< Previous | Contents | Next >
PAN 45 (revised 2002): Renewable Energy Technologies
Wind Power
Introduction
| |
|
36. Wind power is now well established and accepted as a commercial source
of electricity with no production of particulates or harmful gases. The
UK has one of the windiest climates in Europe. Scotland, having a significant
amount of this resource, is well placed to exploit it.
|
| |
|
37. Generating electricity using wind power has
the potential to reduce the amount of electricity from fossil fuel power
stations, thus reducing emissions of harmful gases such as carbon dioxide
(CO2), sulphur dioxide (SO2) and nitrogen oxides (NOx).
For example, in 1999 UK wind farms produced over 0.5 billion units of clean
electricity potentially offsetting over 430,000 tonnes of carbon emissions. |
| |
|
38. This section offers information and advice
on the technologies and characteristics of on-shore wind generators. It
is mainly concerned with larger groupings of wind turbines, referred to
as wind farms. Proposed developments exceeding 50 MW will fall to be determined
under Section 36 of the Electricity Act. However, much of it will apply
equally to smaller scale developments, in particular the issue of visual
amenity. |
Case Study 2 : Hagshaw Hill, Scotlands First Wind
Farm
|

|
Hagshaw Hill wind farm lies
4 km west of Douglas, Lanarkshire and was the first wind farm in Scotland
under SRO1.
It received planning consent in January 1995 and has been operational
since November 1995.
It was developed by Trigen Ltd and is operated by Windfarm Management
Services Ltd on behalf of ScottishPower plc.
26 Bonus 600 turbines.
Rated power - 15.6 MW.
Hub Height - 45m.
Rotor Diameter - 41m.
|
Case study 3 : Isle of Muck Community Wind Energy Project
|
|
| The Isle of Muck wind energy project, officially
opened in August 2000, is intended to provide reliable and cheaper electricity
for the 38 islanders.
Two 26 kW wind turbines harness the windy conditions on the island. When
the wind speed drops below the required level, diesel generators automatically
ensure that the electricity supply is maintained.
The initiative was funded through the local enterprise company, Lochaber
Ltd., the European Partnership, the National Lottery Charities Board and
the Highland Council, with donations from non-islanders, Trusts and the
islanders themselves.
Income from the scheme will cover repair and maintenance and will eventually
fund the replacement of the turbines at the end of their useful life in
about 20 years.
The scheme was developed by ScottishPower Technology (now Ingenco Ltd)
and run by Isle of Muck Power Ltd.
|
The Technology
| |
|
39. The power produced by wind turbines depends on two key factors -
the strength of the wind, and the area swept by the rotor. The energy
produced is strongly dependent on the annual mean wind speed at the site.
The power available increases with the cube of the wind speed. A machine
on a site with a mean wind speed of 6 metres per second will produce less
than half as much energy as the same machine on a site with a mean wind
speed of 8 metres per second. The area swept by the rotor increases with
the square of the rotor diameter, so a machine with a 15-metre diameter
rotor will produce only a quarter of the power of a machine with a 30-metre
diameter rotor. Advances in technology now allow turbines to operate efficiently
at lower wind speeds than previously.
|
| |
|
40. Assessing whether a particular site will harness wind power satisfactorily
entails using historical meteorological data (available from the Meteorological
Office) and information derived from anemometers (on masts, typically
30 metres tall, on a site for about 12 months). The data help to determine
whether or not a site is technically suitable and, if it is, help to identify
the best positions for wind turbines within the site. Other technical
considerations will include an adequate means of vehicular access (capable
of taking articulated vehicles) and the availability of a connection to
the electricity distribution grid.
|
Fig. 2 : Components of a Wind Turbine
|
|
The turbines usually have steel towers supporting the nacelle,
which houses the mechanical machinery and a device known as "the yaw
mechanism", which allows the machine to turn itself towards the prevailing
wind. The majority of rotor blades are made of glass reinforced plastic
or wood epoxy but can be of aluminium or steel. |
| |
|
41. There are essentially two types of wind turbine, vertical and horizontal
axis machines. Within each type there are various technical differences,
the most obvious being the number of blades. Turbines currently preferred,
or likely to be so, in Scotland in the foreseeable future are of the horizontal
axis, three bladed type.
|
| |
|
42. Wind turbines are available in a range of sizes, from small battery
charging units with rotor diameters of less than a metre to very large
turbines with rotor diameters greater than 70 metres rated at several
megawatts.
|
| |
|
43. Current wind power technology is based largely on the considerable
experience in Denmark through several generations of development. Machines
rated between 500kW and 1MW are now commonplace. The technology has now
advanced beyond the 1 to 1.5MW size to 2MW machines, intended originally
for use offshore but now featuring in proposals onshore.
