1. The following schemes will be awarded grants subject to conditions:
| Applicant | Project | Location | Funding Awarded |
|---|
| PrintMatters | Heating for PrintMatters offices and 2 neighbouring businesses | Brechin | £75,845 |
Dow Waste Management | New biomass heater for Dow Waste Management | Cumbernauld | £26,217 |
Wyvis Plant & Power | Blairninich Community Heating Scheme | Strathpeffer, Ross-shire | £64,119 |
Kemnay Golf Club | Kemnay Golf Club Biomass Boiler | Inverurie, Aberdeenshire | £35,950 |
A.R.P. Besterman | Auch District Heating Scheme | Bridge of Orchy | £40,335 |
MacLeod Hotels Ltd | Royal Hotel Portree - Wood Pellet Boiler System | Portree, Skye | £26,212 |
Classic Restorations Scotland | Boiler to heat Classic Restorations Scotland Workshops | Alyth, Angus | £11,557 |
Hill of Banchory ESCO ltd | Hill of Banchory Biomass District Heating Scheme (5MW boiler supplying heat for 206 homes) | Banchory, Aberdeenshire | £221,410 |
Lovat Arms Hotel | Lovat Arms Hotel Biomass Project | Beauly, Inverness-shire | £78,405 |
Howie Irvine Ltd T/A Deeside Activity Park | Deeside Activity Park District Heating Scheme | Aboyne, Aberdeenshire | £33,000 |
Ashtree House Hotel | Ashtree House Hotel Biomass Conversion | Paisley | £63,105 |
Whitehill Storage Company | Convert Continuous Flow Grain and Woodchip Drier | Turriff, Aberdeenshire | £100,000 |
M.M.R. Ltd / T J.U. Ross | Proposed Biomass Heating to Eastbank Works | Strathmiglo, Fife | £23,625 |
Beinn Bhuide Energy Ltd | Glenborrodale District Heating Scheme | Ardnamurchan | Capped at £100,000 |
Arran Energy Ltd | Benlister Terrace (West) District Heating Scheme | Lamlash, Arran | £107,200 |
Eagle Brae Cabins | Eagle brae Biomass - Heating for Log Cabins | Beauly, Inverness-shire | Capped at £60,000 |
| | TOTAL | £1,066,980 |