4. Options for a New System of Marine Planning and Coastal Zone Management
4.1 Options
4.1.1 Introduction
The options for a new system of Marine Planning in Scotland have been developed over many years through a number of initiatives, both in the UK and more locally (e.g. AGMACs, the Sustainable Seas Task Force 4). The most recent steer on the potential options is provided in Sustainable Seas for All 5.
The manner in which marine planning might be managed, and how the objectives that underpin it might be delivered through licensing and nature conservation initiatives, is closely linked to the options on other policy areas of the Scottish Marine Bill.
At this stage, there are two main options in relation to marine planning. These are:
- Option 1: no change. This represents the baseline for comparison with other options; and
- Option 2: Implement a statutory planning system.
The main features of these options, the potential risks associated with them and the information sources that will be required to support an assessment of the costs and benefits are described in more detail in the rest of this section.
4.1.2 Option 1: No Change to Current Arrangements
Main Features
Under this option, a marine planning system would not be implemented. There would be little or no formal integrated planning of activities. Although high-level marine objectives might exist, stemming from national and international initiatives ( UK Marine Bill, European Marine Strategy Framework Directive ( MSFD)), there would be no formal system to 'unpack' these and to deliver objectives at lower levels in an integrated way. Decision-makers would need to take account of the high level objectives through the various sectoral licensing systems.
Potential Risks
There are a number of risks associated with this option. These are summarised in Table 4.1.
Table 4.1: Summary of Potential Risks of Option 1
Type of Risk | Description |
|---|
Sectoral conflicts | Without a planning system to provide an integrated and proactive approach to marine management, the marine licensing system on its own may not be effective enough in addressing conflicts that arise between marine activities |
Modified, delayed or refused development applications | Lack of clearly expressed and integrated policies could result in unclear and ambiguous requirements for developers. Decision-makers could face significant difficulties in evaluating whether proposed new developments did or did not support the achievement of high-level objectives. This might result in additional and disproportionate requirements being placed on developers to seek to demonstrate how development activities were consistent with the achievement of high-level objectives, leading to uncertainty and delay. Sectoral conflicts among users may also result in further modifications to development designs, and delayed or refused applications. Additional costs would be incurred by public bodies and industry |
Cumulative impacts | Lack of an integrated assessment of the cumulative impact of sectoral activities on each other, on the environment, and on society may result in unsustainable development, potentially affecting all those with interests in the Scottish marine environment |
Less efficient use of marine space | As pressure for the use of marine resources increases, a lack of planning may result in the inefficient use of marine resources. Spatial planning can investigate the potential to maximise the sustainable economic revenue from a particular resource or site. This may ultimately reduce the amount of marine resource that is 'sterilised' (i.e. excluded from other uses); for example, cables, pipelines and offshore energy installations may exclude the extraction of marine aggregates and fish through dredging |
Deterioration of the marine environment | The lack of an integrated system to deliver high-level objectives at the local scale and to assess cumulative impacts from multiple activities may result in continued deterioration of marine ecosystem components on which the economy depends and processes with indirect impacts on the economy, society and other environmental aspects |
Lack of preparation and long-term vision | With new technologies being developed and new activities occurring in the marine environment (e.g. carbon capture and storage, renewable energy devices), there is a risk that, without long-term spatial planning, Scotland will be unprepared to deal with the new demands |
Inefficient collection and use of data | Without a strategy coordinating research funding and efforts, data collection may remain inefficient, potentially resulting in gaps and overlaps |
4.1.3 Option 2: Implement a Statutory Marine Planning SystemMain Features
Following the recommendations of SSTF, likely features of a statutory marine planning system would include:
- A statutory basis, whereby public authorities are required to make decisions "in accordance with" the plan and appropriate policy documents "unless relevant considerations indicate otherwise";
- A three-tiered approach consisting of:
- an international tier in terms of the MSFD and OSPAR objectives;
- a national marine policy statement and marine objectives for clean, healthy, safe, productive and biologically diverse seas and a national Scottish Marine Plan; and
- a local level composed of 9-13 plans within Scottish Marine Regions ( SMR). We have assumed that the focus of these plans will be waters within the territorial limit (12 nm), reflecting the relative distribution of pressures. Not all areas will need plans (they are only necessary where there are activities to plan and potential conflicts, e.g. Solway, the Firths, and the West Coast);
- National marine objectives that underpin the Scottish marine plan and encompass ecosystem, biodiversity, social and economic elements. There will need to be clear high-level objectives (these should reflect the objectives being developed under MSFD, ICES, OSPAR and the UK Government's vision for Clean, Healthy, Safe Productive and Biologically Diverse Oceans and Seas), which will then be broken down in plans into lower-level objectives, performance indicators and targets. The national marine objectives themselves are part of the baseline but the ability to deliver them will be provided by the marine planning system;
- Planning responsibilities out to 200 nm. Although the majority of activities, and therefore planning focus, occurs within 12 nm of the coast;
- Responsibility for making the plan will lie with Marine Scotland (the proposed Scottish Marine Management Organisation ( SMMO) - see Section 7) for the national marine plan, with Ministers responsible for signing off the plan. At a local level, plan making responsibilities could be delivered in a range of different ways including through local arms of Marine Scotland (possibly supported by local Coastal Partnerships on community and stakeholder engagement), local authorities, or through existing river basin management planning processes under the Water Framework Directive;
- A mechanism for consultation on the draft plan as part of the plan making process and provision for enforcement of plan policies where required. There are requirements for Strategic Environmental Assessment ( SEA) under the Environmental Assessment of Plans and Programmes (Scotland) Regulations 2004 but requirements for public inquiry into a national plan are less clear;
- The plan-making body would have responsibility for co-ordinating the management of relevant data and maintaining and making available appropriate information to support marine planning; and
- Finally, the principles of ICZM should be considered in the plan-making process. The consultation paper defines Integrated Coastal Zone Management ( ICZM) as "a management process that aims to facilitate more integrated working or partnership working on the coast by different interests, including local communities."
The SSTF supported the overall objective for marine planning set out in Table 4.2.
Table 4.2: Overall Objectives of Marine Planning
"The overall objective of marine planning in Scotland is to provide a framework for decision making for the sustainable management of the marine and coastal environment, integrating the interests of resource use and resource protection in a way that: - Is founded on the five guiding principles of sustainable development (as listed in "Seas the Opportunity"):
- Living within environmental limits,
- Ensuring a strong, healthy and just society,
- Achieving a sustainable economy,
- Promoting good governance, and
- Using science responsibly;
- Maximises the social, economic and environmental value of the marine resource;
- Facilitates the sustainable use and enjoyment of this resource; and
- Incorporates improved measures to protect and restore the natural marine environment."
|
A Scottish marine planning system would cover all activities, constraints and obligations in the marine environment around Scotland. It could take the lead on spatial planning for an activity, not withstanding that policy and/or licensing responsibility had not been devolved:
- marine renewable energy;
- biodiversity obligations;
- marine nature conservation measures;
- sea fisheries and inshore fisheries;
- ports and harbours;
- aquaculture;
- activities covered by regimes such as marine licensing and environmental consents including pollution;
- pipelines and cables;
- sand and gravel extraction;
- historic marine environment;
- recreational activities and tourism; and
- the MSFD obligation to achieve 'good environmental status'.
A local marine plan might deliver the following features:
- strategic local vision for marine and coastal areas;
- local interpretation of national marine plan and priorities;
- consultation and stakeholder engagement;
- development of local management policies for specific sectors and activities;
- identification of areas of potential conflict and resolving conflict;
- a framework for the granting of development consents;
- identification of areas of sea for potential activity/development;
- identification of areas and actions needed for conserving biodiversity;
- local decision-making for the application of marine nature conservation measures;
- construction of shared principles that could be applied by local public sector organisations in their approach to carrying out activities in the marine area;
- coordination with existing local management plans and existing regimes (which may not be marine in their focus) to ensure joined up delivery of a shared local vision for the marine area; and
- local data and information gathering and coordination to inform the development of the plan.
Potential Risks
There are a number of potential risks associated with this option.
Implementation of a system of marine spatial planning represents a considerable investment and there is always a risk that it will not achieve the anticipated benefits. This risk can be mitigated by ensuring that the planning process is adaptable with regular review throughout the plan process and provision for consultation and public hearings.
