Graphical version

SCOTTISH EXECUTIVE

Back

Options for the Future of Ferry Services Between Gourock and Dunoon
Addendum

CONTENTS

1. ADDENDUM TO THE DELOITTE & TOUCHE REPORT ON THE GOUROCK DUNOON FERRY SERVICE
1.1 Introduction
1.2 The Original Options
1.3 Option B
1.4 Introduction to the Halcrow Crouch Report.
1.5 Costs
1.6 Non-Financial Evaluation from Halcrow Crouch Report
1.7 Revised Net Present Cost of Option B Using Halcrow Crouch Data
1.8 Non-Financial Analysis
1.9 Conclusion

1. ADDENDUM TO THE DELOITTE & TOUCHE REPORT ON THE GOUROCK-DUNOON FERRY SERVICE

1.1 Introduction

This report is an addendum to a report produced by Deloitte & Touche in May 1998 on the Gourock-Dunoon ferry service. The main report produced and evaluated six separate options for the future operation of the service. At that time, Deloitte & Touche were unable to comment on the feasibility of one option in particular, that of an enhanced Gourock-Dunoon service. This was due, among other factors, to a lack of specialist technical information.

Since then, Caledonian MacBrayne (CalMac) has instructed Halcrow Crouch, civil engineers, to conduct a study into the likely costs and technical feasibility associated with this option. This addendum summarises and reviews the information contained in Halcrow Crouch's report, and uses it to revisit the option of an enhanced Gourock-Dunoon service.

1.2 The Original Options

The options previously evaluated can be summarised as follows:

A: Status Quo;

A/L Restrictions lifted from the Gourock-Dunoon operator;

B: Enhanced Gourock-Dunoon service;

C: Gourock-Dunoon service: foot passengers only;

D: Gourock-Dunoon service closed;

E: McInroy's Point-Dunoon: a theoretical, PFI-type model, whereby a new organisation takes over to provide a service between these two points, paying a premium to both existing providers for route rights;

F: Closure of the McInroy's Point- Hunter's Quay service. Again, a premium would be payable to the current operator.

The ranking of the original options is shown overleaf. It can be seen that Option B, an enhanced Gourock-Dunoon service, was ranked as providing the best value for money to the taxpayer, in purely financial terms.

Table 1: Ranking of Original Options

Option

Total Net

Change

 

£000

£000

1. Option B

-1,810

6,024

2. Option F: no premium

-4,572

3,263

3. Option D

-4,586

3,248

4. Option E: low premia

-6,300

1,534

     

5. Option A: status quo

-7,834

0

6. Option C

-8,760

-925

7. Option E: high premia

-12,827

-4,993

8. Option A/1

-17,152

-9,318

Source: Deloitte & Touche report

1.3 Option B

The option for providing an enhanced service between Gourock and Dunoon,

described as Option B in the main report, made the following assumptions:

The Net Present Cost of this option was estimated to be £1.8 million1, a saving of £6 million on the Status Quo.

1.4 Introduction to the Halcrow Crouch Report

Halcrow Crouch has presented the following two options:

Each of these options is described in detail below. The vessels used under both options would have capacity for 40 cars. The report does not provide costs for the vessels.

1.4.1 The Slipway Option

Halcrow Crouch believes that the most suitable location for the slipway is the old stone pier in East Bay, to the north of the existing Dunoon terminal.

Halcrow Crouch also considers that a breakwater is required under this option, in order to reduce "downtime" (the amount of time the service cannot operate due to the sea conditions) to acceptable levels.

Under this option, dredging would be required, initially, and also on an ongoing basis, giving rise to a very large quantity of material (100,000 cubic metres in the first instance). This would either be used as infill for the proposed car parking and car marshalling area or dumped at sea, depending on the quality of the material.

The new site would need to be integrated into the existing road system. Car parking and waiting areas would need to be re-provided.

Finally, foot passengers would board and disembark using the ship's ramp, which Halcrow Crouch considers may be dangerous.

1.4.2 The Terminal Option

In order to avoid significant demolition and reconstruction to the pier, which is listed, the new linkspan would be located at the south end of the existing pier. A new berth and mooring system and strengthening works would be required. Some dredging would also be required and car parking would need to be reprovided.

1.5 Costs

The costs provided by Halcrow Crouch are shown below. The last column gives the original estimate, provided by Argyll & Bute Council, of refurbishing the existing pier terminal, which remains more expensive than the options produced by Halcrow Crouch.

The key point to note is that the original estimate of £600,000 to provide a slipway is now proven by Halcrow Crouch to be extremely optimistic. The slipway option is estimated by Halcrow Crouch to cost £3.8 million in capital works. The terminal options cost between £2.9 to £3.6 million, with the more expensive of these options offering a higher degree of protection from the elements.