|
Fig. 3 : Examples of Turbine size
|
Location
|
Type
|
Tower height
|
Rotor diameter
|
|
Novar (Highland)
|
Bonus 500
|
35m
|
41m
|
|
Windy Standard (Dumfries & Galloway)
|
Nordtank 600
|
35m
|
37m
|
|
Whitelee (Eaglesham Moor)
Proposed
|
>2.0 MW (type not specified)
|
>70m
|
>80m
|
|
Burger Hill (Orkney)
|
NEG Micon 2.0
|
68m
|
72m
|
| |
|
44. Turbine towers are fixed to a concrete foundation about 7 metres
in diameter whose surface will normally be flush with the surrounding
ground. The land area actually used by the turbines is therefore very
small. On land normally used for agricultural purposes, agricultural use
can continue up to the edge of the foundations.
|
| |
|
45. Wind turbines can be deployed singly, in small groups or in larger
numbers in wind farms. Technical factors, which may influence the size
of a development, include the physical nature of the site, and the capacity
of the local electricity distribution grid. It is likely that the wind
resources of the UK will be harnessed most satisfactorily using a mixture
of different scales of development. While it is likely that larger developments
will continue to be proposed in rural areas, smaller schemes can be expected
on both urban and rural sites.
|
| |
|
46. Grouped turbines need to be positioned, for operational reasons,
so that the separation distance between individual turbines is around
5 -10 rotor diameters. This represents a compromise between compactness,
which minimises capital cost, and the need for adequate separation to
lessen energy loss through wind shadowing from upstream machines. Land
use planning, ground conditions and operational requirements will usually
result in a compromise between maximising energy capture and minimising
visual impact. The improved productivity of the current generation of
wind turbines is largely the result of improved technology (including
better micro-siting methodologies) and higher hub heights.
|
| |
|
47. A wind farm requires a central monitoring system, consisting of a
computer, which supervises the operation of the turbines. This can be
housed in a small building on-site linked to a headquarters off-site.
Most modern wind farms are un-manned, with their operational status regularly
checked through the central monitoring and remote link facility. There
is also likely to be a slender mast with anemometers and wind vanes to
provide control information for the site.
|
Safety Aspects
| |
|
48. A possible but rare source of danger to human or animal life from
a wind turbine would be the loss of a piece of the blade or, in most exceptional
circumstances, of the whole blade. Many blades are composite structures
with no bolts or other separate components. Even for blades with separate
control surfaces on or comprising the tips of the blade, separation is
most unlikely. The build-up of ice on turbine blades is unlikely to present
problems on the majority of sites likely to be developed in the near future.
In those areas where icing of blades does occur, fragments of ice might
be released from blades when the machine is started. However, most wind
turbines are fitted with vibration sensors to detect any imbalance which
might be caused by icing of the blades. This enables the operation of
machines with iced blades to be inhibited.
|
| |
|
49. The possibility of attracting lightning strikes
applies to all tall structures and wind turbines are no different. Appropriate
lightning protection measures are incorporated in wind turbines to ensure
that lightning is conducted harmlessly past the sensitive parts of the nacelle
and down into the earth. |
| |
|
50. Companies supplying products and services
to the wind energy industry operate to a series of international, European
and British Standards. A set of product standards for wind energy equipment
has been developed by the International Electro-technical Commission - IEC
16400. There are a number of British Standards that correspond to it, for
example, BS EN 61400-1: 1995 "Wind turbine generator systems - safety
requirements". |
| |
|
|
Electro-magnetic Interference
| |
|
Communications Systems
|
|
"Approximation of the Laws of the Member States Relating to Electro-Magnetic
Compatibility",
(89/336/EEC)
The European Commission Directive of 3 May 1989
|
|
51. Wind turbines (in common with all electrical equipment, including
those used in the home) do produce electro-magnetic radiation and this
can interfere with broadcast communications and signals. Since a large
number of bodies use communication systems (some commercially sensitive
or of strategic or military importance), it is impossible to obtain a
definitive picture of all the transmission routes across a potential site.
The Radiocommunications Agency (RA), which holds a central register of
all civil radio communications installations in the UK and acts as a central
point of contact, will identify any radio installations in the neighbourhood
of a wind farm site, but will not identify their owners. Although the
RA is obliged to pass on any enquiry to all other interested parties,
who should respond to an application, an applicant for planning permission
would be well advised to make direct contact with any authorities or bodies
which are likely to have an interest. In addition, it may be necessary
to consult the local emergency services, local authority services departments,
the gas and electricity companies.
|
| |
|
Aircraft, Aerodromes and Technical Sites |
| |
|
52. The siting of wind turbines may have implications
for the flight paths of aircraft and airport radar and communications systems.
Major airports and technical sites (civil and military) are "safeguarded"
by Directions made under the Town and Country Planning (General Development
Procedure) (Scotland) Order 1992 (the GDPO). |
|
"Safeguarding of Aerodromes, Technical Sites and Explosives Storage
Areas".
