This document is also available in
PDF format.
Chapter 3: Analysis Of Questions
1. This chapter sets out the three questions posed in
the consultation document and analyses the level of
response given to each. The chapter will also highlight the
range of answers to these questions.
The three consultation questions
2. The consultation posed three questions relating to
the proposed level of fees payable under the Electricity
(Applications for Consent) Scotland Regulations 1990. They
were:
- Do you agree that the revised scale of fees
detailed in Annex A should be introduced?
- Do you agree that arrangements should be
introduced to compensate planning authorities for
the costs they incur in processing Electricity Act
consents cases?
- Do you agree with the proposed
reimbursement arrangements?
3. Most respondents to the consultation did so by
completing the consultation questionnaire or drafting
letters following its format. A small proportion did not
answer the questions directly but it was possible to draw
conclusions from their responses. All responses received
answered each question (with the obvious exception of the
two nil-returns).
4. The table below outlines the percentage of
respondents who agreed or disagreed with each question.
Question | Yes | No | Nil |
Q1 | 61.5 | 30.8 | 7.7 |
Q2 | 76.9 | 15.4 | 7.7 |
Q3 | 19.2 | 73.1 | 7.7 |
Question 1 - Do you agree that the revised
scale of fees detailed in Annex A should be
introduced?
5. A clear majority of respondents were in favour of the
revised scale of fees set out in the consultation paper .
When analysed by group, local authorities showed a clear
majority in favour of the introduction of the fee schedule
with 11 voting yes and 2 voting no. The response from
companies was less clear cut - 50 % in favour of the
schedule and 50% against.
6. There was a variety of reasons provided by those who
objected to the fees schedule. One believed that the
application and consents process needed simplified with the
costs lowered, and that the proposed changes did nothing to
rectify this.
7. Others stated that developers in Scotland already
face higher costs as they have to apply to Scottish
Ministers for consent for hydro-electric schemes above 1MW.
A correspondent states: "Given the interest amongst
developers in developing smaller projects such as run of
river developments or new marine energy developments, we
are of the view that additional funding bands would be
needed to reflect more accurately the cost of considering
applications from smaller schemes."
8. The issue of fees for section 37 was also raised. It
was considered that cases should be based on distance
rather than voltage as it is distance which increases the
difficulty of assessing applications and creates
controversy with the general public.
9. A final point raised by all who responded to this
question was that additional bandings be created for
section 36 developments below 100 MW. The fees schedule
outlines that a fee of £15,000 will be charged for the
construction or the construction and operation of a
generating station not exceeding 100 MW. Some respondents
would like to see this broken down into further bands with
lower differing fees charged:
"Given the interest amongst developers in developing
smaller projects such as run of river developments hydro or
new marine energy developments, we are of the view that
additional funding bands would be needed to reflect more
accurately the cost of considering applications for smaller
size schemes and not discouraging these smaller size
schemes from coming forwards. We therefore propose that the
current fee level (£5,000) should be maintained for section
36 projects up to 10MW, and that a fee level of £10,000 be
set for projects of between 10 and 50MW."
Question 2 - Do you agree that arrangements
should be introduced to compensate planning authorities
for the costs they incur in processing Electricity Act
consents cases?
10. There was a clear majority in favour of this
proposal with 77% returning a yes answer. It can therefore
be concluded that amongst those who responded, it is
recognised that planning authorities do not receive a fair
settlement under the present regulations.
11. The 4 consultees who are against introducing the
arrangements to compensate planning authorities for costs
incurred included two companies, a local authority and a
trade body. Both companies and the trade body considered
that the scale of compensation outlined is prohibitive to
renewable energy construction.
12. The local authority against introducing the
arrangements raised concerns which will be dealt with in
the section analysing question 3.
Question 3 - Do you agree with the proposed
reimbursement arrangements?
13. Around 73% disagreed with the proposed reimbursement
arrangements. Disagreement however, was not centred on any
one group.
14. The reasons given for disagreeing with the proposals
show a high degree of consensus by the respondents. This is
perhaps not surprising given the relatively small and
focussed nature of those who responded.
15. The main issue raised by those who negatively
responded was the issue of a four month time limit to
complete applications in order to claim maximum
re-imbursement from the Executive. After four months,
planning authorities would receive a reduced fee. This
issue was highlighted as being inappropriate by the vast
majority of those who responded. Only one responder
explicitly agreed that the four month limit was an
appropriate measure to implement.
16. Typical responses to the 4 month limit included:
"The intention to link payment of the full fee to
performance is [equally] unacceptable and creates an
unwelcome precedent. An extended period in processing
applications involving environmental statements,
particularly wind farms, is often due to the applicants
having to provide additional information…"
"An unintended side effect could be that a perverse
incentive would be created for local authorities to respond
in the 4 month period where there genuinely are unresolved
issues, and this may result in more "holding" objections
being made when a favourable response would have been given
more time."
17. A concern was also raised in relation to the
proposal that Local Authorities submit an invoice to the
Executive with a detailed breakdown of the costs incurred
by them. Over half of the 26 consultation responses stated
this was an unreasonable recommendation.
18. The main reason given for these objections was that
it would produce an overly demanding level of accounting
that does not exist at present. Planning authorities are
concerned that the need to produce a detailed cost
breakdown for the work they carry out on each application
would place them under an administrative burden.
19. Local authorities were also concerned that they
would be paid retrospectively for work they carry out on
applications. Under the proposals, developers would pay the
full fee to the Executive when an application is made and
once completed, they would be required to submit an invoice
providing a record of the costs they had incurred. The
Executive would then reimburse a portion of those costs
back to the planning authorities.
20. There were several suggestions on alternative
methods of reimbursement. Some local authorities indicated
they would prefer an upfront fee to be paid to them when an
application is received by the Executive. This would
prevent difficulties arising when an application is not
completed in the same financial year. Others suggested that
local authorities could still be paid retrospectively
without the need to submit a detailed breakdown of the
costs incurred.
21. A further issue raised was the proposal not to
reimburse planning authorities for an overhead line which
requires an EIA but has a voltage not exceeding 132KV.
Local authorities believe this should not be the case and
that they should be reimbursed for all schemes that involve
an EIA.
Summary
- This chapter considered the findings and comments
received about the consultation.
There is agreement that
planning authorities should be compensated for the
costs they incur in the processing of Electricity
Act applications. There is also broad agreement
that the schedule of fees payable by section 36 and
section 37 applicants is correct.
However, respondents of all
groups raised concerns over the proposed
arrangements for reimbursement. These concerns
are:
- the four month time limit in which to claim full
reimbursement
- a need to provide the Scottish Executive with a
detailed breakdown of the costs incurred
- that section 37 applications are based on voltage
and not distance
- that no fee is recovered for overhead lines not
exceeding 132kv.
Executive Summary
Chapter 1: Introduction
Chapter 2: Analysis of Responses
Chapter 4: Conclusion
Annex A: Consultation Paper
Annex B: Distribution List