5 ROAD IMPACTS AND NETWORK MANAGEMENT ISSUES
5.1 INTRODUCTION
This section of the report considers the predicted
climate change trends associated with different weather
events in relation to the design and operation of the
Scottish road network. Measures are identified that may
enable more effective management of the risks associated
with occurrence of these weather events. The criteria for
these measures are that they be practical, pragmatic and
cost-effective. However, it is considered that some
measures will require further and more detailed assessment
before implementation. Where appropriate, recommendations
for such further assessment have been made.
In particular, in connection with all of the assessments
presented here, it is noted that the next update of the
UK Climate Impacts Programme,
UKCIP06, is understood to be due in
2006. It is therefore recommended that where this presents
predicted trends in climate change that are appreciably
different from those predicted in
UKCIP02, the findings of this study are
reviewed and either confirmed or amended as
appropriate.
Consideration has also been given to network management
practices associated with severe weather events.
Consultation with maintaining agents has been undertaken to
review their experience of the effects on the road network
of such events. This consultation has also reviewed the
degree of success achieved in recent years in mitigating
potential impacts through preventative intervention, and
any measures introduced to enhance road user awareness of
severe weather risks.

Figure 5.1 - Snow clearance operations.
Photograph courtesy of
BEAR Scotland Ltd
The time horizons considered include the
UKCIP02 scenarios for 2020's, 2050's and
2080's where given, and additional periods identified
through subsequent work undertaken by the Met Office.
Wherever predictions have been defined as scalable, figures
have been interpolated from the modelled present day
climate to the 2080's.
5.2 TEMPERATURE
5.2.1 Introduction
Three main effects of temperature on the road network
are considered here, namely:
- Effects of High Temperatures on Bituminous
Pavements
- Effects of Freeze-Thaw Action on Bituminous
Pavements
- Growing Season
- Air Quality
The contribution of low temperatures to the formation of
ice is discussed in relation to winter maintenance issues
later in this section under the heading of 'Snow'.

Figure 5.2 - Surfacing operations on the A9
near Blackford. Photograph courtesy of
BEAR Scotland Ltd
5.2.2 Effects of High Temperatures on
Bituminous Pavements
A number of factors add to the influence of temperature
on bituminous pavements. Traffic loading, speed and
density, local ambient temperature, volume and frequency of
rainfall and intensity of direct sunlight will all modify
the effects of elevated temperatures.
The Transport Research Laboratory (
TRL) produced a working paper titled
'Maximum Road Temperatures in Relation to Surface
Deformation in Scotland' in 1993. Mean maximum daily
temperatures were recorded within asphalt wearing courses
over three Scottish summers.
The highest maximum surface temperatures recorded in
specific localities included two values of 43¡C and one at
44¡C. These indicate extreme conditions likely in normal
summers but in general daily maximum temperatures rarely
approached the
DWT (Dry Wheel Tracking) test
temperature of 45¡C. This is the temperature at which
certain design mix asphalts may be liable to deformation.
The temperatures within the asphalt wearing course, 25mm
below the surface, were found to only rarely exceed 40¡C
over the course of the three years of the
investigation.
The length of time the road surface is at an elevated
temperature is significant. In the
DWT test the sample is preheated for a
minimum of 4 hours at 45¡C and then tested for an hour at
that same temperature. An interim report showed that the
road surface temperature would be above 44.5¡C for one hour
in 20 years and 3.5 hours once in 100 years. It is
therefore probable that the potential for deformation due
to prolonged high road surface temperature would occur once
in 20 years. Concerns relating to an increase in
temperature of bituminous pavements include adverse affects
to the hardness of the road surface, fatting up of the road
surface and thermal expansion and contraction affecting the
integrity of the road surface.
The
TRL paper concluded that within a 20
year period design mix asphalts are unlikely to deform due
to prolonged high temperatures. It recommended that
consideration should be given to future monitoring of road
temperatures. This would provide valuable information in
respect to any deformation failures occurring during the
summer period.
Higher annual temperatures would also require an
adjustment to current methods of pavement analysis.