Scottish Executive
Consultation Paper : March 2001
|
|
53. These safeguarding arrangements are currently
under review. New arrangements are required as a result of the Governments
decision that the responsibility for safeguarding civil sites should be
transferred from the Civil Aviation Authority (CAA), in the case of aerodromes,
to the safeguarded aerodromes themselves and in the case of technical sites,
to National Air Traffic Services Ltd. (NATS). The safeguarding of military
airfields and technical sites remains the responsibility of the Ministry
of Defence through Defence Estates. |
| |
|
54. The consultation paper recognises the fact
that the introduction of wind powered generator turbines within the UK can
create certain problems for aviation. In addition to their potential for
presenting an obstacle to air navigation, wind generator turbines can pose
problems for aeronautical radio stations. The rotating blades create electromagnetic
effects, which can degrade the performance of aeronautical systems and cause
incorrect information to be received. The amount of interference depends
on the wind turbines size, shape, construction materials and location.
|
| |
|
55. Although aviation safety is an important
issue, the primary purpose of safeguarding is to ensure that certain aerodromes
can continue to operate at their existing level of activity and that, in
the event of planning permission being granted, levels of operation would
be able to increase without hindrance. This is in recognition of the economic
importance of these aerodromes to Scotland as a whole as well as their significance
to the local economy. |
| |
|
56. Under the proposed new arrangements planning
authorities receiving applications affecting the areas identified in the
(civil) safeguarding maps, will be required to consult the relevant aerodrome
operator or, for en route technical sites, NATS. If the planning authority
proposes not to act on objections, or not to attach conditions requested
by the consultee(s), it must notify the CAA. The CAA will discuss the proposed
development and/or the requested conditions with the consultee(s). If the
CAA considers that the consultee(s) has raised a valid issue, it can request
the Scottish Ministers to call in the application. |
| |
|
57. Following consideration of the consultation
responses, the replacement Direction and associated Circular will be submitted
for confirmation by the Scottish Parliament and further guidance will be
issued thereafter. |
| |
|
58. In the case of a military site, the consultee
is the MoD (Defence Estates). If the planning authority proposes not to
act on objections, or not to attach conditions requested, it must notify
the MoD. Where the MoD considers intervention is necessary, it can request
the Scottish Ministers to call-in the application. |
| |
|
59. The Civil Aviation Authority is responsible
for recording all air navigation obstructions in the UK. This record is
essential for air safety. Full details of obstructions, that is any building
or works extending 91.4 metres or more above ground level, are published
for pilots information and noted on aeronautical maps and charts.
Planning authorities are requested to supply the CAA with information about
approved new development involving obstructions as soon as permission has
been granted. It is normal practice to provide warning lights on any object
which extends 150 metres or more above ground level. |
Case Study 4 : Safeguarding Arrangements for Prestwick Airport
|
A wind farm safeguarding map has been prepared by Prestwick Airport in
conjunction with the Ayrshire Joint Structure Plan Committee and South
Ayrshire Council. The map identifies three areas sensitive to wind farm
development. The three areas seek to safeguard the flight path of planes
using the airport as well as the operation of the navigational and instrument
landing system in the vicinity of the airport. A wider consultation zone
that extends to 40 nautical miles from the airport is also identified.

|
| |
|
60. The Ministry of Defence uses several areas of the countryside for
low flying training. The Hansard extract below indicates the current MoD
position on this issue. Further information on Military Low Flying can
be obtained from the MoD web-site www.mod.uk/issues/lowflying
|
Fig 4 : MoD Position on Wind Turbines in Operational Low Flying Areas
|
In principal the MoD has no objection to wind farms. The UK has
three specially designated Tactical Training Areas (TTA) that are available
for authorised military Operational Low Flying (OLF) training. The three
TTAs are located in Central Wales (LFA7T), North Scotland (LFA14T) and
the border region of northern England / southern Scotland (LFA20T). Within
these areas military fast jet and Hercules aircraft may operate at heights
between 250ft and 100ft. In addition, units make use of these specifically
surveyed areas to conduct specialised night training.
Flying down to 100ft is also authorised over the Electronic Warfare Tactics
Range (EWTR), LFA13. The EWTR is a RAF facility made available to other
NATO countries on a repayment basis, or under other special arrangements.
It is located in the north of England/southern Scotland TTA. In addition
to tactical radar avoidance training, the airspace associated with use
of the EWTR is made available for test and evaluation flying, specialised
night training and some operational low flying training. Low flying within
LFA13 is associated almost entirely with operation of the EWTR.
Conclusions of a study conducted by the RAF Signals Engineering Establishment,
into the Effects of Wind Generators on Radar Performance, were that wind
turbines cause interference to primary surveillance radar and harm the
ability to detect and track aircraft flying over wind farms. Moreover,
the presence of unlit constructions of significant size would be highly
dangerous to aircraft flying down to 100ft.