A second risk is that the system may become overly complex or bureaucratic, leading to uncertainty and delay (with associated costs) for developers and excessive costs to Government during the initial plan-making process; or that plans, once produced, are not adhered to. The risks of delay during plan preparation can be mitigated by ensuring that a robust planning process is established, with clear responsibilities and time scales for plan preparation.
Implementation of a statutory system of planning, with a requirement on decision-makers to follow the plan unless material considerations indicate otherwise, should ensure that the requirements of plans are generally adhered to. Ensuring that relevant stakeholders are fully engaged in the preparation of plans and that a participative process is developed to support their implementation will improve acceptance and understanding of plan objectives.
Incompatibility among policies may occur between neighbouring marine and terrestrial plans and may cause confusion for users of the system, and reduced effective management. In addition, the boundaries for marine spatial planning are administrative ones (i.e. Scottish and regional borders, seaward limit of 12 nm). Such boundaries may be artificial from an ecological perspective and, as a consequence, it may be difficult to deliver an ecosystem approach and integrated nature conservation planning. Ensuring a broad level of early consultation on plans and continued involvement in UK and international planning initiatives will improve the integration of Scottish marine plans with neighbouring marine and terrestrial ones.
4.1.4 Comparison of the Options
Table 4.3 summarises the features of the two options.
Table 4.3: Summary of Options for a New System of Marine Planning and Coastal Zone Management
| Option 1: No change | Option 2: Statutory Marine Plan |
|---|
Scope | International/ UK plan beyond 12 nm only | Three tiered approach: - International/ UK;
- Scottish plan out to 200 nm;
- 9 - 13 local plans within Scottish Marine Regions ( SMRs), focused on territorial waters
|
|---|
Objectives | High-level social, economic and environmental objectives will still be required to meet obligations under the Marine Strategy Framework Directive ( MSFD), and sustainable development. No plan for interpreting these at lower levels. | High-level social, economic and environmental objectives to be developed. These should reflect Scottish issues as well as broader objectives, e.g. from the MSFD. Lower level objectives delivered through local plans. |
|---|
Plan-making | No plan | Plan-making body to develop the plan, sign-off by Ministers |
|---|
Data | Existing responsibilities for data management and co-ordination continue | Plan-making body responsible for management and co-ordination of relevant data |
|---|
SEA | Regional and sectoral SEA | SEA of plans within a more local context |
|---|
Appeals | Appeal process limited to licensing decisions | Assuming a similar system to the terrestrial one; no appeal system for national plans but provisions for public inquiry of local plans |
|---|
Stakeholder involvement | Existing stakeholder engagement activities will continue via local fora. | Each SMR will have a board comprising representatives from the main stakeholder interests |
|---|
Delivery | Existing responsibilities for delivering objectives will continue. Decisions on licensing etc. will continue to be taken on existing basis. | Authorities will be required to make decisions 'in accordance with the plan' Public bodies will be required to take note of the plan in decisions on licensing etc. Lower tier plans will need to take account of the Scottish Plan |
|---|
ICZM | Reduced potential for integration with land and coastal based management | SMRs will be responsible for delivering the principles of ICZM |
|---|
There is a further potential option, of implementing a non-statutory planning system. This would still involve collation of marine data and information, accompanied by the setting of marine objectives and priorities. Spatial plans would be developed largely as outlined above, but there would be no statutory requirements for decision-making authorities to act in accordance with them. The plan may only require that public authorities must "have regard to" the plan in making decisions. Public hearings on the plan would also not be part of the process.
The main potential risk with a non-statutory system of planning is that plans, once produced, might not be adhered to. It might be possible to limit this risk to some extent, by ensuring that relevant stakeholders are fully engaged in the preparation of plans and that a participative process is developed to support their implementation. However, as the process and costs involved in preparing a plan are largely the same as for a statutory planning system but with fewer benefits, this option has not been assessed in detail here.
4.2 Sectors and Groups Affected
As noted above, a planning system (or lack of) affects all activities and interests in the marine environment around Scotland.
Key industry sectors affected include:
- marine renewable energy;
- fisheries (finfish and shellfish);
- ports and harbours;
- shipping;
- aquaculture;
- oil and gas extraction and related pipelines
- telecommunication and power cables installation and operation;
- sand and gravel extraction;
- recreational and tourism, and
- other activities covered by regimes such as marine licensing and environmental consents (see Section 5).
Affected public sector organisations include those that are responsible for managing and licensing the activities listed above, not all of which are devolved to the Scottish Government. They include not just Scottish Government departments and Agencies (such as Historic Scotland and Scottish Natural Heritage), but also local authorities and regulators, as well as the UK Government.
Other groups affected include recreational users of the marine environment, non-governmental organisations with interests in the marine environment and the general public.
4.3 Benefits
4.3.1 Option 1: No change
There are no additional long-term benefits from Option 1. There may be some short-term benefits, in that policy makers, businesses and marine users will not have to modify their activities. However, it is likely in the longer term, that political and economic pressures on the marine environment will ultimately require alternative solutions and consequent modifications in activity.
4.3.2 Option 2: Statutory Marine Plan
Studies by AGMACS, the SSTF and the Irish Sea Planning Pilot identified a range of potential benefits of marine planning. These are summarised in Table 4.4.
There are potential benefits for the full range of stakeholders from marine planning. The scale of the benefits is impossible to quantify accurately, as it will depend on the way in which planning operates in practice and the specific features of each plan. However, planning could significantly reduce the costs of conflicts, delays and compensatory measures associated with the current system, which can cost from several hundred thousand pounds to millions of pounds per development (see Section 4.4).
For example, the value of Scottish marine renewable energy generation is forecast to reach over £200 million per year by 2017 6. If marine planning resulted in more rapid approval of marine energy projects, so that this value was achieved by 2015 instead of 2017, the net present value would be increased by around £5.5m7. There could also be benefits in terms of increased tax revenues.
Marine related industries and goods and services are estimated to contribute over £2 billion annually to the Scottish economy (see Table 4.5).
Table 4.5: Economic Value of Marine-related Industries and Goods and Services
Sector | Gross value added (at 2004 prices) |
|---|
Sea fishing | £150 million |
Fish farming | £122 million |
Fish processing | £481 million |
Building and repairing of ships and boats | £313 million |
Marine wildlife tourism | £57 million |
Other sectors | £1,033 million |
Total marine sector | £ 2,156 million |
Source: Scotland's Seas: Towards Understanding their State |
If reducing conflicts between uses and delays is assumed to increase gross added value by as little as 1%, this would be equivalent to around £20 million per year, or a net present value of £294 million over the 20 year assessment period.
4.4 Costs
4.4.1 Option 1: No Change
Continuing with the current system of marine management will not result in any additional costs. However, if the risks identified in section 4.1.2 are realised, they may give rise to costs for government, businesses, society and the marine environment. These are discussed below.
Costs of Conflicts of Use
Costs may result from the need to resolve conflicts between different users, marine resources and ecosystem components. For example, the Consultation Document identifies the following potential conflicts among interests in Scotland's seas:
- conflict between the need for development at fixed sites for aquaculture and renewable energy generation and the obstruction this might cause to ease of navigation;
- concerns surrounding the economically important but relatively un-regulated harvesting of seaweeds and potential impacts for fisheries, nature conservation and coastal defence.
- protecting habitats of species like dolphins and other marine mammals against the needs of commercial operations to exploit the resources of the seabed;
- the need to develop undersea infrastructure against the needs for safety of fishing;
- the need to dredge to keep ports open against the impact on shellfish and aquaculture; and
- needs of green tourism against the impact of commercial exploitation.
Resolving such conflicts will require time and resources for the organisations involved to negotiate and resolve. In extreme cases, they may result in court hearings with costs met by, for example, government, regulators, developers and businesses, Scottish Natural Heritage and environmental NGOs and local fora.
The costs associated with resolution of conflicts are, by their nature, case-specific. Table 4.6 (at the end of this section) summarises a number of examples of conflicts between different economic sectors and between economic activities and environmental objectives. Further detail on these examples is provided in Annex 1. The costs include:
- loss of the value of marine resources (e.g. aggregates) that cannot be exploited because of the presence of conflicting developments (e.g. pipelines), which can amount to millions of pounds;
- costs involved in resolving conflicts (e.g. costs of meetings and consultation, costs of relocating one or more conflicting activities);
- costs to environmental organisations of campaigning against developments that conflict with nature conservation.
