On this page:

Scotland's Railways

« Previous | Contents | Next »

Listen

Annex - High Level Output Specification

The High Level Output Specification ( HLOS) process

  • A statement of the outputs Scottish Ministers wish to purchase from the rail industry during the next regulatory control period for track access charges.
  • A responsibility created under the Railways Act 2005.
  • Required to allow the Office of Rail Regulation to determine whether public sector funding is sufficient to allow Network Rail to deliver industry outputs.
  • Ministers required to deliver Statement of Funds Available ( SoFA) in parallel.

Responsibilities of Scottish Ministers

  • Funding Network Rail through Network Grant.
  • Franchising ScotRail.
  • Funding major projects to enhance the railway.
  • Determining available funds for rail industry.

Key timescales

  • June 2006: Network Rail cost submission for Control Period 4.
  • February 2007: ORR issues formal Access Charges Review notice to government funders.
  • July 2007: Government submits HLOS and SOFA to ORR.
  • October 2008: ORR issue Final Determination of Access Charges for CP4.

Further copies of this document are available from:

Denise Manzor
Transport Scotland
0141 272 7553
denise.manzor@transportscotland.gsi.gov.uk

This document will be made available in alternative formats on request. Please contact Denise Manzor as above

« Previous | Contents | Next »