In the interests of flight safety, the safety of aircrew and members of
the public, it is vital that any hazard to low flying aircraft are minimised.
Any extraneous distraction or possible reduction in external support capabilities,
such as that provided by ground radar, can have a deleterious effect upon
aircraft safety, and thus the safety of aircrew as well as those on the
ground.
It is, therefore, MOD opinion that obstacles in excess of 100ft in height,
unlit by night and with the ability to cause interference to radar, have
the potential to create an acute safety hazard to aircraft engaged in
operational low flying , tactical radar avoidance training, specialised
night flying and test and evaluation flying, however, each case has to
be considered on its merit.
Dr Lewis Moonie MP Parliamentary Under Secretary of State for Defence
(Hansard 22 March 2001).
|
Fig 5 : UK Military Low Flying System

| |
|
61. There may be a particular concern that turbines will interfere with
television reception. Considerable experience has shown that when this
occurs it is of a predictable nature and can generally be alleviated by
the installation or modification of a local repeater station or some cable
connection. The interference effects can also be reduced by local site
plan changes and this possibility should be discussed with the transmitter
operators.
|
| |
|
Proximity to Roads and Railways
|
| |
|
62. Pre-application discussions are advisable with the Scottish Executive
[Road Network Management & Maintenance Division] for developments
in proximity to trunk roads and the local roads authority for all other
publicly maintained roads. This is particularly important for the movement
of large components (abnormal load routing) during the construction period,
periodic maintenance and for decommissioning. Subsequent planning applications
may require consultation with the relevant roads authority as required
by the GDPO. In the case of railway lines, the authorities are Railtrack
(area Civil Engineering) for operational lines and Railtrack Property
Board for non-operational lines.
|
| |
|
63. Although wind turbines erected in accordance with best engineering
practice should be stable structures, it may be advisable to achieve a
set-back from roads and railways of at least the height of the turbine
proposed, to assure safety. Driver distraction may, in some circumstances,
be a consideration. The provision of appropriately sited lay-bys can be
helpful.
|
| |
|
64. Under certain combinations of geographical position, time of day
and time of year, the sun may pass behind the rotor and cast a shadow
over neighbouring properties. When the blades rotate, the shadow flicks
on and off; the effect is known as "shadow flicker". It occurs
only within buildings where the flicker appears through a narrow window
opening. The seasonal duration of this effect can be calculated from the
geometry of the machine and the latitude of the potential site. Where
this could be a problem, developers should provide calculations to quantify
the effect. In most cases however, where separation is provided between
wind turbines and nearby dwellings (as a general rule 10 rotor diameters),
"shadow flicker" should not be a problem.
|
| |
|
65. Well designed wind turbines are generally quiet in operation. The
table below gives an indication of the noise generated by wind turbines
compared with other everyday activities.
|
Fig 6 : Indicative Noise Levels
|
Source / Activity
|
Indicative noise level dB(A)
|
|
Threshold of pain
|
140
|
|
Jet aircraft at 250m
|
105
|
|
Pneumatic drill at 7m
|
95
|
|
Truck at 30mph at 100m
|
65
|
|
Busy general office
|
60
|
|
Car at 40mph at 100m
|
55
|
|
Wind farm at 350m
|
35-45
|
|
Quiet bedroom
|
35
|
|
Rural night-time background
|
20-40
|
|
Threshold of hearing
|
0
|
| |
|
66. There are two quite distinct types of noise sources within a wind
turbine. The mechanical noise produced by the gearbox, generator
and other parts of the drive train; and the aerodynamic noise produced
by the passage of the blades through the air. Since the early 1990s there
has been significant reduction in the mechanical noise generated by wind
turbines and it is now usually less than, or now of a similar level to,
the aerodynamic noise. Aerodynamic noise from wind turbines is generally
unobtrusive; it is broad band in nature and in this respect similar to,
for example, the noise of wind in trees.
|
| |
|
67. Wind generated background noise increases with wind speed, and at
a faster rate than wind turbine noise increases with wind speed. The difference
between the noise of the wind farm and the background noise is therefore
liable to be greatest at low wind speeds. Varying the speed of the turbines
in such conditions can if necessary, reduce the sound output from modern
turbines.
|
| |
|
68. The Report, "The Assessment and Rating of Noise from Wind
Farms", describes a framework for the measurement of wind farm
noise and gives indicative noise levels thought to offer a reasonable
degree of protection to wind farm neighbours, without placing unreasonable
restrictions on wind farm development or adding unduly to the costs and
administrative burdens on wind farm developers or planning authorities.
The report presents a series of recommendations that can be regarded as
relevant guidance on good practice.
|
Fig 7 : Recommended Good Practice on Controlling Noise from Wind
Turbines
From : "The Assessment and Rating of Noise from
Wind Farms" (ETSU for DTI 1996).