Assigned stiffness values are used for analysis and design.
If the average temperature is warmer, then materials will
display less stiff properties. The less stiff the
bituminous component of the pavement is the thicker the
pavement may have to be to provide the required lifespan.
It should be further noted that at the time of the
TRL report the typical design life of a
bituminous pavement was 20 years, but many bituminous
pavements on major roads are now designed with a 40-year
design life and this could exacerbate weakness due to lower
stiffness. In parallel with this development, current
materials do, however, have typically improved stiffness
properties over materials used in the past.
As the
TRL report suggests, failure of
bituminous carriageways due to high temperatures in
Scotland is not a common occurrence. Although rutting,
which is possible evidence of this method of failure, has
been observed, this tends to have other causes. However,
some recent instances of deformation of bituminous
materials where heat may have been a factor are listed
below:
- 1999, the binder content of surface dressing on
certain local roads in a central belt district
exhibited excessive fluidity. Gritters were sent out to
sand the roads
- 1995, a sudden wearing course rutting failure
occurred on a section of southern Scotland trunk road
following elevated temperatures. Analysis showed 100pen
binder rather than 50pen binder had been used by the
surfacing contractor, indicating the potential
susceptibility of this material to deformation
associated with elevated temperatures.
- 2003, a section of trunk road in the central belt
suffered basecourse failure. Material was within
specification and no reason for failure was apparent.
The hypothesis of the Managing Agent was high
temperatures on a heavily trafficked section of
carriageway where vehicles were also braking caused the
failure.
Managing Agents consider that most rutting problems on
the trunk road network are the result of pavement failure
due to the volume of heavy goods vehicles. In particular,
rather than the effects of high temperatures, it is
considered that there is an increasing number of vehicles
that are single-wheeled on each side as opposed to
double-wheeled.
Raising the temperature in the upper layers of pavement
can cause the binder to lubricate the aggregate where the
materials are binder-rich. However, this is less of a
concern in Scotland, as Scottish aggregate tends to be more
angular, thus promoting mechanical interlock.
The introduction of stiffer pavement materials, even
with a longer life design, together with the likely rarity
of prolonged periods of high temperatures, should result in
effects due to high temperatures on recently constructed
major roads being very limited. However, older sections of
road, and much of the local road network, which is largely
composed of less stiff materials, or materials of unknown
stiffness, may be more susceptible to failure.
It is recommended that bituminous materials with
appropriate stiffness characteristics are specified in road
construction or maintenance works on the road network, in
order to provide greater confidence that pavement
deformation due to high temperatures does not occur. It is
not considered cost-effective to replace sections of roads
constructed with less stiff materials specifically to
address this issue. However, should any pattern of failures
emerge in the future this position should be reviewed.
5.2.3 Effects of Freeze-Thaw Action on
Bituminous Pavements
During the winter months moisture in certain types of
road surfacing material may freeze and thaw in cycles. This
cycle of freezing and thawing can cause a volume change
within the material, with changing stresses resulting in a
loosening effect. This may be exacerbated by vehicles
displacing or disturbing surfacing materials, which in turn
allows more moisture to ingress.
Once water has entered the road pavement structural
damage is initially caused by hydraulic pressure, with
vehicles passing over the road pavement impacting
considerable and sudden pressure on the water, thus forcing
it further into the fabric of the road. Water that has
already entered the road pavement and is then subjected to
the process of freezing and thawing during the winter
further increases this internal pressure. The recent
practice of specifying smaller aggregates and requiring
intermediate bond or tack coats may be expected to reduce
the voids within road pavements, and thus provide greater
durability under freeze/thaw conditions.
Surface dressing reacts poorly to freeze/thaw conditions
as it has a highly exposed binder. A combination of this,
its susceptibility to freeze/thaw action and its thickness
may result in embrittlement of the surface. This is then no
longer able to provide the function of sealing the upper
layers of the underlying bituminous carriageway.
All four climate change scenarios suggest that there
will be a significant reduction in the number of days per
year when the daily minimum temperature is at 0
oC, therefore the annual number of freeze-thaw
cycles may be expected to reduce, thus reducing the extent
of damage associated with this process.
