Getting 'IT'
Right
A Thematic Inspection
3. Programme and Project Management
Programme Management
3.1 HM Inspector expected to find in each police
force a programme management team (probably a group chaired by a chief officer) to oversee
progress on all current IS/IT projects and allocate resources to these projects. In
practice, he found little evidence that projects were being managed within a formal
structure. There was evidence of major decisions being taken without consideration of the
detailed options, risks and implications of these decisions. Decisions tended to be taken
following informal discussion which seldom codified the reasons for decisions and
therefore rarely allowed a judgement to be taken on whether the decisions were correct, or
indeed whether they were implemented in the intended way.
| Recommendation 5
It is
recommended that each force and common service should put in place a programme management
team, chaired by a senior user, to consider the organisations entire programme of
IS/IT projects, empowered to give the go-ahead to new projects, and allocate (and
re-allocate) resources to these projects within the framework of the annual business plan. |
Project
Initiation
3.2 HM Inspector found few examples of thorough
evaluation of proposals to develop new IS/IT systems or make changes to existing systems.
Typically, forces gave approval to projects on the basis of preparation of a report on
each individual project, which was submitted through the chain of command for approval by
senior management. But these approvals were often given in isolation, with the result that
the IT Department was presented with work in the form of a series of unprioritised bids.
Understandably, they tended to proceed with the projects whose users were most vociferous
in pressing their cases - which might or might not be those which were most important to
the force.
3.3 Moreover, HM Inspector was disturbed to discover
that projects were initiated without a proper option appraisal. Good practice did exist.
For instance, HM Inspector commends the investment appraisal for a SCRO project, carried
out with the assistance of the Central Computing and Telecommunications Agency. It is
good practice to follow the advice of the Central Computing and Telecommunications Agency
(CCTA), since they have wide experience of managing public sector computer projects.
The publications listed in paragraph 1.13 are readily available and are based on
principles which are straightforward to apply. They can be supplemented if necessary by
assistance from CCTA themselves or by consultants approved by them.
3.4 HM Inspector concludes that each new computer
project, or significant amendment of an existing computer system, should be approved only
on the basis of an appraisal carried out in line with the CCTA guidance. In particular,
that appraisal should:
- be based on the business needs of the organisation;
- consider viable options (including the status quo) for
meeting these business needs - not necessarily by the use of a computer system;
- cost each option over its total life span, discounting
these costs to present-day values;
- assess the benefits of each option, in meeting the
organisations business needs - against costs calculated over the life span of the
project and discounted to present-day values;
- identify the technical and financial resources
necessary to deliver the option, paying particular attention to the need for skilled
staff;
- take account of all costs and benefits - financial and
non financial, measurable and non-quantifiable;
- identify all the risks associated with the project,
and assess their effects on the project.
3.5 The resulting investment appraisal document,
containing a clear recommendation, should be submitted to the Programme Management Team
(see Recommendation 5) for a decision. The recommendation should state clearly what the
recommended option will deliver, when - and at what cost (in financial, staffing and other
terms).
| Recommendation 6
It is
recommended that an option appraisal be carried out for each significant proposed
investment in IS/IT, including an investment appraisal based on the costs and benefits of
various ways of achieving the business aims over the life span of the project, and
specifying the risks associated with it. No significant investment should be approved
without such a business case. |
Standards of
Business Analysis
3.6 Once a project has been given the go-ahead, it is
necessary to analyse the business need in detail in order to translate the business
proposal into a workable system.
3.7 HM Inspector found that the absence of standards
in many of the IS/IT strategies was accompanied by an absence of standards in systems
analysis and documentation and shortcomings in many technical and resource plans.
3.8 In many of the organisations inspected, there was
no evidence whatever of business analysis taking place. HM Inspector was encouraged to see
a few organisations adopting a structured approach (typically SSADM) but had some doubts
about whether it was used comprehensively (because it proved difficult to identify option
papers produced for consideration and approval by the client - which is a function of
level 3 of SSADM).
3.9 The quality of technical and resource plans was
similarly varied. In some organisations, they did not exist. Organisations relied instead
on technical plans provided by their suppliers. These plans were, however, not
comprehensive, because they did not cover the activities which were carried out by the
organisations themselves - and HM Inspector would expect to find the equivalent technical
and resource plans being produced by organisations for these activities.
Project Management
3.10 All forces use some form of project management
but in some cases it was apparent that essential elements were not being implemented and
in particular progress reports to Project Boards left much to be desired.
3.11 The standard of project documentation was
generally disappointing. In many cases, critical project documents, including project
initiation documents, highlight reports to project boards, minutes of meetings, simply
could not be produced. Of those documents which were produced the quality varied, many
were undated and few included any kind of version control, making project control and
review impossible.
Post Implementation Reviews
3.12 Few forces and other policing organisations were
making use of post implementation reviews - to check, once the project had been completed,
that it had met the aims which were specified at the outset, within the allocated time and
budget. The review allows lessons to be learned from completed projects, which can be
applied to current and future projects.
3.13 HM Inspector found a general lack of awareness
that a post implementation review, undertaken or at least overseen independently of the
project implementation, can contribute to the success of future project. But HM Inspector
saw one high-quality post implementation review following the successful implementation of
a multi-million pound project. The review had been carried out by consultants and was a
substantial document - appropriate to an investment of that scale. But lessons can also be
learned from smaller projects by a simpler review, carried out in-house. At present, post
implementation reviews would be hindered by the absence of a statement of expected costs,
benefits and timescales specified before the project is started. But as, in line with
previous recommendations, such information becomes more widely available, it is good
practice for an independent post implementation review to be carried out to check that
each project achieves its aims, within budget and timescale, and that lessons are learned
and applied to other projects.
Conclusion
3.14 HM Inspector found scope for considerable improvement
in programme and project management. That does not necessarily mean more bureaucratic
procedures: the principles of the PRINCE methodology recommended by CCTA are
straightforward to apply. But HM Inspector considers that much firmer discipline should be
applied throughout the Scottish police service to the whole process of planning, project
initiatives and project management. The recommendations, with those in the previous
Section, will ensure that resources diverted from front-line policing to install computer
systems yields the maximum benefits for users, freeing police officers and support staff
from tasks which can be carried out by computers - and thus maximising the resources which
can be devoted to front-line policing and ensuring that police officers are provided with
the information which is necessary for them to tackle demands effectively and efficiently. |