ANNEX J Model timetable for the completion of the first statutory regional transport strategies
Month | Stages in preparation of RTS | Compliance with: |
|---|
STAG | SEA |
|---|
January 2006 | Announcement of preparation of RTS by RTP Board Scoping of issues (paragraph 71) Vision (paragraph 78) | | |
March | Issues and Objectives Report completed (paragraph 84) | Objectives, and Analysis of present and future problems | |
April | Issues and Objectives Report approved by RTP Board | | |
April | First assurance/progress report to SE | | |
April/May | Option generation and appraisal including consultation with key stakeholders (4 weeks) | Option generation, high-level assessment | |
June | Options Report approved by RTP Board | Begin options appraisal | Scoping report to SEA Gateway |
End-June | Status Report to SE giving consideration to whether an extension to the March 2007 deadline is required | | |
June/July | Consultation with key stakeholders (5 weeks) on Options Report | Options appraisal | Consultation with CAs (5 weeks) |
August/ Sept | Decision on overall RTS option and drafting of remainder RTS | | Drafting of Environmental Report |
October | Draft RTS approved by RTP Board | Reporting Produce ASTs | Environmental Report to SEA Gateway |
October | Second assurance/progress report to SE | | |
Oct/Nov/Dec | Public consultation (8 weeks) | Refining estimates of costs and benefits | Consultation with CAs (8 weeks) |
February 2007 | Final RTS approved by RTP Board | | |
31 March | Submission to Scottish Ministers of RTS and supporting documents ( e.g. Consultation Report, STAGASTs, Environmental Report, SEA Statement and Implementation Programme) | | SEA Statement and RTS to CAs |
June/July | Approval by Scottish Ministers | | |