- The current practice on controlling wind farm noise by the application
of noise limits at the nearest noise-sensitive properties is the most
appropriate approach;
- Noise limits should be applied to external locations and should apply
only to those areas frequently used for relaxation or activities for
which a quiet environment is highly desirable;
- Noise limits set relative to the background noise are more appropriate
in the majority of cases;
- Generally, the noise limits should be set relative to the existing
background noise at the nearest noise-sensitive properties and that
the limits should reflect the variation in both turbine source noise
and background noise with wind speed;
- It is not necessary to use a margin above background noise levels
in particularly quiet areas. This would unduly restrict developments
which are recognised as having wider national and global benefits. Such
low limits are, in any event, not necessary in order to offer a reasonable
degree of protection to wind farm neighbours.
- Separate noise limits should apply for day-time and for night-time
as during the night the protection of external amenity becomes less
important and the emphasis should be on preventing sleep disturbance.
- Absolute noise limits and margins above background should relate to
the cumulative effect of all wind turbines in the area contributing
to the noise received at the properties in question. Any existing turbines
should not be considered as part of the prevailing background noise.
- Noise from the wind farm should be limited to 5dB(A) above background
for both day- and night-time, remembering that the background level
of each period may be different.
- The LA90,10min descriptor should be used for both the background
noise and the wind farm noise, and that when setting limits it should
be borne in mind that the LA90,10min of the wind farm is
likely to be about 1.5-2.5dB(A) less than the LAeq measured
over the same period. The use of the LA90,10min descriptor
for wind farm noise allows reliable measurements to be made without
corruption from relatively loud, transitory noise events from other
sources.
- A fixed limit of 43dB(A) is recommended for night-time. This is based
on a sleep disturbance criteria of 35dB(A) with an allowance of 10dB(A)
for attenuation through an open window (free field to internal) and
2dB(A) subtracted to account for the use of LA90,10min rather
than LAeq,10min.
- Both day- and night-time lower fixed limits can be increased to 45dB(A)
to increase the permissible margin above background where the occupier
of the property has some financial interest in the wind farm.
- In low noise environments the day-time level of the LA90,10min
of the wind farm noise should be limited to an absolute level within
the range of 35-40dB(A). The actual value chosen within this range should
depend upon; the number of dwellings in the neighbourhood of the wind
farm; the effect of noise limits on the number of kWh generated; and
the duration of the level of exposure.
- For single turbines or wind farms with very large separation distances
between the turbines and the nearest properties, a simplified noise
condition may be suitable. If the noise is limited to an LA90,10min
of 35dB(A) up to wind speeds of 10m/s at 10m height, then this condition
alone would offer sufficient protection of amenity, and background noise
surveys would be unnecessary.
|
Power Lines
| |
|
69. Power lines connecting the individual turbines to the on-site substation
will be underground. To avoid visual confusion, routing and design of
power lines, connecting the wind farm substation to the electricity distribution
system, will require sensitive treatment (see paragraph
28).
|
Siting in the Landscape
| |
|
70. In order to minimise wind speed variations, commercial wind farms
need to be located in areas of relatively smooth and rounded relief. They
also require ready access to the electricity transmission and distribution
system unless they are intended solely for private use. The current generation
of turbines is capable of operating at lower wind speeds than previously
which has the effect of increasing the types of areas (and landscapes)
that may attract developer interest. Public concern over the visual impact
of past (and many current proposals) has been a recurring feature. Experience,
following construction, suggests that much of the fear is unnecessary.
It is, nevertheless, an issue that continues to need to be addressed.
|
Case study 5 : Public Attitudes Towards Wind Farms in Scotland
| This research examined
the attitudes of local populations towards the four operational wind farms
in Scotland (Hagshaw Hill, South Lanarkshire; Windy Standard, Dumfries and
Galloway; Novar, Highland; and Beinn Glas, Argyll and Bute). The major aim
of the research was to examine how residents feel about the existence and
proximity of their local wind farm. An important objective was to identify
whether, and to what extent, residents views of wind farms are based
on actual experience or perception formed through the media, word of mouth
or other sources.
Respondents were generally positive about wind farms. Those who lived
nearest a wind farm were more likely to provide positive responses when
asked about the wind farm than those in the other areas. For example,
while 67% of respondents overall said that there was something they liked
about the wind farm, this proportion increased to 73% of those living
in the area closest to the wind farm.
The proportion of respondents who had anticipated problems prior to the
development (40%) was far higher than the proportion who actually experienced
problems after the development (9%). Actual noise caused by the turbines
or the visual impact of the wind farm did not feature as issues for the
majority of respondents.
Public Attitudes Towards Wind Farms in Scotland.
Scottish Executive Central Research Unit. 2000
|
| |
|
71. Scotland has a variety of landscapes. Some will be able to accommodate
wind farms more easily than others, on account of their landform and relief
and ability to limit visibility. Some are highly valued for their quality.