The experience of surface dressing failure on the trunk
road network varies depending upon geographic area, with
some areas experiencing large scale failures and others
performing satisfactorily. The Managing Agents considered
that the failure mechanism is generally a two stage
chip-loss, the first soon after application and the second
during the winter months, leaving a deeply exposed
substructure.
It is also observed that bituminous pavement materials
other than surface dressing tend to deteriorate more
quickly during the winter months than at other times of the
year, although this may relate to winter wetness rather
than freeze-thaw action. However, the Managing Agents also
considered that temperature changes observed at present
tend to result in a greater extent of thawing and
refreezing, possibly following a day/night pattern, than
observed previously. If so, this would suggest that greater
damage may occur from freeze-thaw action in the future.
The porosity of pavement layers is likely to remain an
issue of some concern. However, it is recognised that
surface dressing is a cost effective short term solution
which goes some way to protecting the underlying materials
and restoring necessary skid resistance. In order to
maximise the effectiveness of this treatment it is
recommended that local experience of the durability of
surface dressings be reviewed to consider whether these or
another intervention measure is appropriate for the
location concerned.
5.2.4 Growing Season
Landscaping of roads may entail both significant
planting that matures over time to meet visual and
ecological objectives, and seeding of verges and side
slopes to provide a simple finished form. In order to
maintain an appropriate appearance of the soft estate and
to maintain a safe road it is essential that cyclic
maintenance is undertaken to ensure that vegetation does
not obscure signage or visibility splays.

Figure 5.3 - Example of grass-cutting in
verges.
It is generally considered that a minimum of two cuts
per year is adequate to control the height of grassed
roadside verges, centre reserves and junction areas on the
Scottish trunk road network. However, in recent years this
has increased to 3 or more cuts. This maintenance activity
requires traffic management at most locations and hence
increased cutting is likely to result in greater disruption
and delay to the travelling public.
The approach to landscaping design should recognise the
potential effects of a longer growing season, and it is
recommended that slow-growing elements are used where
appropriate, in order to minimise the extent of cyclic
maintenance required. It should be noted that an increasing
extent or frequency of cyclic maintenance will require a
consequential larger annual budget to achieve the same
quality of appearance.
5.2.5 Air Quality
The predicted average temperature increase in Scotland
of 1¡C suggests that the future temperature regime in
Scotland will not change to be significantly different from
that observed elsewhere in the
UK at the present time. As the air
quality assessment guidance is used throughout the
UK, it is therefore not considered
necessary at this time to recommend any change to current
practices of air quality assessment and prediction.
5.3 RAIN
5.3.1 Introduction
Five main effects of rain on the road network are
considered here, namely:
- Road Surface Drainage
- Pavement Deterioration as a Result of Wet
Conditions
- Watercourse Flooding
- Ground Water
- Soil Moisture
5.3.2 Road Surface Drainage
Road drainage design has two major objectives:
- the rapid removal of surface water to provide
safety and minimum nuisance for the road user
- provision of effective sub-surface drainage to
maximise longevity of the pavement and protect its
associated earthworks
Traditional methods of draining paved carriageways
involve the use of a network of gullies or filter drains to
collect surface water runoff, which is then discharged to a
watercourse. Due to the closed nature of these systems, the
capacity available is limited and can be further hindered
by blockages, leading to localised flooding on the road
surface.
The effects of the predicted climate changes in
precipitation in 8 locations across Scotland with good
geographical coverage were selected for analysis.
Calculations were undertaken to examine how the return
period of the 1-year rainfall, for 3 durations - 15, 30 and
60 minutes, would change according to these statistics. By
the 2020's the 1-year event was found to change to a 1.4
+/- 0.2 year event when assessed using the present
depth-duration-frequency statistics, with rainfall
increases of between 4% and 13%. By the 2080's the 1-year
event was found to change to a 2 +/- 0.6 year event when
assessed using the present depth-duration-frequency
statistics, with rainfall increases of between 10% and
30%.