Costs of Modified, Delayed or Refused Development Applications
Conflicts among users and unclear environmental requirements may also result in further modifications to development designs, and delayed or refused applications. In the absence of a plan, decision-makers could face significant difficulties in evaluating whether proposed new developments did or did not support the achievement of high-level objectives. This might result in additional requirements being placed on developers to seek to demonstrate how development activities were consistent with the achievement of high-level objectives, leading to uncertainty and delay.
Most of the costs of delays, modifications or refusals will tend to fall on developers. As the example of Dibden Bay illustrates (see Table 4.6), the costs of refusal of major development applications can be very high. In this particular case, costs of £40 million to £50 million were incurred for the consents and public enquiry process. Significant costs are also incurred by the Government through consultation and negotiation on proposals prior to their refusal.
For some projects, it may be possible to accommodate delays within the overall planning and construction timetable for the project. However, for projects on a critical time path, such delays could be extremely costly and jeopardise the viability of the project. An example of this is the Port of Mostyn, where damages of £9 million were awarded for revenue lost due to delays (see Table 4.6).
Stakeholders responding to the consultation indicated that delays in granting planning permission are a particular issue for the aquaculture industry, potentially leading to significant costs through loss of revenue. The lack of a clear planning framework makes it difficult for businesses to identify preferred locations and for local authorities to evaluate applications.
Costs of Compensatory Measures
Conflicts among users and unclear environmental requirements may also result in the need for compensatory measures. There are few examples of industry or Government providing compensatory measures in the marine environment. Where compensation has been provided, this has generally been specifically to meet the requirements of the Habitats and Birds Directives. The main reasons for such requirements have tended to be scientific uncertainties over the scale of impacts, leading to provision of compensation areas significantly larger than the predicted damage. In these cases, the costs are incurred primarily by the developer.
Examples are summarised in Table 4.6 with further detail provided in Annex 1. The major cost is associated with land purchase and scheme construction, which amounted to £3.2 million in the case of Immingham and Hull ports. Licensing and monitoring costs generally add around 10% of the total cost.
Costs of Cumulative Impacts
Lack of an integrated assessment of the cumulative impact of sectoral activities on each other, on the environment and on society may result in unforeseen consequences for all interests. An example is provided in Table 4.5 of where information on cumulative impacts would help in the assessment of risks to environmental objectives.
Table 4.5: Example of the Costs of Cumulative Impacts - Boat Traffic on the Moray Firth
An application has been made for a development on the site of a former fabrication yard in Ardersier. This includes housing, a hotel, a visitor centre and marina. The development is close to the Moray Firth SAC, one of the features of which is a population of bottlenose dolphins. There are concerns over the effect that a marina and associated boat traffic will have on the bottlenose dolphins, particularly this close to areas regularly used by them. To address these issues, a harbour revision order ( HRO) and section 75 planning agreement are likely to be put in place. These will specify the need for a leasing scheme for moorings, a sea ranger to help manage boat activity in the area and a research and monitoring programme to confirm that the proposed mitigation measures are working. There are uncertainties over whether the HRO and section.75 agreement are appropriate tools for managing marine recreational activity for the purposes of conservation. This is not the only new marina in areas close to those regularly used by the bottlenose dolphins and it would be useful to have a tool capable of addressing the cumulative effects of increased recreational activity. |
Source: Scottish Natural Heritage |
Costs of Less Efficient Use of the Marine EnvironmentAs pressure for the use of marine resources increases, a lack of planning may lead to the inefficient use of marine resources. Spatial planning can investigate the potential for interests to overlap and reduce the amount of marine resource that is 'sterilised' (i.e. excluded from other uses). For example, cables and pipelines may exclude the extraction of marine aggregates and fish through dredging. This may result, for example, in the sterilisation of aggregate assets worth millions of pounds (see Table 4.6).
Costs from Deterioration of the Marine Environment
The costs of deterioration relate to the loss of goods and services provided by the marine environment. A number of current risks of deterioration are identified in "Scotland's Seas: Towards Understanding their State" and are discussed further in Section 6 on marine nature conservation.
A summary of the type of costs and potential magnitude is given in Table 4.6 overleaf.
4.4.2 Option 2: Statutory Marine Planning system
Costs to the Scottish Government
Option 2 will give rise to costs for the Scottish Government in preparing plans at the international, national and local level.
Tasks involved in international planning are likely to include:
- consultation with national and international cross border partners;
- interacting with other planning authorities, particularly over reserved activities; and
- delivering international commitments to e.g. the MSFD.
The majority of these functions would be required regardless of the implementation of a marine planning system. Therefore, the costs incurred largely in consultation (attending meetings and writing responses) can be considered to be part of the baseline.
Marine planning is a new and developing initiative worldwide and there is therefore limited accessible and comparable data on costs. Some data are available on the costs of preparing terrestrial plans. However, these data need to be used with caution, as terrestrial plans differ from marine plans in a number of key areas:
- terrestrial planning systems benefit from a legacy of over 50 years experience of the planning process resulting in a stream-lined and cost effective system;
- experience has resulted in a large number of detailed policies being developed at national level to avoid and manage potential conflicts between different uses and between different uses and the environment;
Table 4.6: Examples of the Impacts of Conflicts, Delays and Compensatory Measures in the Marine Environment
Conflict | Description | Economic Impacts & Costs |
|---|
Sectoral conflicts |
Offshore Wind and Gas Pipelines | Conflict between a proposed Round 2 wind farm off the Humber Estuary and a pipeline carrying gas from Norway to Easington that was due to become operational in 2007. | (Unknown) costs involved in resolving the conflict (meetings and consultations) and significant costs of re-location of one or other of the projects |
Aggregates and Offshore Wind | Conflict over future resource allocation for marine aggregates and a proposed wind farm site for Scarweather Sands off South Wales | Loss of marine aggregate resource (of unknown value). |
Aggregates and Pipelines | Assuming a 250 m dredging exclusion zone on either side of the pipeline to protect its integrity and an aggregate resource depth of 2 m, 1 km of pipeline (or cable) laid over an aggregate resource will sterilise 1 million m3 of aggregate resource. | This is equivalent to 1.7 million tonnes of aggregate with a value of £8.5 million at the wharf |
Environmental conflicts |
Fisheries | Concerns over the impact of mobile fishing gear on marine life in Lamlash Bay, Isle of Arran, particularly maerl beds. | Significant costs to the Community of Arran Seabed Trust for ten-year campaign on the issue. Marine planning would provide a structure to enable community input to local decision-making, thereby reducing the costs and length of campaigns. |
Costs of modified, delayed of refused development applications |
Offshore Wind Farms | Significant populations of Common Scoter were identified at a proposed 90-turbine Windfarm project on Shell Flats (Irish Sea) at an advanced stage of development. An alternative site conflicted with maritime navigation | Significant delays to project and costs involved in failed applications and scoping alternative sites. Developer would not have chosen this site had bird population information been available. |
Significant populations of Red Throated Diver were identified for the London Array, an offshore wind farm of up to 341 turbines off the coast of southeast England. | Costs involved in delays to project and additional monitoring studies |
Scarweather Sands Offshore Windfarm and the unknown impacts of construction-related noise on marine mammals in Swansea Bay. | Delays to the issuing of a FEPA construction licence for the development. £500,000 monitoring programme to improve knowledge of porpoise activity in the Bay |
Oil | Application by Melbourne Marine Shipping for ship-to-ship oil transfers in the Firth of Forth, increasing the risk of oil spills by a third in an area considered internationally important for wildlife | Costs of to a number of stakeholders of opposing the application. Such an application might not have been considered under a system of marine spatial planning. |
Ports | Port developments for Mostyn in the Dee Estuary has had ongoing licensing issues since the 1990s regarding the potential to affect the estuary as a whole. | Costs to fund studies of the whole estuary with no sharing of costs among other users of the estuary and regulators. Delays in proposals and extensive consultations regarding maintenance dredging costing more than £100,000. Lost revenue from a proposed Ro-Ro terminal of £1.3 million per annum. Ro-Ro operator (P&O) was awarded damages of £9 million for lost revenue. |
Dibden Bay: an area of land proposed for port development was designated as a SSSI and SPA during the development application process. | Failed application and costs of between £40 and £50 million for the consents and public enquiry process. |
Incompleteness of the SPA network at the time added confusion over nature conservation requirements for a proposed Ro/Ro Terminal in Immingham Outer Harbour | Five-month delay to project and costs of legal challenge to all parties involved. |
Costs of compensatory measures |
Ports | In 2006, ABP implemented two managed realignment schemes as part of an agreed compensation package for port development impacts at Immingham and Hull. The two managed realignment schemes created new intertidal area of around 60ha, to offset losses of intertidal area of up to 30ha from the two port developments. | Costs to ABP of land purchase and construction - £3.2 million Costs to ABP of obtaining planning consent - £123,000 Monitoring costs - £400,000 over 10 years. Costs to Government (including Agencies and local authorities) - approx £36,000. |
Two separate port developments at Lappel Bank and Fagbury Flats resulted in a total loss of 54ha of intertidal mudflats. At the time of granting planning approval, the areas had not been designated as SPAs. Following a judgement in the European Court, the Government committed to providing compensation measures for these losses in accordance with the requirements of the Habitats and Birds Directives. In 2006, the compensation was provided through a managed realignment scheme. | Costs to the developer of EIA at £88,000. Additional costs of £200,000 were incurred for Project Management (part of which relate to consenting and part to scheme implementation. An additional £300,000 was incurred in relation to legal costs. The site selection process incurred a further £500,000. Unquantified costs to Government. Land purchase and construction costs of £6 million. Monitoring costs of £360,000 over 5 years. Total cost of around £7.5 million. |
The extension of the Trinity III terminal, Felixstowe was predicted to result in a number of impacts to the Stour & Orwell Estuaries SPA. Compensation package included the creation of 16ha of intertidal area at Trimley marshes | Construction cost only of Trimley marshes was £1.2 million |
Flood Defence Works | An 80ha managed realignment scheme at Paull Holme Strays on the Humber Estuary was agreed in 2005 as compensation for ongoing and future flood defence works. | Cost to EA of land purchase and construction - £7.5 million |
- public acceptance of planning policies over the years has meant that it has been less necessary to collect data to resolve potential conflicts because they are effectively resolved by the policy;
- patterns of 'ownership' of the marine area differ from those in the terrestrial environment and maritime areas are perceived to be a public rather than a private resource;
- the scope of terrestrial planning is also more limited than the arrangements proposed for the marine area in the Marine Bill. For example, some key areas are not addressed by terrestrial planning such as policies relating to the environmental impacts of agriculture and there are fewer environmental objectives for land compared to the marine environment; and
- the environmental information requirements for marine plans are arguably greater because of the more open and connected nature of marine systems.