There are no landscapes into which a wind farm will not introduce a new
and distinctive feature. Given the Scottish Ministers commitment
to addressing the important issue of climate change and the contribution
expected from renewable energy developments, particularly wind farms,
it is important for society at large to accept them as a feature of many
areas of Scotland for the foreseeable future.
|
| |
|
72. This is not to suggest that areas valued for their international
or national landscape and nature conservation interest will have to be
sacrificed. Nor that elsewhere, attempts to lessen the impacts by integrating
the development into the surrounding landscape would not be worthwhile.
On the contrary, it emphasises the need for account to be taken of regional
and local landscape considerations. Development that has been carefully
sited and tied into the surrounding landscape will still be visible but
the impact will be less than had this effort not been made and the development
left less well related to its surroundings.
|
| |
|
73. The landscape and visual impact of wind turbines is influenced by
:
-
design and colour;
-
access tracks; and
|
| |
|
74. The capacity of the landscape to accommodate wind farm development
depends on two considerations :-
- the degree of impact the development will have on the existing character
of the landscape; and
- the extent to which this impact can be modified and reduced by design.
The ability of the landscape to absorb development depends on careful
siting, the skill of the designer, and the inherent characteristics of
the landscape such as landform, ridges, hills, valleys, and vegetation.
|
| |
|
75. A cautious approach is necessary in relation to particular landscapes
which are rare or valued, such as National Scenic Areas and proposed National
Parks and their wider settings. Here, it may be difficult to accommodate
wind turbines without detriment to natural heritage interests. In a regional
context care should also be exercised within Areas of Great Landscape
Value and Regional Parks. Other landscapes are not especially valued and
a significant change in some landscapes may be considered acceptable.
For example, areas recovering from past degradation, such as those semi-rural
areas of the central belt affected by historic mineral extraction, may
be appropriate areas to accommodate wind farm development.
|
| |
|
76. Scottish Natural Heritage has carried out a comprehensive national
programme of Landscape Character Assessment. These assessments cover all
of the council areas of Scotland and broadly define the variety of Scotlands
landscape types. While not directed specifically at potential wind farm
developments, they identify landscape characteristics that may be sensitive
to wind farm development. Within such broad areas there will be areas
of varying landscape characteristics with different implications for development.
|
| |
|
77. Three pilot projects are being undertaken by SNH, in conjunction
with the planning authorities in Argyll & Bute, Highland and Ayrshire
and Lanarkshire. These will assess the landscape capacity to accommodate
wind farm developments and are intended to inform the preparation of development
plan policies and the possible identification of areas of search.
|
| |
|
78. Turbines in wind farms are likely to be tall, frequently located
in open land, and therefore likely to be highly visible. Domestic turbines
will be smaller. It will normally be unrealistic to seek to conceal them.
Developers should seek to ensure that through good siting and design,
landscape and visual impacts are limited and appropriate to the location.
The visual effect will be dependent on the distance over which a wind
farm may be viewed, whether the turbines can be viewed adjacent to other
features, different weather conditions, the character of the development
and the landscape and nature of the visibility. The following is a general
guide to the effect which distance has on the perception of the development
in an open landscape.
|
Fig 8 : General Perception of a Wind Farm in an Open Landscape
| |
Perception
|
|
Up to 2 kms
|
Likely to be a prominent feature
|
|
2-5 kms
|
Relatively prominent
|
|
5-15 kms
|
Only prominent in clear visibility - seen as part of the wider landscape
|
|
15-30 kms
|
Only seen in very clear visibility - a minor element in the landscape.
|
| |
|
79. The visual impact of wind farms will be affected by their siting
and layout in relation to local land form and landscape characteristics,
and the qualities of the specific site, as well as by the number of turbines.
Different layouts will be appropriate in different circumstances. For
example, grouped turbines can normally appear acceptable as a single,
isolated feature in an open, undeveloped landscape, while rows of turbines
may be more appropriate in an agricultural landscape with formal field
boundaries. Although wind farms may be complex, they should not appear
confusing in relation to the character of the landscape. Ideally they
should be separate from surrounding features to create a simple image.
The design of each development must be appropriate to its site.
|
| |
|
80. The style and colour of turbines may also be relevant. Experience
suggests that solid towers appear less complex than lattice and tapering
towers are generally regarded as being more elegant than cylindrical.
