<<SE CREST>> Scottish Executive Consultations <jigsaw>
Your Views Consultations Development Department Home | Search | Contacts | Site Map

Foreword
Executive Summary
1: Introduction
2: Assessment
3: Design
References
Glossary
Appendix A
Acknowledgements
Comments

River Crossings and Migratory Fish: Design Guidance

< Previous | Contents | Next >

PART 2 ASSESSMENT

4 ASSESSMENT PROCESS

4.1 The requirements for fish passage should be considered throughout the development of the road project. A step-by-step approach is provided in Figure 4.1 which shows the progression of proposals through a staged process leading to the conceptual design of the in-river structure. The procedure for integrating fish passage requirements within the development of the conceptual design is described in Chapter 6.

fig 4.1

Stage 1

4.2 As part of the initial assessment of the overall road improvement strategy the location of river and burn crossings should be considered and included in the review of options for positioning the road alignment to achieve a balance between broad engineering, cost and environmental considerations. The need for crossings should be confirmed through examination of broad alternatives for the route of the road. If possible, crossings of important watercourses should be avoided. This step should be considered as part of the constraints analysis in the Stage 1 environmental assessment process outlined in the DMRB.

4.3 Early consultation with SEPA, SNH and SERAD(1) is essential. Information obtained from consultation and initial site visits should be taken into account in considering the siting and justification for a stream crossing as part of the Stage 1 assessment. In assessing the requirement for fish passage facilities at a river crossing, it is important to consider any existing obstructions to fish passage nearby. There is little point in providing good conditions for migrating fish passage if the stream is impassable downstream or a short distance upstream due to a natural obstruction.

Stage 2

4.4 In this stage further relevant data on the watercourse should be collated in order to identify the future requirements for the design of the structure. The hydrological data for the catchment are collated for later use in calculation purposes in Stage 3 and also to identify any significant flooding risks. Other considerations at this stage include identification of potential ground conditions for foundation design, investigating the potential to temporarily divert the watercourse so that the structure can be built "in the dry" and any specific access and maintenance requirements (e.g. for cattle, farm traffic etc). Consultations with relevant bodies (including the relevant DSFB (see Appendix A)) and, if appropriate, site surveys, should be undertaken to establish the need to accommodate particular fish species, in conjunction with other wildlife needs (for example, allowance for otter passage).

4.5 This step concludes with the comparison of options which have been identified and consideration of their relative costs in relation to the overall costs of the road improvement. These options could, for example, include a short culvert with a realigned watercourse, a long culvert on original line, a bridge, etc (see Figure 4.2). This review of options should contribute to the Stage 2 DMRB route option environmental assessment.

Stage 3

4.6 The development of the conceptual design should be undertaken as part of the Stage 3 environmental assessment of the preferred option. For culverts this stage closely relates to that presented in the CIRIA Culvert Design Guide (1997) and firms up on the type and size of the in-river structure. The sizing is derived from the hydrological parameters gathered in Stage 2 by calculating the acceptable maximum headwater depth for flood flows. In terms of fish passage, the flow velocity and depth under typical conditions when the fish are running needs to be identified (see Section 5.5). Consultations should continue with relevant organisations to ensure the developing design takes adequate account of the requirements for fish passage.

Scheme Procurement

4.7 With Design and Construct schemes it is necessary to complete sufficient development of the conceptual design to ensure that robust requirements can be included in the contract documentation. Development of the detailed design will be the responsibility of the appointed contractor.

4.8 For road projects which are not formally assessed using the 3-stage DMRB process, such as maintenance and minor improvement schemes, the principles of the staged process described above should be followed to ensure early consideration of fish passage requirements.

(1) Contact the Inspector of Salmon and Freshwater Fisheries (ISFF) and The Freshwater Fisheries Laboratory, Pitlochry.

 

fig 4.2

< Previous | Contents | Next >