Scottish Government Health Directorates - KCND Overall Programme Progress Report, April 2009

Activity

Process

Timescale

Lead

Progress

Status

Actions taken/ required

Establish support process for leading and supporting KCND

Completed

May 2007

MMcG

AH

Completed

Completed

Produce literature review to support programme

Completed

July 2007

CSO

NMRU

Completed, disseminated

Completed

Appoint consultant midwives/leads to support local implementation

Completed

January 2008

HOMs

Completed

Completed

Establish process for leadership and change management support

Completed

2007-2008

NES

Completed

Completed

Discontinue admission CTG for healthy women

Completed

August 2008

NHS Boards

Completed

Completed

Produce nationally agreed referral criteria and care pathways

Completed

March 2009

NHSQIS

Completed

Completed

Identify training needs, deliver training related to care pathways

NHS Boards to progress locally

March 2009

NHS Boards

Completed or ongoing

Completed

Disseminate and launch care pathways

Completed

From March 09

SGHD

NHSQIS

Disseminated to Boards April 09, launch May 09

Completed

Implement care pathways across NHS Scotland

NHS Boards to implement locally

From March 09

NHS Boards

Ongoing locally

Green

Implement midwife as named caseload holder for healthy women antenatal, intrapartum, postnatal

Board implementation groups to progress locally; National work required around relevant data capture

July 2009

NHS Boards

AH

Mainly implemented or on track

NHS Borders & Fife progressing, GG&C introducing with service redesign

Proposal complete

G

AMB

Implement midwife as first point of contact, to undertake initial risk assessment and onward referral

Boards to progress locally; National work required around professional communication

December 2009

NHS Boards

AH

Local work progressing, slow in some areas; Proposal complete

G

Establish process for evaluating impact of KCND nationally

Identify key stakeholders; agree evaluation plan; report to steering group

Ongoing

CSO (HC)

AH

1st data collection complete; stakeholder interviews underway

G