« Previous | Contents | Next »
Listen
6 RECOMMENDATIONS
6.1 INTRODUCTION
The recommendations identified within this study have
been classified as either:
- Priority Recommendations, or
- Other Recommendations, which are further
sub-divided into short or long term
classifications.
In addition, recommendations have also been categorised
by type, namely:
- Design Issues, where changes in the design of the
road network are proposed
- Operational Issues, where changes in the operation
of the road network are proposed
- Research Issues, where detailed recommendations are
not possible at this time and further research is
required
- Policy Issues, where recommendations would have an
impact on current policies
6.2 PRIORITY RECOMMENDATIONS
6.2.1 Design Issues
- Revise the parameters for the design storm for
surface water drainage performance. This could be
achieved by continuing the use of historical
information but for an increased return period, or by
basing the approach on further research on rainfall
changes arising from climate change.
- Revise the parameters for the design storm for
watercourse structures. This could be achieved by
continuing the use of historical information but for an
increased return period, or by basing the approach on
further research on rainfall changes arising from
climate change.
6.2.2 Operational Issues
- Identify locations where flooding of the road
network has occurred, and develop potential solutions
for evaluation on a cost/benefit basis, prioritising
those areas where repeated flooding has occurred.
- Pre-emptively clear detritus from
channels/watercourse structures in known areas of
flooding risk in response to predicted heavy
rainfall.
6.2.3 Research Issues
- Undertake further research in respect of catchment
runoff estimation parameters, and provide guidance on
possible risk-based design approaches, including
evaluation of alternative solutions on a cost/benefit
basis.
6.2.4 Policy Issues
- Consider using the
VMS network to provide a greater
level of locally relevant information to road users on
predicted severe weather events, expressed in terms of
probability of occurrence.
6.3 OTHER RECOMMENDATIONS
6.3.1 Short Term Issues
Design Issues
- Review local experience on the durability of
surface dressings and consider whether these or another
intervention measure is appropriate for the location
concerned.
- Consider implications of an extended growing season
when developing landscape designs, and specify
slow-growing species where appropriate.
- Design drainage systems with additional storage
capacity, taking account of sustainable drainage
techniques, where appropriate.
- Introduce surface/sub-surface drainage during
maintenance works where these do not exist at present,
while recognising that this may not always be possible
due to land-take constraints.
- When developing new designs, consider whether these
will be susceptible to full or partial closure in high
winds, and prepare a cost/benefit analysis to assess
the opportunity for including wind barriers at these
locations.
- When developing new designs, consider whether these
will be susceptible to coastal flooding, taking account
of predicted sea-level changes and the possible effects
of storm surges, and consider how the design should
take account of any such susceptibility.
Operational Issues
- Clarify the investigation requirements for
watercourse structures potentially susceptible to
scour, in terms of periodic and post-event inspection
requirements.
- Continue the process of developing a High Winds
Strategy for the trunk road network and consider the
need for a similar approach on exposed sections of the
local road network
Research Issues
- Undertake further research on likely changes in
wind patterns, including seeking to reduce the
significant uncertainty that exists in regard to this
issue. This would enable further guidance to be given
on future consideration of wind in the design and
operation of the road network.
- Update this report as necessary following
publication of the
UKCIP06 report
6.3.2 Long Term Issues
- Design Issues
- Specify materials with appropriate stiffness to
provide greater confidence that pavement deformation at
high temperatures should not occur.
Operational Issues
- Consider periodic reviews of required pavement
interventions, to determine whether high temperatures
have been identified as a significant contributing
factor.
- Consider carrying out earthworks inspections under
the principles of Technical Memorandum
HD 41/03 'Maintenance of Highway
Geotechnical Assets' pending further guidance on
landslide risk management arising from the 'Landslide
Study', prepared as a companion to this report.
- Identify areas of the road network that require
full or partial closure in high winds and consider the
introduction of wind barriers at these locations. This
consideration should include a cost/benefit analysis
and, if necessary, an environmental assessment.
- Consider whether enhanced parking/turning
facilities at locations on the road network susceptible
to full or partial closure in high winds would provide
a cost effective operational benefit.
- Identify locations on the road network susceptible
to coastal flooding. This should take account of
predicted sea-level changes and the possible effects of
storm surges, to consider whether measures such as
signage, sea-defences or re-routing are
appropriate.
Research Issues
- Carry out further research on specific aspects of
winter conditions where data does not presently exist,
to provide a greater understanding of the likely
pattern of change in winter conditions that is
expected.
Policy Issues
- Consider how enhanced communication could be
developed with all parties involved in flood
management.
- Consider how information on areas known to be at
risk of flooding may be integrated with flood warning
systems to provide early indication of potential
hazards.
- Consider the predicted changes in winter conditions
to determine how winter maintenance of the trunk and
local road networks may be carried out on a
cost-effective basis.
- Consider developing a road user education programme
on the appropriate response to different types of
severe weather events.
- Consider using the
VMS network operated by
NADICS to support the above road
user education programme.
« Previous | Contents | Next »