10 Next Steps
10.1 Next Steps
Table 10.1 below highlights key outstanding stages in the SEA process and the development of the NAPs.
Table 10.1 Next Steps
Task / Milestone | Description | Expected Date |
|---|
Public Consultation | The draft Action Plans and the Environmental Report will be published for public consultation for a period of 8 weeks. | Oct-Dec 2008 |
Assess Significant Changes | Should consultation result in significant changes to the NAPs, the impacts of these changes will be assessed. | Dec 2008 |
Adoption of NAP | Adopted Action Plan will incorporate changes based on consultation responses, where appropriate. | Jan 2009 |
Prepare Post-Adoption SEA Statement | This will highlight how the findings of the SEA and comments from consultation have been taken into account in the development of the final NAPs. It will also set out a final monitoring framework. | Dec 2008/ Jan 2009 |
Analysis of CNMAs and CQAs | Analysis of data used to define CNMAs and CQAs, enabling an understanding of whether these should be determined and adopted in the future. | Jan 2008 onwards |
Develop methods for designating NMAs and Quiet Areas | Development of technical guidance for declaring NMAs and Quiet Areas. This will be subject to consultation in January 2009 for 12 weeks. | Oct 2008 - Mar 2009 |
Declaration of NMAs and Quiet Areas | Final adoption of NMAs and QAs. | Ongoing post May 2009 |