Two terrestrial plans provide a potential example of the costs of a national marine plan for Scotland. These are:
- the National Planning Framework for Scotland; and
- the Wales Spatial Plan.
These plans have a similar scope to that for marine planning, with a focus on sustainable development and are based on broad economic, social and environmental objectives. These plans are described Tables 4.7 and 4.8.
The tasks likely to be involved in preparing a national Scottish marine plan include:
- collation and management of data;
- plan preparation, including setting a marine policy statement, national marine objectives, policies and priorities;
- appraisal of the impacts of the plan;
- implementation of the plan; and
- review of the plan every five years.
Table 4.7: The National Planning Framework for Scotland
The Second National Planning Framework ( NPF) for Scotland aims to set out a strategy for Scotland's spatial development to 2030, providing a national context for development plans and planning decisions and helping to inform the wider programmes of government, public agencies and local authorities. The Framework will play a key role in setting out, co-ordinating and integrating strategic development priorities. The legislation requires planning authorities to take the Framework into account in preparing development plans and it will be a material consideration in determining planning applications. Main objectives are for a Scotland that is wealthier and fairer, greener, safer and stronger, smarter and healthier. Preparation of the plan involves the following tasks and timing over almost two years: - initial engagement on scope and content of the NPF: February-October 2007;
- the issue of NPF2: Discussion Draft;
- revision in the light of reaction to the discussion draft: Spring 2008
- scrutiny of a final draft in Parliament: Autumn 2008
- final considerations and publication of the NPF: Late 2008
- monitoring and evaluation: Ongoing
The NPF2 team comprises five full-time equivalents ( FTEs): - One Assistant Chief Planner
- 2 Senior Planners
- 1 SEA specialist
- 1 administrative assistant
Based on the Scottish Government pay band ranges for 20061, the average staff costs per year of the team is likely to be around £175,000. This excludes the costs of overheads. No public inquiry is required for the NPF. It is submitted to parliament for 60 days' scrutiny and then goes out for public consultation. Under the Planning etc. (Scotland) Bill (2005), Scottish Ministers are to consult such persons or bodies as they consider appropriate in preparing or revising the national planning framework and may appoint a person to conduct an assessment of a planning authority's performance and decision-making. It is likely that a similar process will be adopted for the national marine plan. |
Notes: 1. Scottish Executive. 2008. Equal Pay Review of The Scottish Government Main Bargaining Unit Pay System: Fourth Report 2006-07 |
Table 4.8: The Wales Spatial Plan
The Wales Spatial Plan (WSP) followed a similar process of development. The WSP was adopted by the Welsh Assembly Government in November 2004 with a plan period of 20 years. An SEA and Sustainability Appraisal was not required at the time. Scoping for a combined SEA and SA began in 2005 and was due to be published in 2008. The costs of the plan, from 2001 to the publication of the plan in 2004, were: - Preparatory research: £120,000
- Consultation document production: £40,000
- Consultation process: £50,000
- Final document production: £30,000
- Staff costs (based on a team of three for two years): £300,000
- Total cost: £540,000
Since its publication, there has been ongoing work on the Wales Spatial Plan. The core team has been expanded and 6 regional co-ordinators are currently developing the work further on a regional basis. The existing team structure comprises: - 0.5 Head of Division
- 1 Grade 7
- 5 regional Spatial Plan Coordinators
- 1 Senior Executive Officer
- 1.5 Executive Officer
- 1 team support
- 0.5 personal assistant
The total annual staff cost for the Wales Spatial Plan team, estimated by averaging across the 2006 pay scales and including overheads at 87% of staff costs, is £745,500. The Wales Spatial Plan budget has been set at £650,000 per year since 2005. However, it should be noted that the budget has been under-spent in each year. The under-spend is estimated to be around £100,000 for 2007 - 2008. This is due to the co-financing of posts and projects with the Department for Enterprise, Innovation, and Networks (DEIN), which delivers the economic and transport agendas in Wales. |
These tasks would largely be carried out by the plan-making body (potentially Marine Scotland, see Section 7) but there would also be costs to other stakeholders (including government departments) in responding to the various consultation documents associated with the plan. Scottish Ministers anticipate that it will take somewhere between 12 to 18 months to draft marine objectives and construct a national marine plan. Allowing time for consultation suggests that the first Plan and objectives could take up to two years to produce.
Data Management
Effective management of the marine environment, both at a national level and local level, is dependent on sound science. Marine planning is likely to require spatially expressed information on a range of marine resources, including historic marine resources, and activities. Although data will also play a role in assisting decision-making in the licensing system and managing nature conservation interests, the costs for both data collation and management are assessed here.
According to the UK Department for Business, Enterprise and Regulatory Reform 8, the average cost for each of the eight offshore energy SEAs (including oil and gas and, more recently, offshore wind) which have been carried out since 1999, and which cover the whole of UK continental shelf, was £2.4 million. This included data collection, which may represent up to 90% of the SEA costs. A significant amount of broad-scale information, including information on the historic marine environment, is therefore already provided through SEA ( SEA regions 4 to 7 include Scottish waters out to 12 nm from the baseline) and other data initiatives.
The UK Marine Monitoring and Assessment Strategy ( UKMMAS) is putting in place arrangements to improve the co-ordination and reporting of marine assessments, to ensure that they are fit for purpose and to inform progress towards achievement of marine objectives. Furthermore, the Marine Environmental Data and Information network ( MEDIN) aims to deliver a data management system, supported within Scotland by funds of £150,000 per year from the Scottish Executive. As part of this initiative, a Geographic Information System ( GIS) has been identified as a priority providing a front end portal for users to access data relevant to their areas of interest. These costs may therefore be considered to be part of the baseline.
New data collection is likely to focus on informing areas where potential conflicts are anticipated or where there are gaps. The amount of information required will therefore be largely dependent on the issues and priorities involved in the planning system and are likely to be specific to each Scottish region. The costs of new data collection are therefore included within the costs of local plan preparation (see Table 4.15 below). However, a cost of £150,000 per year to support a national database has been assumed as part of the costs of the National Plan.