In terms of colour, white or off-white is generally preferred, but other
colours may be acceptable in appropriate circumstances. A semi-matt surface
is required to reduce the reflection of light. However, colour choice
can not be a substitute for good siting and design.
|
| |
|
81. Ancillary elements also need to be fully addressed, as their impact
can often be as significant as those of the turbines. Access tracks should
be routed and designed to minimise both visual and habitat impacts. This
can be minimised by careful route selection, which takes account of layout
and appropriate surfacing material together with the impact of cuttings,
embankments and drainage channels. Managing problems of erosion and providing
for reinstatement of vegetation along the track is essential. Power lines,
fencing, buildings and anemometer masts should be located and designed
in a way which minimises clutter.
|
|
"Guidelines for Landscape and Visual Impact Assessment"
published by SPON (1995) on behalf of the Landscape Institute and the
Institute of Environmental Assessment (now the Institute of Environmental
Management and Assessment). A second Edition is due in March 2002.
|
|
82. There are a number of techniques which may be used to inform visual
assessment of a proposed development :
- a zone of visual influence map will show where a wind farm
may be seen from;
- viewpoint analysis based on key viewpoints throughout the surrounding
area;
- computer generated wireline diagrams will indicate how wind
turbines will appear from specific viewpoints;
- photo- and video montages are images whereby an impression
of a proposed development is superimposed upon an actual photograph
or video of the proposed site.
All of these have strengths and limitations.
|
| |
|
83. In comparison with other, well-established, forms of development
in the countryside, wind turbines are relatively unfamiliar, prominently
vertical and have the significant characteristic of movement. Individually
or in groups, they will be distinctive features in the landscape. The
visual impact of wind turbines must be assessed with these characteristics
clearly in mind.
|
|
"European Protected Species, Development Sites and the Planning
System - Interim Guidance for Local Authorities on Licensing Arrangements".
Scottish Executive Environment Group Oct 2001
|
|
84. Experience indicates that many bird species and their habitats are
unaffected by wind turbine developments and the impact of an appropriately
designed and located wind farm on the local bird life should, in many
cases, be minimal. To date, the most common concern has been the risk
of "bird strike" i.e. birds flying through the area swept by
the blades and being hit, causing injury or death. This will depend on
a number of considerations such as, the particular species and numbers,
the nature of the bird flight and any relevant seasonal patterns. Most
birds in flight can be expected to take action to avoid obstacles but
different species will vary in their reaction (see Fig.9).
However, some areas in Scotland are important for a variety of bird species
protected under the EU and UK legislation (SPAs, SACs and SSSIs) These
could represent potential constraints to wind farm development. As indicated
in NPPG 6 the importance of complying with international and national
conservation obligations must be recognised and wind farms should not
adversely affect the integrity of designated sites. Protected species,
such as eagles and hen harriers, occupy many areas outwith designated
sites and are protected across Scotland. These factors have to be considered
against the positioning and size of turbines, including the size of the
area swept by the blades in relation to the air space used by the birds
in the vicinity of the development.
|
| |
|
85. In addition, under the EC Habitats Directive, other species or habitats
of special interest may be present. For example montane and bog habitats
can be adversely affected by track construction unless attention is paid
to minimising impact on the hydrology of the site. They may also be affected
by any changes in land management which may be brought about as a consequence
of improved access.
|
| |
|
86. Developers should instruct their ecological advisers to enter into
early discussions with SNH about the presence and importance of species
and habitats in and around their proposed development site. Discussions
should assess how serious the problems are and the scope for taking ameliorative
action or seeking alternative sites nearby.
|
| |
|
87. SNH, in consultation with the British Wind Energy Association (BWEA),
is preparing a "Methodology for assessing the effect of wind farms
on ornithological interests". In addition ETSU have published
a report "Cumulative effects of wind turbines" in which
Section 3 deals with "Cumulative effects on birds". Both will
be of use to developers when assessing the potential impact of proposed
developments on bird life. Royal Society for the Protection of Birds (RSPB),
World Wildlife Fund (WWF), English Nature and BWEA have also published
"Wind Farm Development and Nature Conservation". While
intended for an English audience, it contains material that is equally
relevant in a Scottish context.
|
| |
|
88. The risks of disturbance to bird species during construction and
operation of the wind farm is also an important consideration. For some
species this is of greater potential significance than collision mortality.
|
|
Fig 9 : Examples of Bird Species Sensitivity
|
|
Golden Eagles
|
Golden eagles, during the breeding season, tend to centre much of their
activities within 2-3km around the nest site and on ridges nearby. Hence
terrain close to the nest site will tend to be most sensitive to disturbance
from / collision with developments. Many areas will have only one pair
but some may have several. In areas with many adjoining eagle pairs, the
impact of an occasional casualty on the eagle population may be less significant
than in areas with only one or few pairs. (See Case
Study 6)
|
|
Geese & Swans
|
The risks to barnacle geese, whitefront geese and whooper swans
are likely to arise mainly through flights between feeding areas and between
feeding and roosting grounds. Distances involved are highly variable between
species and locality. Geese fly in typical V skeins and their ability
to avoid obstacles depends on the alertness of the lead bird. It is likely
to be more difficult to accommodate developments in areas which contain
nationally or internationally important concentrations of birds, than
areas where these birds are present but for which important concentrations
are not recorded.
|
|
Harriers & Owls
|
Where hen harriers and short-eared owls are present, only
a small percentage of the terrain is likely to offer conflicts between
development and the birds. Both species make use of a wide range of moorland
habitats, tending to nest in areas with long heather and hunt over rough
grassland and flush-dominated plains. However, there is considerable variation
in habitat use by these species. Male hen harriers are probably most vulnerable
to collision while displaying, and inexperienced juveniles may find it
difficult to avoid turbine blades.
|
|
Divers
|
Black and red throated divers are potentially vulnerable where
a development might impede flight between breeding and feeding areas.
