Note of National Stakeholder Forum
meeting
16 November, Royal Lodge Hotel,BridgeofAllan
Introduction & welcome
Elinor Mitchell welcomed attendees to the meeting. She
outlined progress to date since the last meeting of the NSF
in April 2004, on matters including:
- Controlled Activities Regulation
consultation
- Development of of GBRs
- Charging Scheme
- Diffuse Pollution
- Remedial & Restoration
work
- Executive attendance at European
meetings to increase Scottish profile.
She set out plans for 2004/05:
- SEPA will finalise its
Characterisation report by December
- SE will finalise Controlled
Activities Regulations in the spring
- Diffuse Pollution - a working
group had been established to take this forward and the
SE invited stakeholders' help in developing this area
of control
Agenda items and key points :
1. Revised Proposals for Regulation
-Joyce Carr, Scottish Executive
Joyce Carr outlined the revised proposals for the
Controlled Activities Regulations, focusing on the new
structure of controls. She welcomed comments and feedback
from stakeholders, inviting questions to a panel consisting
of Elinor Mitchell and Joyce Carr from the Executive, and
Martin Marsden and Dougie Johnstone from SEPA.
Stakeholders broadly welcomed the revised proposals.
There was some discussion on the role of the risk
assessment and how SEPA's characterisation exercise would
inform the regulatory process. Consideration had been given
whether it was possible to set different regulatory
controls for different parts of Scotland. The tiers set out
in the diagrams were indicative of the likely level of
control, and the Regulations would be designed to be
sufficiently flexible to allow SEPA's risk assessment
process to set the appropriate level of control for the
area.
Stakeholders would like to see some examples of simple
licences.
There was considerable discussion on the development of
SEPA's risk assessment and the nature of the risk being
assessed - whether current impact or potential impact. SEPA
were in the process of developing their risk assessment
which would be discussed and considered at their Regulatory
Stakeholder Group.
Joyce Carr undertook to produce a more detailed paper on
how the revised controls would permit flexibility of
regulation. It was agreed that a meeting in late January
would be a good opportunity for stakeholders to review and
provide comment on the revised Regulations
2. Transitional Arrangements Update -
Dougie Johnstone, SEPA
Dougie Johnstone outlined the proposed transitional
arrangements including the transfer of existing consents
into the new regime.
In response to queries, Dougie explained that with
regard to the concept of a "Responsible Person", either a
person or corporate body can be named. Holders of IPPC
Permits would still have to apply for an abstraction permit
under WEWS as well as having an IPPC permit. In the longer
term the SE were planning to consider how these regimes
might be merged.
Stakeholders expressed considerable concern about the
data requirements, workloads, amnd budget implications. It
would be useful to see proposals for the format in which
data will be required to be prepared.
There was some general discussion about the draft
general binding rules. These were still working drafts, and
once these had been refined they would be issued to
stakeholders for comment, within a couple of weeks. SEPA
would also make available information on the detailed
transfer requirements by early December. They would also
discuss the requirements directly with stakeholders.
3. Executive progress report - John
Langlands & Ian Speirs, Scottish Executive
John Langlands and Ian Speirs gave a brief outline of
the Executive's general progress on implementing WFD,
including the designation of protected areas, diffuse
pollution and remedial & restoration works.
4. SEPA progress report - Colin Bayes,
SEPA
Colin Bayes presented a summary of SEPAs work on two
major activities, the analysis of pressures and impacts on
Scotland's water environment, and SEPA's consultation on
river basin management planning.
5. Economics - Evan Williams,
SEPA
Evan Williams presented the initial findings of SEPA's
economics characterisation report, required to support the
environmental characterisation of Scotland's waters.
Some stakeholders expressed disagreement with the
findings of the draft economic report, and with its focus.
There was also considerable concern about the future use of
this report. Moreover such a report could only reflect
averages, not site specific data. It was agreed that some
of these concerns would be set out in the revised
report.
The Executive recognised that this report was a useful
starting point but that the contents should not be taken as
definitive.
5. Regulatory Impact Assessment - Jenna
Coull, Scottish Executive
Stakeholders commented that the RIA should demonstrate
greater benefits as a result of the increased regulation.
There was also some discussion about the respective costs.
It was emphasised that this was a very early draft and that
the Executive proposed to seek both SEPA's and
stakeholders' input to the further development of the
RIA.
6. Charging Scheme - Martin Marsden
SEPA
Martin Marsden outlined the work that had been done to
develop SEPA's charging scheme. A revised work plan had
identified a reduction in costs of around 30-35% per year,
resulting in a cost estimate of around £10m pa for the
additional cost of implementing WFD. Of these costs, it was
expected that some £3.5m would be spent on regulation,
£5.4m on monitoring, and £1.1m on river basin management
planning.
SEPA was in the process of developing appropriate bands
and multipliers for the charging scheme. This work will be
taken forward through SEPA's Regulatory Stakeholders
Group.