Plan Preparation
The costs presented in Table 4.9 are the direct costs to Marine Scotland for the preparation of a national marine plan. We have assumed that the process and costs are likely to be comparable to that required for WSP. The core team required to develop a national marine plan is likely to be comparable to that for NPF (Table 4.7), excluding the costs of an SEA specialist (the costs of SEA are considered separately below).
Table 4.9: Potential Costs of Preparing the Scottish National Marine Plan 1
Activity | Cost |
|---|
Preparatory research | £120,000 |
Consultation document production | £40,000 |
Consultation process | £50,000 |
Final document production | £30,000 |
Staff costs (based on a core team of 4): - Assistant Chief Planner (£53,000) - 2 x Senior Planners (2 x £31,900) - Administration assistant (£15,100) | £264,000 |
Total cost of plan preparation | £504,000 |
Notes 1. One-off cost, spread over two years 2. Based on a core team of four, including overheads, for two years |
The cost of developing objectives and policies for sustainable development and nature conservation is assumed to be included in the plan process above. This assessment does not differentiate between the development of objectives for the plan and those that may be required under other UK-level and international obligations (e.g. MSFD). Extensive work has already been carried out on marine ecosystem objectives as part of the MSFD and UKMMAS initiatives. Therefore, there may be cost savings in the development of objectives.
Appraisal of the Impacts of the Plan ( SEA)
As for the NPF, an SEA of the Scottish marine plan will be required by the Environmental Assessment (Scotland) Act 2005. SEA is a systematic method for considering the likely effects of plans, programme and strategies on the environment. SEA integrates environmental factors into policy preparation and decision-making. It also has an important role to play in increasing public participation and facilitating openness and transparency in decision-making. From experience with the Wales Spatial Plan and its associated Local Area Statements, it is advisable that SEA is started early enough in the planning process in order to influence development and that the same processes for assessment are used throughout 9.
As noted above, the average cost for each of the eight offshore energy SEAs, which cover the whole of UK continental shelf, was £2.4 million per SEA. If the data collection element is removed, an SEA can be estimated to cost £240,000. The full RIA10 undertaken for transposing the SEA Directive into UK law provides an estimate of £50,000 for an SEA of a regional (terrestrial) plan. The Strategic Assessment for the South West Regional Spatial Strategy was estimated at £70,000 - £80,000.
An SEA of a national marine plan will require more detailed consultation and analysis than that for a regional SEA or terrestrial SA. Taking these examples into account, and allowing for the scope of a national plan and the complexity of marine systems, £250,000 for an SEA at a national plan level (covering staff costs of £42,400 and consultation) provides a more realistic and conservative estimate.
Annual Running Costs
The Scottish Government has suggested that 30 to 35 staff would be required overall to resource planning. This includes two coordinators per local plan (i.e. 18-26, costs allocated to local planning below) leaving a small core for national and international planning (i.e. 9-12 staff). Some of these staff will be involved in the ongoing review process. We have therefore assumed that the team required to implement the Scottish national marine plan is likely to be closer to that for the WSP and will consist of a dedicated team of six (Table 4.8). The costs are set out in Table 4.10, based on Scottish Government pay band ranges for 2006 11.
Table 4.10: Annual Costs of the Possible National Scottish Marine Planning Team 1
Team member 2 | SE Pay Band | Total Average pay |
|---|
0.5 x Head of Division | C3 | £26,500 |
2 x Senior Planners | B3 | £63,800 |
2 x Planners | B1 | £40,200 |
1 x Administrative Assistant | A3 | £15,100 |
0.5 x Personal Assistant | A3 | £7,600 |
Salary cost per year | | £153,200 |
Overheads (87% of staff costs 3) | | £133,300 |
Total annual cost (2006 salaries) | | £286,500 |
Notes: 1. Based on 2006 salary scales 2. Four staff to prepare the plan (see Table 4.9); six to implement the plan; remaining staff will participate in reviews and international planning activities. 3. Based on DCLG 2006 overheads as a percentage of staff costs |
Review of the National Plan
Scottish Ministers intend to review and revise the National Marine Plan and objectives on a five-yearly cycle. The UK Marine Bill RIA assumed that review of plans will involve a full repetition of the process involved in initial plan development and is likely to include an SEA.
The full cost of plan preparation probably overstates the more specific requirements of plan revision. However, in the absence of relevant data this is provided as a maximum estimate, i.e. £750,000 per review including SEA. Assuming that it will take two years to develop the plan, over a period of twenty years there will be two full reviews.
Overall Costs to Government of National Plan
A summary of these costs over the 20-year period of this impact assessment is presented in Table 4.11. Further detail of the timing of costs is given in Annex 2.
Table 4.11: Summary of illustrative costs of National Scottish Marine Plans over 20 years, (Present Value Costs, 2008 prices)
Cost category | Costs | Assumptions and Timeline |
|---|
Data management | £2,205,000 | £150,000 per year from 2009; ongoing |
Initial plan preparation | £479,000 | £252,000 per year 2009-2010 |
Initial SEA | £237,000 | £125,000 per year 2009 - 2010 |
Running costs | £3,667,000 | £286,500 per year from 2011; ongoing |
Review of plan | £730,000 | 2 reviews @ £504,00 in 2015 and 2020 |
Total discounted cost | £7,317,000 |
Average Annual costs | £498,000 |
Notes *: Rounded to nearest thousand; figures may not add due to rounding. |
Although the specific format of local marine planning has not been prescribed it is likely to be developed at the scale of 9 - 13 Scottish Marine Regions ( SMRs) and involve the following tasks:
- setting up of steering groups or SMR boards;
- plan preparation: setting local marine objectives, policies and priorities;
- appraisal of the impacts of the plan ( SEA);
- public enquiry;
- data management;
- ongoing operation; and
- plan review.
We have assumed that the focus of these plans will be out to the limit of Scottish territorial waters, on the basis that human pressures are most concentrated in this area. The national marine plan could be used to manage the generally lower levels of pressure offshore.
A steering group or board is likely to be appointed to deliver local planning and may include local authorities, marine industries, Local Coastal Partnerships, Inshore Fisheries Groups, RBMP Area Advisory Groups and various recreational interests.
It is not yet clear who will meet the full cost of developing local plans. We have assumed here that the costs of setting up and running boards for SMRs will be met by the Scottish Government.
The costs presented in this section represent the direct costs for the creation and operation of local marine plans. Examples of costs are drawn from the costs involved in comparable existing plans such as:
- Irish Sea Marine Spatial Planning Pilot ( MSPP);
- River Basin Management Plans ( RBMP);
- English Regional Spatial Strategies ( RSS);
- inshore Fisheries Groups;
- the Sustainable Scottish Marine Environment Initiatives ( SSMEIs), particularly those in the Clyde;
- the Scottish Coastal Forum;
- the Solway Local Partnership; and
- Area Advisory Groups ( AAGs) under the WFD12.
Setting-up and Running of SMR Boards
Possible models for the SMR Boards include the Boards of National Park Authorities and liaison panels for River Basin Management Plans ( RBMP) under the Water Framework Directive.
The Board of the National Park Authority is the principle decision-making body. The Boards are typically composed of locally elected representatives and Scottish ministerial appointments. The Loch Lomond & the Trossachs National Park Board has 25 members and cost £250,000 to run in 2004/05 13. SNH notes that the composition of the SMR Board will be important and should balance the need for local representation with the need to include expertise and experience on inshore fisheries management, aquaculture and maritime shipping/ports.
The Environment Agency estimated that it incurs costs of £64,000 (personal communication, 2006) to set up each liaison panel associated with RBMPs. This includes the costs of venues, catering, running stakeholder workshops and training courses for staff. Liaison panels have no more than 15 members, except the cross border panels, which may have up to 18. These costs do not take account of time contributed by existing Environment Agency staff or overheads, nor do they cover the costs of developing communication strategies, thus they may represent an under estimate.
For local marine planning, there may be opportunities for cost savings where existing coastal partnerships are already well-developed, e.g. the Solway Local Partnership and fora established for the SSMEIs. Therefore, a cost of £100,000 per year is estimated for each SMR Board to cover workshops, training and annual running.
Plan Preparation: Setting Local Marine Objectives, Policies and Priorities
Estimates of the cost of plan preparation were drawn from experiences with the Clyde SSMEI Pilot Project, the Highland Regional Council and the Marine Spatial Planning Pilot ( MSPP) in the Irish Sea and the Highland Regional Council, as shown in Table 4.12.