Black-throated divers tend to nest in large lochs and feed in these
or in nearby lochs. They fly low as they take off from lochs. The identification
of flight lines requires investigation when development is proposed. Red-throated
divers nest in small lochs and lochans. They tend to feed in the sea,
so flightlines are more likely to be predictable and occur on the seaward
side of these nesting areas. Divers appear to have relatively poor manoeuvrability.
Flight lines, around nesting and when approaching and leaving feeding
areas, tend to be low and impacts with developments are possible within
a radius of 0.5 to 1.0 km from such areas.
|
Case Study 6 : Beinn an Tuirc, Safeguarding Eagles by Habitat
Management
|

|
| Beinn an Tuirc wind farm, situated on the west coast of
Scotland in Kintyre will be one of the most productive wind farms owned
by ScottishPower. However, the site forms part of the territory for a pair
of golden eagles, a species listed on Schedule 1 of the Wildlife and Countryside
Act 1981 and Annex I of the EU Directive on the Conservation of Wild Birds.
When the wind farm was being developed and before the planning application
was made, it was clear that the golden eagles were occupying a marginal
territory where food resources were scarce. The birds have only bred successfully
twice in the last 15 years and this is probably due to massive declines
in prey availability. This is thought to be closely linked with a twelve
fold increase in the forest area over the last 12 years.
The proposed wind farm site was not an important hunting area for the
golden eagles although the birds had been seen in the vicinity at certain
periods during the year. It was decided that although the risk of an eagle
colliding with a wind turbine was minute, the development would further
stress an already struggling pair of eagles. To mitigate against the possibility
of an eagle collision but more importantly, to improve the overall situation
for the golden eagles, ScottishPower developed an innovative habit management
plan to increase prey availability within the eagle territory. The scheme
was developed by ScottishPowers consultant ornithologist and is
managed by a full time ranger who reports to the Habit Management Committee
with representatives from SNH, RSPB and Argyll & Bute Council. Large
scale removal of immature plantation, forestry, heather management and
the creation of prey "hotspots" will not only help to shift
eagle activity away from the wind farm but will make the eagle territory
sustainable in the longer term.
|
Cumulative Effects
| |
|
89. The cumulative impact of a number of neighbouring developments may
also be a relevant consideration. The nature and character of the location,
and the landscape in which a development is located, will in part determine
the acceptability or otherwise of siting proposals in proximity to each
other.
|
|
"A Guide to Assessing the Cumulative Effects of Wind Energy Development"
W/14/00538/REP
ETSU 2000
|
|
90. A number of factors have influenced the current geographic distribution
of wind farm proposals in Scotland, for example :
- the distribution of the viable wind resource;
- technical and economic constraints to the viability of exploiting
different wind speeds;
- electricity grid access constraints;
- protected areas;
- planning policy.
These have tended to focus developments in a relatively limited number
of areas. However there have been few instances where cumulative effect
has had to be addressed but with more proposals coming forward this could
change.
|
|
"Beinn An Tuirc :
Assessment of Effects on the Landscape Resource and on Visual Amenity".
Special report by Turnbull Jeffrey Partnership for ScottishPower June
1998
|
|
91. The cumulative effects of wind farm development can arise as the
combined consequences of:
- an existing wind energy development and a proposed extension to that
development;
- proposals for more than one wind energy development within an area;
- proposal(s) for new wind energy development(s) in an area with one
or more existing development(s);
- any combination of the above.
In assessing cumulative effects, it is unreasonable to expect this to
extend beyond schemes in the vicinity that have been built, those which
have permissions and those that are currently the subject of undetermined
applications.
|
Decommissioning, re-equipping and replacement
| |
|
92. Wind turbines can be decommissioned and sites cleared and restored
easily and rapidly. This should be covered in the conditions and/or legal
agreement accompanying the consent and will be triggered by the expiry
of the consent or in the event of the project ceasing to operate for a
specified period. Planning authorities should satisfy themselves that
funding for decommissioning will be available when required.
|
| |
|
93. It is likely that the duration of the consent will be linked to the
expected operational life of the turbines. However during this period,
proposals may be forthcoming to extend the life of the project by re-equipping
or to replace the original turbines with new ones. While there are obvious
advantages in utilising established sites, such cases will have to be
determined on merit and in the light of the then prevailing policy and
other relevant considerations.
|
< Previous | Contents | Next > |