River Crossings and Migratory Fish: Design Guidance
< Previous | Contents | Next >
PART 3 DESIGN
5 DESIGN REQUIREMENTS FOR FISH PASSAGE
Introduction
5.1 Consideration of the life history, migratory behaviour and swimming
ability of various types and sizes of fish, together with a review of where
fish passage problems have arisen, indicates that the following factors must
be acceptable for successful fish passage:
- adequate depth of water at the time of passage;
- appropriate water velocity;
- adequate resting places above and below the structure; and
- no physical obstructions to passage.
Discussion
5.2 Attention to the above design factors is only required where a culvert
installation modifies the stream profile. If the preferred option is for a bridge
or a large culvert with effective retention or re-creation of the stream channel
features these considerations need not apply (see Chapter
6).
5.3 It is not necessary for installations to be passable to fish at all
times. Most upstream migrations take place at flows well above the dry-weather
(Q95) flow, and well below the peak discharges. Peaks of discharge are generally
short-lived events in smaller watercourses and a short delay in passage periods
need not be critical.
5.4 In planning fish passage facilities it is important to consider the
range of flows over which conditions for fish passage are to be optimised -
the "passage design flow range". Good passage conditions should be provided
during the period when fish are migrating in a particular area.
5.5 The appropriate DSFB (2) or other fisheries
experts can provide advice on the passage design flow range, as it will vary
between sites and fish species. Generally, there will be a shorter window of
time over which fish passage can occur in small streams than in larger ones.
A suggested "passage design flow range" for checking for excessive velocity
at high flows and inadequate water depth at low flows is that lying between
the 10 percentile and 90 percentile of normal flows respectively (the flows
which are exceeded 10% and 90% of the time).
Design Criteria
5.6 The design criteria listed in Table 5.1 for river-crossing structures
to enable successful salmonid passage have been determined from a combination
of biological data and other guideline publications. Key references are included
in a Technical Report which is available to accompany this guidance document.
5.7 Small fish are able to exploit boundary layers close to culvert walls,
where the water velocity is significantly lower than that in the central section
of the water flow. For this reason the criteria presented in Table 5.1
for brown trout are likely to allow passage for much of the time of smaller
fish and weaker swimmers such as eel and lamprey. In most situations no special
consideration of other species is necessary. However, where other species, especially
smaller fish and weaker swimmers, are of specific conservation interest, more
stringent design criteria may be justified. Such cases are beyond the scope
of this document, and specialist advice should be sought.
Table 5.1 Design Criteria for Salmonids
|
|
Notes
|
Brown Trout 15cm
|
Sea Trout 25cm to 50cm
|
Salmon > 55cm
|
|
Maximum Water Velocity:
|
a,b,c
|
|
|
|
|
Culvert Length <20m
|
|
1.25m/s
|
1.6m/s
|
2.5m/s
|
|
Culvert Length 20-30m
|
|
1.0m/s
|
1.5m/s
|
2.0m/s
|
|
Culvert Length >30m
|
|
0.8m/s
|
1.25m/s
|
1.75m/s
|
|
Minimum Diameter of Pipes
|
|
0.3m
|
0.3m
|
0.5m
|
|
Minimum Depth of Water
|
d
|
0.1m
|
0.15m
|
0.3m
|
|
Maximum Water Level Drop
|
e
|
0.2m
|
0.3m
|
0.3m
|
|
Trash Screen (minimum gap)
|
f
|
0.05m
|
0.1m
|
0.2m
|
5.8 Resting areas immediately downstream of and upstream of the culvert
are desirable with the requirements being:
- an area of water of adequate depth (at least 30cm for trout, 45cm for salmon);
- an area of deeper water with adequate cover for resting;
- rocks or overhanging vegetation; and
- moderate flow conditions (well within the cruising speed of the fish (3)).
5.9 Resting pools within the culvert are not recommended as they are likely
to collect silt and debris and would be difficult to maintain.
6 DESIGN CONSIDERATIONS
Introduction
6.1 This chapter introduces the steps for ensuring that fish passage considerations
are integrated into the design process for in-river structures.
Culvert Conceptual Design
6.2 It is recommended that the conceptual design of a culvert is carried
out using the process described in the Culvert Design Guide (CIRIA, 1997). The
guide identifies that the conceptual design takes into account the relevant
importance of hydraulic, environmental, operational and economic performance
criteria. If the Culvert Design Guide is used with the guidance set out below
it will be possible to ensure that issues of fish passage are adequately addressed
in the culvert design process.
6.3 During the earlier stages of the road project design, initial data will
have been collated such as the fish species which may be affected, the passage
design flow range, the design flood return period etc (see
Chapter 4). At the initial stage of the conceptual design, calculations
of trial sizes for the culvert barrel size will have been undertaken and various
data collated including the design flow rate, gradient, barrel roughness and
culvert length.
6.4 This is the stage when the designer must check that the predicted hydraulic
conditions in the structure at critical times are appropriate for any fish species
which will migrate through it (see Section 5.5).
6.5 The main parameters to be considered in the calculation of flow velocity
and water depth are culvert slope, length and the Manning n value (roughness)
for the culvert invert material being considered. These parameters together
with the culvert size can be adjusted through iteration to develop an economical
solution which allows both for fish passage and flood flow conditions.