Table 4.12: Examples of the Costs of Local Plan Preparation
Example | Cost |
|---|
SSMEI Clyde Pilot | Total budget over the last three years is £315,000 (pers comm.). However, there are considerable differences between an SSMEI and a statutory plan at a local level. The SSMEI Pilots we instigated by the Scottish Executive in 2002 as a testing process for the management tools available for marine planning. These first plans are not statutory and will not cover the full scope required under the proposed level of planning in the marine bill due to resource constraints. The SSMEI's are also dependent on in-kind contributions from involved agencies and existing voluntary partnership schemes that are not expressed in their running costs. |
|---|
Highlands Council | Spends £11 million annually on plan-making and development control (plan-making accounts for approximately half of the expenditure, i.e. £5.5 million). The Council is responsible for managing 26,000 km2 of land, representing 33% of Scotland. If the cost is extrapolated to the whole of Scotland, and divided by 12 (for the average number of local plans), this indicates a possible cost per plan of £1.38 million |
|---|
Irish Sea MSPP | the Irish Sea MSPP estimated costs for a non-binding plan to be £1 million and assumed that a binding plan would cost twice as much to prepare (£2 million) due to the costs of greater stakeholder consultation, examination in public and the need to provide a robust mechanism for delivering a binding plan. These additional costs of binding plans are covered separately here from plan preparation, therefore the costs to government of plan preparation alone, are unlikely to vary between statutory and non-statutory plans. |
|---|
Given the examples above, it seems likely that the cost of plan preparation could range from £0.75m to £1.5m, covering the broad range of planning requirements in the different Scottish marine regions. Although each plan is likely to be developed by an independent SMR Board, it is likely that overall direction will come from the national plan-making body (potentially Marine Scotland - see section 7). There are therefore likely to be efficiency savings in plan development over time from the increase in experience within the plan-making body. This saving could amount to around 10%, potentially reducing the cost of this component to £680,000 to £1.35 million per plan.
Public Inquiry
Public Inquiry is a mechanism to allow interested parties to raise objections to proposals contained in local terrestrial plans in Scotland. An approach similar to this process could be incorporated into marine planning in Scotland. In order for the process to be unbiased and effective, there needs to be sufficient separation between the original plan-makers and those undertaking the review. It is our understanding that in Scotland, the Scottish Executive Inquiry Reporter's Unit ( SEIRU) or Secretary of State 14 meets the cost of Public Inquiries on plans developed by local councils and appoints an independent inspector. It is likely that a unit such as SEIRU will also be responsible for running public inquiry on marine plans.
A comparison may be provided by the Examination in public (EiP) process for Regional Spatial Strategies ( RSS) in England. The responsibility for running the EiP on RSS is borne by the Planning Inspectorate ( PINS). Examples of the costs are provided in Table 4.13 and are based on discussions with a senior PINS official.
However, the scope of such an inquiry for a local marine plan will be somewhat different from that of a local terrestrial plan. While marine bodies are likely to deal with geographical areas of a comparable size to a terrestrial region, the issues that they deal with are unlikely to be as fine grained and detailed, although they could be more significant, and the number of interested parties is expected to be considerably fewer. It is therefore expected that the costs of running an inquiry for a local marine plan will be at the bottom end of the range in Table 4.13.
Table 4.13: Estimated Average Costs to the Planning Inspectorate of Examinations in Public for English Regional Spatial Strategies
Activity | Cost per Strategy |
|---|
Contribution to the cost of publishing the draft report | £30,000 |
Recruiting the panel | £10,000 |
Accommodation: hire of the venue where the EiP is to take place (costs for England outside SE) | £60,000 - £90,000 3 |
Panel fees | £90,000 - £120,000 4 |
Producing panel report | £30,000 - £40,000 |
Publishing changes to strategy | £30,000 |
Publishing final report | £60,000 - £70,000 |
Total | £310,000 - £390,000 |
Notes: 1. For the East Midlands 2. £10,000 to £15,000 per week for six weeks 3. £30-40,000 /quarter for about three quarters |
Source: Planning Inspectorate estimates |
In addition, the SMR Boards (or the plan-making body) will incur costs for appearing at the Public Inquiry, addressing the consultation responses, undertaking further research and evidence gathering where necessary. The cost to the South West Regional Authority of this activity for EiP was estimated at £600,000. Similar costs could be incurred in Scotland; if so, this could be a significant additional cost for the SMR boards or the plan-making body.
Appraisal of the Impacts of the Plan ( SEA)
As noted for the national marine plan, the costs of SEA can range from £70,000 to £240,000. At a local level, the same process will be required as the SEA for the national plan. Assuming some cost savings from experience gained in the process, an estimate of £200,000 per SEA is used here.
Data Management
As noted above, SEAs are likely to support a significant amount (£2.2 million per SEA) of the data collation required for marine planning. Data management is likely to take place at a national level.
Based on experience with the Marine Spatial Planning Pilot in the Irish Sea and other databases, the costs of establishing and maintaining a data and information system, which would be needed to support all the proposals in the proposed Scottish Marine Bill, including planning, could range from £200,000 to £10.5 million.
Taking into account the large amount of data provided through existing SEAs, an additional initial investment of £1 million per region is considered a sound estimate.
Annual Running Costs
As noted in relation to the national marine plan above, the Scottish Executive suggests that two full-time equivalents would be required to coordinate each local plan. These staff would be involved in preparation and implementation of the plan. The annual running costs of other local planning initiatives vary considerably. Examples are given in Table 4.14.
Table 4.14: Examples of Running Costs of Local Planning Initiatives
The Highland Council is responsible for managing 26,000 km2 of land, representing 33% of Scotland. The Council has 211 staff and spends £11 million annually on plan-making and development control (plan-making accounts for approximately half of the expenditure). This equates to expenditure of approximately £52,000 per staff member. The expenditure for the Loch Lomond & the Trossachs National Park in the 2005/06 financial year was £7.4 million, based on an average of 133 (full-time equivalent) staff. Approximately 16 of these are involved planning. Therefore, the running costs for the planning component are estimated at £892,000. This is partly funded by income of about £170,000 from planning fees. Overall, running costs for planning equate to £56,000 per staff member. The Solway Local Partnership is a charity overseen by four trustees and is open to everyone interested in the sustainable management of the Solway. Total incoming resources for 2007 were £115,000 from charitable activities (in 2006 this was £116,000). Some of this is allocated to specific research projects and data collation. It also does not include costs for a secretariat, which are hosted and employed by Solway Heritage. The Lake District National Park has 5 staff in development control and 4 in planning policy and spends £1.3million on development control and £590,000 on forward planning annually. Respectively, this equates to expenditure of £260,000 and £147,500 per staff member. The marine spatial planning pilot for the Irish Sea estimated the ongoing administrative costs for a binding plan at £20,000 per plan, per year. This cost would only be incurred after plan development, i.e. after the first two years. The Scottish Coastal Forum supports nine local coastal fora that cover much of the Scottish Coastline. To implement coastal planning in Scotland, they advise that core specialist staff costs should be covered by an annual grant from the Executive of up to £50,000 per unit. This core funding could be met by match funding for specific projects from more local sources or organisations, potentially giving each unit an annual budget of £100,000 to deliver Integrated Coastal Zone Management in their own area. Currently the SCF runs on a budget of £30,000 for the employment of a part-time Officer and £12,000 for additional projects such as training and running conferences (pers comm., 2008). If a full time equivalent staff member was required at Scottish Government B3 level, with associated pensions and other benefits, an additional £10,000 would be required for staff costs (pers comm., 2008). This equates to a total of £52,000 per staff member. Three Inshore Fisheries Group ( IFG) pilots in the Outer Hebrides, the Clyde and the South East have been set up and backed by a total of £300,000 funding. The role of the IFGs is to represent the combined interests of fishermen in their respective areas, to develop management plans for the enhancement and development of inshore fisheries and to generate legislative management proposals. However, IFGs have no statutory duties or powers and it is unclear how far current funding goes towards covering their full costs. |
The annual running costs, as shown in Table 4.14, range from £20,000 to £827,000 per organisation. Some of the differences depend on whether they include or exclude costs for data collation and research, plan preparation and review, and implementation and enforcement. Costs per staff member range from £52,000 to £56,000. With two staff members estimated to be required to coordinate local planning, it is likely that £100,000 per year per plan will be needed for annual running, implementation and enforcement.
