |
895 |
895 |
895 |
895 |
895 |
895 |
895 |
|
Indirect ship costs |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
100 |
|
Direct shore costs |
250 |
250 |
250 |
250 |
250 |
250 |
250 |
250 |
250 |
250 |
250 |
250 |
250 |
250 |
250 |
250 |
|
Indirect shore costs |
260 |
260 |
260 |
260 |
260 |
260 |
260 |
260 |
260 |
260 |
260 |
260 |
260 |
260 |
260 |
260 |
|
Sub-total, operating costs: |
1,505 |
1,505 |
1,505 |
1,505 |
1,505 |
1,505 |
1,505 |
1,505 |
1,505 |
1,505 |
1,505 |
1,505 |
1,505 |
1,505 |
1,505 |
1,505 |
|
Operating surplus (deficit) |
302 |
455 |
496 |
538 |
556 |
575 |
594 |
613 |
632 |
651 |
671 |
691 |
711 |
731 |
752 |
772 |
|
Investment Profile |
||||||||||||||||
|
Ships |
||||||||||||||||
|
Overhaul of existing vessels |
||||||||||||||||
|
Purchase of new vessels |
7,600 |
|||||||||||||||
|
Decommissioning of vessels |
||||||||||||||||
|
Redundancies among crew and terminal staff |
500 |
|||||||||||||||
|
Sale proceeds from surplus vessels |
-140 |
|||||||||||||||
|
Sub-total, ships: |
0 |
7,960 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Piers |
||||||||||||||||
|
Gourock - Linkspans |
||||||||||||||||
|
Gourock - Terminals |
||||||||||||||||
|
Gourock - Breakwaters |
||||||||||||||||
|
Sub-total, Gourock Pier: |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Dunoon - Linkspans |
600 |
|||||||||||||||
|
Dunoon - Terminals |
||||||||||||||||
|
Dunoon - Breakwaters |
||||||||||||||||
|
Sub-total, Dunoon Pier: |
600 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Total investment requirements |
600 |
7,960 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Total cashflow |
-298 |
-7,505 |
496 |
538 |
556 |
575 |
594 |
613 |
632 |
651 |
671 |
691 |
711 |
731 |
752 |
772 |
|
Discount rate |
6% |
|||||||||||||||
|
Net Present Value |
(£1,810) |
|||||||||||||||
Enhanced G-D Service £3.8m Ship
|
Mclnroy's Point / Hunter's Quay Service Operator |
||||||||||||||||
|
Revenues |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
£000 |
|
Tariff revenues |
2,603 |
2,676 |
2,738 |
2,801 |
2,829 |
2,858 |
2,886 |
2,915 |
2,944 |
2,974 |
3,003 |
3,033 |
3,064 |
3,094 |
2,974 |
3,004 |
|
Non-tariff revenues |
60 |
61 |
62 |
63 |
64 |
65 |
66 |
67 |
68 |
69 |
70 |
71 |
72 |
73 |
74 |
75
|
|
Sub-total, operating revenues: |
2,663 |
2,737 |
2,800 |
-2,864 |
2,893 |
2,923 |
2,952 |
2,982 |
3,012 |
3,043 |
3,073 |
3,104 |
3,136 |
3,167 |
3,048 |
3,079 |
|
Costs |
||||||||||||||||
|
Direct ship costs |
1,190 |
1,190 |
1,190 |
1,190 |
1,190 |
1,190 |
1,190 |
1,190 |
1,190 |
1,190 |
1,190 |
1Y190 |
1,190 |
1,190 |
1,190 |
1,190 |
|
Indirect ship costs |
290 |
290 |
290 |
290 |
290 |
290 |
290 |
290 |
290 |
290 |
290 |
290 |
290 |
290 |
290 |
290 |
|
Direct shore costs |
320 |
320 |
320 |
320 |
320 |
320 |
320 |
320 |
320 |
320 |
320 |
320 |
320 |
320 |
320 |
320 |
|
Indirect shore costs |
305 |
305 |
305 |
305 |
305 |
305 |
305 |
305 |
305 |
305 |
305 |
305 |
305 |
305 |
305 |
305 |
|
Sub-total, operating costs: |
2,105 |
2,105 |
2,105 |
2,105 |
2,105 |
2,105 |
2,105 |
2,105 |
2,105 |
2,105 |
2,105 |
2,105 |
2,105 |
2,105 |
2,105 |
2,105 |
|
Operating surplus (deficit) |
558 |
632 |
695 |
759 |
788 |
818 |
847 |
877 |
907 |
938 |
968 |
999 |
1,031 |
1,062 |
943 |
974 |
|
Investment Profile |
||||||||||||||||
|
Ships |
||||||||||||||||
|
Overhaul of existing vessels |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Purchase of new vessels |
0 |
0 |
1,500 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Decommissioning of vessels |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Sale proceeds from surplus vessels |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Sub-total, ships: |
0 |
0 |
1,500 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Piers |
||||||||||||||||
|
Hunter's Quay - Linkspans |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Hunter's Quay - Terminals |
0 |
1,500 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0- |
0 |
|
Hunter's Quay - Breakwaters |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Sub-total, Hunter's Quay Pier: |
0 |
1,500 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
McInroy's Point - Linkspans |
||||||||||||||||
|
McInroy's Point - Terminals |
||||||||||||||||
|
McInroy's Point - Breakwaters |
||||||||||||||||
|
Sub-total, McInroy's Point: |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Total investment requirements |
0 |
1,500 |
1,500 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Total cashflow |
558 |
-868 |
-805 |
759 |
788 |
818 |
847 |
877 |
907 |
938 |
968 |
999 |
1,031 |
1,062 |
943 |
974 |
|
Discount rate |
6% |
|||||||||||||||
|
Net Present Value |
£5,757 |
|||||||||||||||
|
Net Present Value @ 9% |
£4,305 |