A number of locations on the trunk road network have
been identified as particularly at risk of drainage
'failure', and inspections by Managing Agent Area Teams are
consequently prioritised during periods of heavy rainfall.
The purpose of these inspections is to ensure unimpaired
drainage. The most common cause of flooding in areas where
drainage is present is due to detritus being washed into
the system, resulting in partial or complete blockage.

Figure 5.4 - Damage to A9 Raigmore Slip Road,
Inverness, 2002, following heavy rainfall. Photograph
courtesy of
BEAR Scotland Ltd.
Filter drains can also be susceptible to failure through
root invasion. Serious problems have been observed within
10 year old plastic filter drain pipes that have become
inundated with roots. In addition, a major maintenance
scheme was delayed when it was found that the sub-base was
water-logged. Inspection showed that the adjacent filter
drains had consisted of porous concrete pipes, which
through root ingress had disintegrated and collapsed.
Given the expected change in rainfall events, it is
recommended that consideration be given to revising the
parameters for the design storm. This could be done on an
immediate basis by simply changing the design storm from
the 1 in 1 year and 1 in 5 years events to a 1 in 2 years
and 1 in 10 years events respectively, whilst continuing to
take account of the available historical information.
Alternatively, further assessment could be carried out
using climate change modelling to provide guidance on the
extents of future 1 in 1 year and 1 in 5 years events. In
either case it is important that drainage systems are
designed to meet the desired performance level and there is
a risk that at present the drainage systems being designed
under current guidelines may not achieve that
objective.
Some types of drainage systems have increased available
capacity for storage of surface water runoff in comparison
to gully drainage systems. It is also noted that filter
drain systems can also provide environmental benefit
through partial filtration of the surface water runoff. It
is recommended that where a choice of drainage system is
available preference is given to systems that provide
additional capacity and take account of sustainable
drainage techniques.
5.3.3 Pavement Deterioration as a Result of Wet
Conditions
The durability of a mixed material depends on either its
ability to keep the weather out if it is intended to be an
impermeable material, or the ability of its components to
resist the weather, if it is permeable. Certain elements of
bituminous pavements can be permeable, and the pavement
will deteriorate if moisture remains within the bound or
sub-grade layers. It is therefore essential for pavement
durability that effective drainage is present to remove
both surface and sub-surface water.
The climate change predictions suggest wetter winters,
in which circumstances the greatest extent of pavement
deterioration is likely to occur. This would indicate that
the need for effective drainage to maintain pavement
durability is likely to be greater in the future.
The Managing Agents noted that recent summers appear to
have been wetter than average and this has coincided with
the need for more structural trunk road maintenance than in
previous years. It may be that the level of deterioration
experienced is as a result of the high levels of this
precipitation. The sections of carriageway which have been
most badly affected have in general been older sections of
carriageway, sections already showing signs of surface
deterioration and sections with limited or no formal
drainage system.
It is recommended that appropriate formal surface and
sub-surface drainage systems are introduced to the road
network during maintenance operations where these are not
in existence at present. It is noted that for many of the
rural roads in Scotland this will involve land purchase to
accommodate the extra width required for drainage measures.
However, it is considered that the long-term benefits will
usually justify the additional investment.
5.3.4 Watercourse Flooding
Whether major river or minor watercourse, flooding from
catchment response to storm events is a significant risk,
with the potential to impact on the safe operation of the
road network. Examples of the issues that may arise
include:
- Bridge/culvert capacities exceeded, causing
upstream flooding to occur
- Overtopping and scouring problems to
structures
- Roads and any properties on flood plains becoming
inundated
The climate change predictions suggest that in addition
to the generally wetter winters that are expected, the
intensity of precipitation is predicted to increase. In
addition, rising temperatures resulting in fewer snow days
and a shorter period prior to snowmelt occurring through
fewer days where the temperature is below 0¡C, may create a
situation where catchment responses are significantly
higher than previously observed.
The view of the Managing Agents is that generally there
are very few areas of the trunk road network in Scotland
that are susceptible to river flooding and it is not seen
as a major concern in terms of the frequency of incidents.
