Latest Implementation Timetable

Scotland Rural Development Programme: Implementation Timetable

Key milestones and proposed dates for introduction of all SRDP delivery mechanisms:

Programme recommended for approval

23 Jan 08

Formal written approval received 26 February

Programme changes confirmed and assessed

By 31 Jan 08

LFASS - issue payments

From Feb 08

£56.9m issued to 94% of applicants

Lay further SSIs

Feb 08

Including those for RDC - RP and RDC - LMOs

LEADER - 2nd call for LAGs, strategies & bids

By late Feb 08

Went out on 10 March 2008.

RDC - LMOs - issue guidance & forms

Mar 08

FPMC - open to applications

By 12 Mar 08

Food Processing, Marketing & Co-operation; opening date subject to SSI approval.

Easter weekend

21-24 Mar 08

RDC - RP launch - announce Regional Priorities

25 Mar 08

RDC - RP - Guidance published

25 Mar 08

First tranche

SSIs approved

29 Mar 08

Actual - laid on 7 March and effective following negative process

LEADER - announce LAGs & funding

By end Mar 08

FPMC - first round closes

31 Mar 08

CCAGS - Crofting Grant applications & payments

From Apr 08

Once SSI approved, existing forms & processes will continue with minimal change

RDC - RP - Open for applications ( SoI)

7 Apr 08

Achieved

RDC - RP - Respond to SoIs

From 30 Apr 08

Allows for minimum response time

Forestry Challenge Funds - open to applications

5 May 08

Woodland In and Around Towns (WIAT) and Forestry for People (F4P)

FPMC - PAC meeting

w/c 12 May

Project Assessment Committee meet, with confirmation of awards thereafter

RDC - LMOs - closing date

15 May 08

Aligned with SAF

Skills Development - open for applications

From May 08

If SSI in force by April.

RDC - RP - Proposal Outcome Plan form available

27 May 08

To allow applicants to prepare plans & get feedback before full Proposal

RDC - RP - Proposal data capture system available

7 Jul 08

On-line facilities for completion of full Proposal

RDC - RP - first payments for Plan preparation

From Jul 08

RDC - RP - First RPAC meetings

From Aug 08

Dependent upon stakeholder feedback, allowing for submission & assessment of quality Proposals

LEADER - 2nd round approved

Jul/Aug 08

RDC - RP - Notification of RPAC findings

Following 1st RPAC

Followed by contract with necessary checks & formal approval as required

RDC - RP - first payments for Capital projects

Autumn

For 'actual cost' cases; 'standard cost' cases depend on Inspection schedules.

Forestry Challenge Funds - Assessment round

From 1 Sep 08

LEADER - funds to LAGs & project claims

From Apr 09

May also be smaller interim funding in 08-09 financial year

RDC - RP - first payments for Multi-annual land based

From Oct 09

Payment for these projects requires submission and processing of SAF 09


Note: all implementation dates are subject to formal approval of the Programme & domestic legislation as shown