6.6 The criteria which will allow the successful passage of fish are provided
in Chapter 5.
6.7 The suggested approach is to review a number of alternative culvert
designs and check which will ensure the free passage of fish.
6.8 The alternatives should be considered in the order listed below. If
the basic culvert in Case 1 is found to be unsatisfactory for fish passage then
the designer considers Case 2, etc until a satisfactory design is achieved.
(i) Case 1: Culvert barrel with dimensions derived for the passage of flood
flows.
(ii) Case 2: Culvert with a depressed invert to allow the inclusion of stream
bed material within the barrel. For circular and pipe arch culverts this will
result in the specification of an increased diameter for the barrel. Similarly
for rectangular shaped culverts the height of the box section will need to be
increased to accommodate both flood flows and the bed material.
(iii) Case 3: Provision of a bottomless arch culvert to retain the natural
stream bed.
(iv) Case 4: Provision of a low flow channel within the culvert invert,
resulting in increased structural dimensions as identified in Case 2.
(v) Case 5: Provision of baffles within the culvert (particularly appropriate
for steeply sloping culverts), resulting in increased structural dimensions
as identified in Case 2.
6.9 In Chapter 3 common problems which
affect the passage of fish have been described. Other factors which will help
avoid these problems and should be considered during conceptual culvert design
include the following:
(i) Matching culvert gradient with the stream gradient where possible to
minimise changes in stream hydraulics which may affect fish passage.
(ii) The provision of outlet pools as a means of raising tailwater levels
and avoiding extensive erosion protection works at the outlet. These pools provide
resting places for migratory fish prior to negotiating the culvert. Inlet resting
pools may also be required in certain situations.
(iii) When a multi-pipe structure is used ensure at least one barrel is
set at sufficiently low level to ensure an adequate depth of water for fish
passage under low flow conditions.
(iv) Designing inverts to allow for both the free passage of fish and the
passage of other animals (otters etc).
(v) Maintaining appropriate conditions for fish passage through long culverts.
(Long culverts do not in themselves represent an increased obstruction to fish
as long as appropriate conditions for fish passage are maintained throughout.)
Lack of light in a culvert does not appear to influence fish passage.
(vi) The design of a trash screen (if this cannot be avoided) should ensure
fish passage is not impeded.
(vii) Approach conditions should be within the cruising ability of the fish
in the watercourse.
Bridges
6.10 The design of river bridges and their foundations should accord with
BA 59/94 in Volume 2 of the DMRB. This gives advice in the consideration of
scour protection of in-river piers and abutments. If the foundations are designed
at an adequate depth to avoid scouring then it is unlikely that bridge aprons
and weirs will be required and issues of fish passage will not be of concern.
Where a bridge apron is unavoidable it should be designed to ensure an adequate
depth of water to ensure fish passage is facilitated through the passage design
flow range and to avoid the need for a control structure such as a weir downstream.
In situations where a weir is unavoidable it is important to ensure that there
is an adequate depth of water to facilitate fish passage in low flow conditions
over at least part of it. Baffles may be necessary to reduce water velocity
through any fish passage measure.
General Design Principles to Minimise Construction Impacts to Fish
6.11 The following principles should be followed in the design process and
contract preparation to ensure that construction impacts on fish are minimised.
(i) Avoid in-river structures where possible to prevent scour and reduce
the impacts of temporary works during construction which could affect fish passage.
(ii) Where appropriate use a bridge in preference to a culvert to minimise
impacts to free fish passage.
(iii) Design all new in-river structures to avoid the necessity for retrofit
measures.
(iv) Wherever possible, schedule in-river works to minimise impacts to fish.
(v) Ensure the detailed design is complete and construction process adequately
planned before starting construction to reduce impacts on fish and other wildlife.
(vi) Inspect culverts regularly during construction to ensure inlets and
outlets are kept free from debris which could prevent fish passage.
(vii) Explore the potential to restore the natural river banks at the end
of construction and avoid the use of gabions and rip rap where possible to ensure
that shelter at the bankside is retained for fish.
(viii) Use of rip rap or boulders for erosion protection is preferred to
gabion baskets which may harm fish if they become damaged (and also results
in lower maintenance liabilities).
(ix) Remove all redundant in-stream works where these affect fish passage
unless such action would cause other significant environmental damage or where
cost would be prohibitive.
(ix) If a stream requires realignment as part of the works, consideration
should be given to provision of straight lengths upstream and downstream of
the structure to reduce the need for extensive erosion protection works which
may be detrimental to fish passage.
Other Issues
6.12 As well as guidance contained in this report other general best practice
guidance, such as SEPA Best Management Practices, should also be implemented
during construction.
6.13 The risk of disturbance to and pollution of watercourses should be
minimised during the construction process by careful control of site run-off,
chemicals and fuels.
6.14 Maintenance issues should be considered at an early stage in collating
contract requirements. Requirements for timing and form of maintenance should
be discussed with SNH and DSFBs during consultations. For example, it may be
necessary to include a maintenance requirement to clean trash screens prior
to fish runs to that ensure that these do not obstruct fish passage.
< Previous | Contents | Next > |