Table 2: Capital Works Costs

 

Slipway

Terminal 1

2

3

Argyll & Bute option

 

£000

£000

£000

£000

£000

Slipway/ linkspan2

1,990

1,275

1,850

1,990

1,000

Breakwater

665

     

1,750

Dredging3

800

90

90

90

 

Strengthening works

 

550

550

550

 

Pier refurbishment

       

2,000

New terminal building

200

       

Carparking

 

855

855

855

 

Site investigation

100

100

100

100

 

Contingencies4

       

500

Total

3,755

2,870

3,445

3,585

5,250

Source: Halcrow Crouch/ Argyll & Bute Council

1.6 Non-Financial Evaluation from Halcrow Crouch Report

The table below sets out the arguments made by Halcrow Crouch for and against both the slipway and the terminal options.

Table 3: Advantages and Disadvantages of Slipway versus Terminal

Slipway

Terminal

Pro

Pro

The construction work could be undertaken without disruption to current operations.

The construction work could be undertaken without much disruption to current operations.

 

Other vessels within the fleet are mostly roll-on, roll off and could therefore now service this route if required.

 

The new berth could be used as an overnight berth, creating additional flexibility in the timetable.

 

Pedestrian and vehicular passengers are segregated.

Con

Con

The existing pier would remain entirely unrefurbished, causing an eyesore in central Dunoon. The pier would very probably require some additional works, not yet costed, to make it safe.

The non-strengthened areas of the pier may give problems i.e. this is not a solution which improves and shores up the entire pier.

Pedestrian passengers and cars will disembark via the same mode of exit. The slipway will not have barriers or handgrips at the sides and may be wet.

A ro-ro terminal has higher maintenance and staffing requirements than a slipway.

There will be an ongoing requirement for dredging.

 

Ground conditions are unknown.

 

Source: Halcrow Crouch

The non-financial advantages of the terminal solution as compared to the slipway outweigh the disadvantages, as shown above. However, either solution would leave all or part of the pier in a poor condition, requiring further public investment, and potentially deterring visitors to the town.

Halcrow Crouch concludes that the terminal options all cost less than the slipway option. However, Halcrow Crouch notes that other considerations, including the type of service to be provided, the cost of the service vessels and the type of terminal at the other side (i.e. Gourock) must be examined before any final recommendation regarding Dunoon can be made.

1.7 Revised Net Present Cost of Option B Using Halcrow Crouch Data

The major factor influencing the cost of Option B is not, in fact, the cost of the capital works, although these are substantially (five times) higher than originally forecast. The major factor is the cost base to be used by the Gourock-Dunoon operator. We have, therefore, conducted some sensitivity analysis on this issue, the results of which are summarised below:

Table 4: Revised Net Present Cost of Option B with Halcrow Crouch Data5

   

Slipway

Terminal 1

2

3

Series

 

£000

£000

£000

£000

A

Using existing costs

14,913

13,865

14,407

14,549

B

Using increased costs due to increased market share from lifting of restrictions (Note l.)

25,894

24,847

25,389

25,531

C

Using the reduced cost projections presented by CalMac

4,999

3,951

4,494

4,635

Source: CalMac/Halcrow Crouch/Deloitte & Touche6

Note 1: At present, the operator on the Gourock/ Dunoon route is restricted to an hourly service, with some additional sailings at peak times. Were the operator to run a half-hourly service, this factor by itself is assumed to result in a 3% increase in market share. However, the operator would then be required to dedicate two ships full-time to this route, rather than the present 1.2 ships, resulting in an increase in direct and indirect ship costs.

The Series A calculations shown above rank next to last in the original option. rankings (Table 1), and, therefore, represent poor value for money.

The Series B results are the most costly of all the options considered.

Of the Series C calculations, Terminal. 3 would rank fifth, after the slipway. However, the Terminal 1 and Terminal 2 options would rank first. In other words, they would represent the best possible option for the taxpayer.

However, Halcrow Crouch has stated (Table 3) that terminal options require more staffing than a slipway. This then poses the question of whether or not CalMac could deliver the reduced staff projections on a terminal model.

Table 1 shows that the next best options, after Option B as originally costed, were Options F and D. Option F excluded the premium payable to the current operator at Hunter's Quay, which would be a matter for negotiation. However, it is likely that this would be significant, and would undoubtedly exceed the difference between Option F and Option D.

We would, therefore, have to conclude that Option D, closure of the Gourock-Dunoon service, represents the best option in purely financial terms for the taxpayer.

1.8 Non-Financial Analysis

The following table summarises Option B against the next best options.