Plan Review
Scottish Ministers intend to set out the timescales for SMRs to develop and review local plans. However, in order to ensure integration with the national plan they are likely to be reviewed on a similar timescale, i.e. every five years.
At this stage, there is no basis for estimating what the costs of such reviews could be, as it will depend on the individual circumstances of each marine plan. The costs could potentially be quite significant, especially in the early years of marine planning, as the process 'beds down'. If major changes to the plan are required there could be a need for widespread consultation and even a further Public Inquiry. For example, the Glasgow and Clyde Valley Structure Plan required a formal alteration in 2005. The Firth of Clyde Marine Spatial Plan has a 20-year vision and sets out a five-year framework to reach this vision. It is expected that this plan will be reviewed and rewritten after five years.
The UK Marine Bill RIA suggested that review of plans would involve a full repetition of the process involved in initial plan development. However, these plans involved a significant data component. In reality, it is unlikely that data costs will form a significant component of the review process as data will be updated regularly as part of the ongoing management and monitoring of marine objectives. Furthermore, the full cost of plan preparation overstates the more specific requirements of plan revision. If simple amendments are required, such as later on in the planning process, cost of plan revision of local plans may therefore be as low as 20 percent of the original plan preparation cost.
Assuming that it will take two years to develop the plan, over a period of twenty years three full reviews will occur. We estimate that the first review may be quite similar in cost to the original plan preparation but that later reviews will be less involved. Therefore, costs are estimated at roughly 50% of full plan preparation, i.e. £680,000 to £1.35 million.
Overall Costs to Government of Local Plans
Based on the discussions and cost examples above, Table 4.15 provides a minimum and maximum total cost estimate for the provision of local plans, based on 9 to 13 SMR plans respectively; Annex 2 provides further detail on the timing of the costs.
Table 4.15 - Summary of Illustrative Costs of Local Planning (Present Value Costs, 2008 prices)
| Assumptions, including cost per plan | 9 plans, lower bound 1 | 13 plans , upper bound 2 |
|---|
Initial plan preparation | - Plan preparation £680,000 - £1,350,000
- Public Inquiry - £310,000
- Appraisal of the plan ( SEA): £200,000
- Data collation; £1,000,000
Total costs for initial plan preparation: £2,190,000 - £2,860,000, incurred in first two years only for each plan Assumes plan preparation is phased, with additional plans prepared every 2 years | £14,355,000 | £28,243,000 |
|---|
Implementation | - SMR Boards: £100,000
- Plan management, implementation and enforcement: £100,000
Total costs of implementation: £200,000 per plan per year. Costs incurred from 2011, with the number of plans to be implemented increased every two years | £17,683,000 | £26,893,000 |
|---|
Reviews | Total Costs for 2 reviews for each plan over 18 years (every 5 years after initial plan.) at £680,000 - £1,350,000; | £3,936,000 | £10,987,000 |
|---|
Total discounted cost | £35,974,000 | £66,123,000 |
|---|
Average annual costs | £2,448,000 | £4,499,000 |
|---|
Notes 1: Assumes 2 plans prepared every 2 years, at lower bound of estimated costs range 2: Assumes 3 plans prepared every 2 years, at higher bound of estimated costs range |
Historic Scotland (an executive agency of Scottish Government) has identified that provision of advice on the development, implementation and review of a national marine plan to ensure that it includes satisfactory consideration for the historic environment, advising on SEAs of the national and regional plans (Historic Scotland is a consultation authority under SEA) would cost the Scottish Government around £50,000 per year.
Costs to Industry
As one of the aims of a system of marine planning is to provide better guidance to local regulators, industry is likely to benefit from the proposals. However, some industries have expressed concern that the implementation of a new system of marine planning might have the potential to delay development proposals, particularly during periods of plan preparation. A well-designed planning system should address the needs of all users of the marine environment, including industry, in resolving resource conflicts. Nevertheless, clear transitional arrangements will be necessary to ensure that delays to decision making are avoided.
A planning system may impose restrictions over currently unregulated industry activities, such as algal harvesting and tourism. Therefore, there is the potential for greater restrictions to be imposed on such activities, resulting in further costs for the industry sectors affected. This can be addressed, however, by ensuring that industry is engaged in the planning process, so that such costs can be identified and mitigated as far as possible.
Costs to Others
The direct costs to other stakeholders of marine planning will arise from their participation in the planning process (e.g. in responding to consultations and participating in consideration of plans). The size of these costs will be dependent on how far a plan affects their individual interests and how far they wish to engage in the process.
Historic Scotland has also identified that the development and implementation by Scottish Marine Regions of regional plans should include a budget to allow for sourcing of adequate archaeological advice and information and has suggested that it would be prudent to earmark a figure of £75,000-£140,000 per year for a period of 10 years in the first instance across Scotland (i.e. if there are ten Scottish Marine Regions, this would equate to £7,500 to £14,000 per year for each). If this budget is not built into the direct cost of regional marine planning, there will be a cost to others (e.g. local authority archaeology services) of this magnitude in order to engage with the regional marine planning process.
SMR Boards
Representatives on SMR Boards may include those from local authorities, marine industries, Local Coastal Partnerships, Inshore Fisheries Groups, RBMP Area Advisory Groups and various recreational interests. There will be costs to these groups as part of their role on the board.
However, it may be argued that these functions are already carried out as part of the current marine management regime and the costs associated with this are therefore largely part of the baseline. Furthermore, as marine planning aims to streamline the management process, there may be cost savings. For example, it is possible that, with a development strategy in place, representatives will have fewer contentious development applications to respond to.
Public Inquiry
Costs to local authorities and other stakeholders of the public enquiry can be estimated by the time incurred by participants. The number of participants varies considerably, depending on the number of interested parties and issues raised. Examples of the possible costs include:
- the East of England EiP lasted for 47 days and considered nine matters. There were 18 key stakeholders involved in the consultation process throughout the preparation of the RSS and about 28 participants for each of the matters at the EiP (a total of 252 participants). If these participants each attended for two days on average (a total of 500 person-days), and assuming a daily cost of £500, the cost could amount to £250,000;
- the South West EiP List of Matters and Participants identified nine matters to be discussed; 41 local planning authorities were invited to attend, most of these will be attending for 1-2 days and will be responding to one matter. This amounts to around 54 days of the local planning authorities' time. In addition to this, representatives from the local planning authorities will also be invited to attend some matters on behalf of the strategic planning authorities. Three strategic planning authorities are invited to attend, and this amounts to 63 days. The cost to local planning authorities for participating at an EiP therefore totals 117 days. Assuming a daily staff cost of £500, this is equivalent to a cost of £58,500. There are also additional costs for research and preparing for the EiP etc; however, it is difficult to separate these costs as separate items from the authorities' everyday planning functions.
The costs to participants in public enquiries on marine plans in Scotland could be of a similar order. However, it could be argued that costs of participating in the planning process will be offset by savings in the time taken in responding to contentious development applications.
Social and Environmental Costs
These costs are expected to be minimal as the aim of Marine Planning is to provide benefits for society and the environment from more sustainable management of the marine and coastal environment. However, restriction and zoning measures associated with planning may have implications for recreational activities and the siting of marine protected areas. These impacts are assessed further in Chapter 6 on Marine Nature Conservation.
4.5 Small/Micro Firms Impact Assessment
Almost all of the industry sectors identified in section 4.2 include some small and micro-sized firms.
As one of the aims of a system of marine planning is to provide better guidance to local regulators and industry, small firms are likely to benefit from the proposals.
A well-designed planning system should address the needs of all users of the marine environment, including small-scale activities, in resolving resource conflicts. This may lead to better representation of small firms that tend to be overlooked in such negotiations, particularly if they are not members of a relevant industry body or association.
However, a planning system may impose restrictions over currently unregulated activities, such as algal harvesting and tourism. Many of these activities will be dominated by small businesses. Therefore, there is the potential for greater restrictions to be imposed on such activities resulting in further costs for small businesses. This can be addressed, however, by ensuring that small businesses are engaged in the planning process, so that such costs can be identified and mitigated as far as possible.
4.6 Competition Assessment
The benefits of a system of marine spatial planning include:
- increased transparency from clear policies
- reducing the uncertainty to developers in the marine area,
- allowing the needs of all users to be considered, and
- equal access to information and data on the marine area.