In addition, emergency response plans are in place to cover
events including flooding. In one area the Managing Agent
is linked to a flood early warning system run by the local
authority, and it is understood that consultations are
currently taking place to discuss recent flooding events
with the Operating Company, Council Emergency Planning
Officers,
SEPA, Police and Scottish & Southern
Electricity in an effort to further improve the system of
communication.
Culverts are generally considered by the Managing Agents
to represent a more recurrent, if less extensive, concern,
with flood events regularly affecting particular locations.
This is due, in part, to culverts at these locations being
unable to accommodate flood-borne detritus, which then
reduces the available capacity of the culvert and hence
exacerbates the impact of the flood event. To address this
there are programmes for culvert inspections, focussing
attention in specific months, when areas of particular
concern are identified and monitored by the Managing Agent
for additional attention.
It is noted that that while major watercourses rarely
affect the trunk road network, they can be severely
damaging to local roads. Such roads often follow historic
routes that pre-date significant developments within the
river catchment. As a result, at the present time they are
at a much higher risk of flooding than at any time
previously.
Where a known problem with regard to flow capacity
exists, it is recommended that assessments should be made
of the implications of improving or replacing the structure
concerned. In order to target this work, it is recommended
that a schedule of watercourse structures that have been
affected by flood events is prepared and those that have
seen repeated occurrences be treated as the highest
priority.

Figure 5.5 - Flooding on the A90 at Boddam,
2003.
In addition, when developing the designs for watercourse
structures, it is recommended that the design return period
be reviewed, to take account of the predicted change in
intensity of rainfall event and the other factors that may
affect catchment response. At present the design of such
structures is based on a return period between 1 in 50
years and 1 in 100 years. As for the surface water drainage
systems, the change could be implemented on an immediate
basis by simply amending the design storm from a return
period of between 1 in 100 years to 1 in 200 years.
Alternatively, further assessment could be carried out
using climate change modelling and reviewing flood
estimating procedures to provide guidance on the extents of
future 1 in 50 years and 1 in 100 years events. In either
case it is important that the structures are designed to
meet the desired performance level. At present there is a
risk that the systems being designed may not achieve this
objective.
It is also recommended that consideration be given to
extending the flood warning systems that have been
developed by other public bodies and agencies to identify
potential conflicts with the road network. This could
include, for example, integrating a Geographical
Information System for known watercourse areas of concern
with systems showing predicted catchment responses to
anticipated rainfall events. This could also usefully
include pre-agreed proposed diversion routes for local or
trunk road traffic should it become necessary to close the
affected section of road.
This system would also be enhanced through improved
communication between all parties with responsibilities
arising from major flood events. This would also facilitate
improved communications with
NADICS, affording the opportunity to
improve the dissemination of information to road users.
It is noted that clarification is being prepared on the
requirements for inspections of watercourse structures on
the trunk road network that are potentially susceptible to
scour. It is recommended that this address both periodic
and post-flooding event requirements, in order to provide
early warning of any potential problems.
The effective maintenance of watercourses and ditches is
essential to the operation of culverts and it is
recommended that measures to target areas where known
problems exist through pre-emptive clearing of detritus in
advance of predicted heavy rainfall should be considered by
all maintaining authorities.
5.3.5 Ground Water
Ground water is one of the critical elements affecting
the design of cutting slopes. Parameters used in design
include the height of ground water and the degree of
movement to which it is susceptible. Changes in these
parameters can materially affect the design or operational
effectiveness of the cuttings concerned. The presence of
effective surface and sub-surface drainage previously
discussed for the road pavement, together with well
maintained pre-earthworks drainage at the top of slopes,
also enables cuttings to remain stable. In some instances
counter-forte slope drainage is also required to maintain
slope stability.
Ground water is also one of the factors that is a
potential contributor to landslide events. Further
information on this subject may be found in the Landslides
Study, as referred to in Section 1 of this report.
The climate change trends tend to suggest that potential
evaporation is likely to increase across Scotland. This
factor, coupled with the reduced summer rainfall, will tend
to result on average in greater and more persistent soil
moisture deficits, thus reducing the summer and autumn
recharge to the groundwater. However, with slightly
increased winter soil moisture it is possible that winter
conditions will increase the recharge to the ground water.