Table 5: Advantages and Disadvantages of Option B versus Options D and F

B

Enhanced

Gourock-

Dunoon

service

Advantages

Disadvantages

  • Quicker turnaround time for passengers.
  • Possible (small) positive impact from new ship effect.
  • Possible external benefits for the town of Dunoon.
  • Reinforces and increases structural overcapacity on this route.
  • Costly investment in piers and ships.
  • Continuing operational deficit thereafter;
  • Possibility of a price war subsidised by the taxpayer, with no guarantee of success.
  • Possible disadvantages to Dunoon if the existing pier remains as an eyesore.
  • D

    Closure of

    Gourock-

    Dunoon

    service

    • Structural overcapacity is eliminated.
    • Lowest cost option for the public sector.
    • Possibility of tariff reduction and of the private sector meeting closure costs.
  • Loss of competition, possibly leading to higher tariffs.
  • Higher tariffs may be preventable either by an effective regulatory framework or by renewed competition on the route. However, regulatory framework may be difficult to formulate and to enforce, and competition cannot be guaranteed.
  • No new investment.
  • Possible detrimental effect on the town of Dunoon.
  • Possible concerns over passenger commitment.
  • F

    Closure of

    Hunter's

    Quay-

    McInroy's

    Poinservice

    • Structural overcapacity is eliminated.
    • Superior service quality to Option D.
    • Continues service into Dunoon with possible external benefits for the town of Dunoon.
  • Loss of competition leading to higher tariffs (unless another party took over Hunter's QuayMcInroy's Point).
  • More capacity than Option D.
  • How can it be implemented? e.g. through price war, as in Option B, in which case Gourock- Dunoon operator may be weakened, or through buy-out? Both will be seen as protectionist.
  • Source: Deloitte & Touche report

    This table highlights the central policy issue of whether or not overcapacity on the route is to be addressed. It also questions how the market might react under the various options, and raises possible risks to the consumer, discussed further below.

    Firstly, if an investment totalling £10 million for a new terminal and ships is made in CalMac, does that investment guarantee the company's financial stability on the route for the foreseeable future? The two operators would be offering the marketplace a similar offering. Either they will continue in harmony as before, or else a price war will break out, to the temporary benefit of the service users, but with potentially poor outcomes for the taxpayer. In a worst case scenario, one or other may be forced off the route altogether, i.e. Option B could turn out to have been merely a staging post on the way to Option F or D, but at an additional cost of £10 million.

    Secondly, if such an investment would indeed guarantee CalMac's future, can CalMac, on this basis, be persuaded to set up a separate entity for this route, which would require no further subsidy from the taxpayer?

    Thirdly, if only one operator is on the route, will it raise tariffs unreasonably? If this is deemed to be a real risk, can the user be protected by legislation? Or can it be assumed that another operator will come onto the scene to create competition and thus drive prices down?

    The implementation issues around Option B as originally stated were as follows:

    i. the availability of suitable vessels on the second-hand market, and whether such vessels could technically perform to the projected journey times;

    ii. the likely union reaction to a perceived reduction in service standards, albeit in line with current terms and conditions for the type of vessel now envisaged;

    iii. whether the proposed slipway site is feasible;

    iv. the effect on the town of Dunoon if its existing pier is not used and probably not refurbished;

    V. the outcome of what would effectively be a price war between two similar operators, no longer differentiated by their services;

    vi. Western Ferries' contention that the revenue costs of this option, such as fuel and insurance, had been understated.

    While the Halcrow Crouch report has addressed issue iii., all of the other issues remain live.

    1.9 Conclusion

    Halcrow Crouch has provided firm capital costs for the option of providing an enhanced Gourock-Dunoon service. Halcrow Crouch concluded that the best option in terms of lowest cost and other benefits is to provide a roll~on, roll-off terminal at the south end of the existing pier. This proposal would meet the expressed wishes of Argyll & Bute Council, which believes that any proposal to move the terminal out of the town would have detrimental effects on the town's economy. It would, however, leave the existing pier unrefurbished beyond some strengthening works.

    The costs now projected by Halcrow Crouch are some five times the capital cost shown for this option in the original report. The option, therefore, fails to prove itself the best value for money for the taxpayer, unless radical assumptions are added about the future cost structure of the operation.

    The question then arises as to whether or not CalMac can actually implement such a radically different cost structure. On this point, CalMac has presented no new information. Halcrow Crouch suggests, however, that the preferred option of a roll-on, roll-off terminal would require higher staffing levels than the slipway originally envisaged. This suggests that it will be even more challenging for CalMac to deliver a reduced cost base.

    Our original report identified Option B (enhanced Gourock-Dunoon service) as the best value for money to the taxpayer. Based on the additional information provided by CalMac and its advisers, Halcrow Crouch, we now conclude that Option D, closure of the Gourock-Dunoon service, represents the best value for money option for the taxpayer, in purely financial terms.

    A final decision requires some assumptions to be made about likely market behaviour under different circumstances. The outstanding issues for consideration are:

    < Back to main report

    Footnotes

    1 6% discount rate over a 15 year timescale.

    2 Slipway costs include reclaimed carparking area.

    3 Projected costs for dredging assume that no rock is encountered. There will be an ongoing requirement for dredging, the cost of which is not included above.

    4 Halcrow Crouch figures include an allowance for contingency.

    5 In producing these figures, we have used the same assumptions as before re vessel costs

    6 Additional assumptions made by Deloitte & Touche:

     


    Making It Work Together