All of these benefits are likely to have a positive impact on competition, by producing a more equitable situation both across and within different industry sectors.
4.7 Enforcement, Sanctions and Monitoring
Responsibility for compliance, monitoring and enforcement of plans would be carried out by the plan-making body, which could be Marine Scotland (see Section 7). Reserved issues would continue to be addressed by the respective departments within the UK Government. The plan would be delivered through the licensing system (see Section 5) and measures for nature conservation (see Section 6).
4.8 Summary
The present value benefits and costs of the two options are summarised in Table 4.16. The annual benefits 15 and costs are presented in Table 4.17.
Table 4.18 summarises the ability of the two options to meet the overall goals of the Scottish Marine Strategy
Table 4.16: Summary of the Total Present Value Costs and Benefits of Marine Planning in Scotland
| Option 1: No change | Option 2: Statutory Planning System |
|---|
Benefits | - Short term economic benefits in that businesses, government, other public bodies and marine users will not have to change their behaviour.
- No environmental or social benefits
| - Economic benefit of conflict avoidance: £294 million 1 if it resulted in a 1% increase in value of the marine economy; £5.5 million 1 if it resulted in more rapid approval of marine energy production
- Environmental benefits: unquantifiable, but could be significant
- Social benefits: improved opportunity for stakeholder involvement
|
|---|
Costs (to Scottish Government) | - No investment required
- Potential costs from action required to address the risks
| - International Planning: no additional costs
- National Plan: £7.3 million 1
- Local Planning: £36 million to £66.1 million 1 for 9 to 13 plans
- Historic Scotland has identified potential additional costs of £1.1m to £1.6m, discounted over 10 years
|
|---|
Costs (to Local authorities) | - Unquantified costs in resolving disputes
| - Unquantified costs of participation in local planning boards and public inquiries (likely to be offset by reduced costs of dealing with applications)
|
|---|
Costs (to other organisations) | - Costs of campaigning against inappropriate developments
| - Limited costs for participation in planning process
|
|---|
Costs (to industry) | - Potential costs to developers from existing conflicts, delays and compensation could be significant - up to £50m per development
| - Possible costs to marine environment users from restrictions on activities in specific locations, but can be mitigated by inclusion of industry in planning process
- Participation in planning process (local government and other stakeholders): cost-neutral overall
|
|---|
Costs (to other stakeholders) | - Loss of employment if conflicts and uncertainty restrict sustainable development of the marine economy
| - Limited costs for participation in planning process
|
|---|
Costs (environmental) | - Failure to meet environmental objectives
| |
|---|
Notes: 1. Net present value costs over 20 years |
Table 4.17: Summary of the Annual Costs and Benefits of Marine Planning in Scotland
| Option 1: No change | Option 2: Statutory Planning System |
|---|
Benefits | - Short term economic benefits in that businesses, government, other public bodies and marine users will not have to change their behaviour.
- No environmental or social benefits
| - Unquantified (but potentially significant) benefits from reduced conflict
- Environmental benefits: unquantifiable, but could be significant
- Social benefits: improved opportunity for stakeholder involvement
|
|---|
Costs (to Scottish Government) | - No investment required
- Potential costs from action required to address the risks
| - International Planning: no additional costs
- £498,000 for national plan;
- £2.5m to £4.5million for 9 to 13 plans
- Historic Scotland has identified possible additional costs of £125,000 to £190,000 per year
|
|---|
Costs (to Local authorities) | - Unquantified costs in resolving disputes
| - Unquantified costs of participation in local planning boards and public inquiries (likely to be offset by reduced costs of dealing with applications)
|
|---|
Costs (to other organisations) | - Costs of campaigning against inappropriate developments
| - Limited costs for participation in planning process
|
|---|
Costs (to industry) | - Potential costs to developers from existing conflicts, delays and compensation could be significant - up to £50m per development
| - Possible costs to marine environment users from restrictions on activities in specific locations, but can be mitigated by inclusion of industry in planning process
- Participation in planning process (local government and other stakeholders): cost-neutral overall
|
|---|
Costs (to other stakeholders) | - Loss of employment if conflicts and uncertainty restrict sustainable development of the marine economy
| - Limited costs for participation in planning process
|
|---|
Costs (environmental) | - Failure to meet environmental objectives
| |
|---|
Table 4.18: Ability of the Options to Meet the Objectives of the Scottish Marine Strategy
Objective | Option 1: No change | Option 2: Statutory Planning System |
Ability to meet international obligations (legal) | Low: planning would only exist beyond 12 nm (due to UK-level planning). Given that the majority of activities occur within 3 nm of the coast, such an approach is unlikely to sit well with proposed EU policy for maritime planning. | High: a tiered system of planning supported by objectives would meet proposed EU Integrated Maritime policy and help to deliver the aims of the MSFD for GES. |
Protection of ecosystem services | Medium: objectives for protecting ecosystem services exist at a high level, delivered through licensing system. Protection from unregulated activities reliant on voluntary codes of practice. | High: tiered system of objectives, performance indicators, targets and actions ensures a high level of protection at all levels. |
Certainty with which nature conservation requirements are delivered | Low: High-level objectives exist. Delivery of these would rely on the licensing system and levels of understanding of requirements may vary for each sector. | High: a statutory and tiered system of objectives provides for greater certainty in the delivery of and improved understanding of conservation requirements. |
Ease of and clarity for decision-making | Low: no prioritisation of national objectives; Decision makers lack guidance on how to reconcile conflicting objectives locally | High: more local objectives provide better guidance for decision makers; zoning system provides a clear steer to decision makers on which objectives should have priority in a given area |
Sustainable development and management of economic resources | Low: Lack of targeting may impose disproportionate costs | High: increasing scope for targeted decision making to ensure that benefits are proportionate to costs |
Continuity with terrestrial forms of planning | Low: Current approach is not consistent with hierarchical system adopted for terrestrial planning. | High: multi-level approach would generally be compatible with terrestrial planning system and the ICZM approach would help to ensure integration of different policies at the land-sea interface, e.g. River Basin Management Plans and Shoreline Management Plans. |
Effectiveness of arrangements across administrative boundaries | Low: current system unlikely to be consistent with anticipated approaches for English, Northern Irish or UK offshore waters | High: would generally be compatible with anticipated approaches for English and Northern Irish territorial and UK offshore waters. Clear boundaries and policies will assist cross-border negotiations. |
Degree of integration among differing policies | Low: system dependent on separate economic, social and environmental policies with no system for integrating them. | High: Development of a marine plan would need to consider and integrate a number of different economic, social and environmental policies. These would likely be expressed through high-level objectives. |
Community Involvement | Low: limited scope for community involvement as objectives and targets set at national/regional level. | High: improved opportunity for local engagement in the development of local objectives and zoning proposals. |
Acceptability to stakeholders | Low: a prescriptive set of objectives determined at a UK and EU level may be perceived as predetermining the balance of sustainable development and may not be acceptable to economic, environmental and social interests. | Medium: acceptability may be determined by the outcomes of the plan (i.e. do plan policies, objectives or targets negatively affect economic or social interests). A timely and transparent stakeholder process may help to support acceptance of the plan. |
Flexibility - scope for changing objectives and boundaries | Low: dependence on the licensing system for delivering objectives means that flexibility would depend on individual sectoral review processes. | High: the planning process will provide the necessary flexibility to amend objectives and boundaries through the periodic review process. |
Facilitation of cumulative effects and environmental capacity assessments | Medium: national/regional objectives provide a framework for addressing environmental capacity limits. | High: this framework may be supported by more local objectives/zoning systems in Option 2. |
Ability to address unregulated activities | Low: unlikely to be an appropriate scale at which to advise on the control of unregulated activities. | High: advisory policies for unregulated activities could be included in local marine plans. |
Impacts of devolved/reserved responsibilities | Medium: regardless of devolution settlements, Scotland will still need to engage with the UK Government and the EU (e.g. Common Fisheries Policies, UNCLOS, IMO & OSPAR) over planning policies to ensure integration and continuity across borders. | High: may facilitate negotiations by explicitly stating a strategy for Scotland's waters. |
Likely information requirements | Low: no prioritisation of objectives. Information requirements may be significantly increased if it is necessary to justify a set of prescriptive marine environmental objectives. | High: broad scale information would be required to meet MSFD & agreed UK-level objectives. A potentially significant amount of additional information may be required to support local policies, objectives and targets. |