This may yield greater variability in ground water in soils
that are reasonably permeable. It is possible that in
winter conditions the ground water levels may be higher
than allowed for in the design of the cuttings
concerned.
The Managing Agents expressed no opinion in relation to
observation of any impacts associated with general changes
in ground water level or moisture content.
While no formal recommendation can be made without an
appropriate climate change model being developed for this
issue, it is recommended that consideration be given to
carrying out earthworks inspections under the principles of
HD 41/03 'Maintenance of Highway
Geotechnical Assets' of the Design Manual for Roads and
Bridges by parties responsible for maintaining the road
network.

Figure 5.6 - Debris flow being cleared from the
A82, 2002. Photograph courtesy of
BEAR Scotland Ltd
5.3.6 Soil Moisture
Soil moisture is one of the factors that affects
catchment response, with soils holding greater moisture
being less capable of absorbing additional rainfall and
therefore contributing to an increased surface water
runoff.
The climate change trends tend to suggest that potential
evaporation is likely to increase across Scotland, which
coupled with the reduced summer rainfall will tend to
result on average in greater and more persistent soil
moisture deficits. However, it is considered winter soil
moisture will increase slightly, which together with the
additional winter wetness and greater storm intensity may
result in increased catchment runoff.
The Managing Agents noted that some landslide events
occurred when a period of intense rainfall followed a
longer period of general rainfall. It is possible that this
is a demonstration of the implications of increasing soil
moisture producing greater catchment runoff.
There are a number of methods available to enable the
estimation of surface water runoff for the small to medium
sized catchments in which the road network typically lies.
It is recommended that further work be undertaken to review
the assumptions underlying these methods, in the light of
predicted changes in variables such as rainfall, soil
moisture and snowfall. This review could propose a range of
alternative assumptions to be tested in the design process,
providing different outputs for the surface water runoff
and hence alternative proposals for drainage provision and
watercourse structures. The implications of greater or
lesser degrees of provision could then be assessed on a
cost/benefit basis, taking account of the increased level
of confidence that would be associated with a greater level
of provision.
5.4 SNOW
5.4.1 Introduction
Snow has two significant effects on the road network.
The contribution of snowmelt to catchment runoff has been
discussed previously. The other effect, discussed here, is
the impact of winter weather conditions on the operation of
the road network. This includes the implications of
predicted climate change trends on both snowfall and ice
formation.

Figure 5.7 - A90, South of Aberdeen, 2004.
Photograph courtesy of Performance Audit
Group.
5.4.2 Winter Conditions
Maintaining availability, reliability and safety of the
road network is a key objective of winter maintenance. Snow
and ice on the road causes hazardous driving conditions and
can result in damage to the fabric of the road pavement.
Therefore, effective winter maintenance makes important
contributions towards road safety and the minimisation of
whole life costs.
While the predicted climate change trends suggest a
general reduction in snowfall, it is also noted that
individual years may have greater than average snowfall as
a result of natural variability. In addition to generally
reducing snowfall, the predicted climate change trends also
suggest that there will be fewer days where the temperature
is below 0¡C and therefore less ice formation may also be
expected. Therefore, it may be anticipated that future
winter maintenance requirements will be less onerous over a
period of years than at present. However, as a result of
natural climate variability it is possible that individual
years may have winter maintenance requirements similar to
the modelled present day climate.
Consultations with the Managing Agents suggest that
milder winters, with reduced snowfall, are being observed
at present. However, they have also suggested that there is
a change in some other aspects of the weather behaviour.
This includes the more frequent occurrence of snow/ice
thawing and then refreezing. As a consequence of these
conditions, the practice of gritting to prevent freezing
becomes less effective, with grit being washed off the road
surface prior to the next freezing event. This requires a
heavier spread of grit in order to prevent wash-off, which
increases maintenance costs.
Reducing winter maintenance burdens may result in lower
costs of winter maintenance services. However, the risk of
significant individual events will mean a continuing need
for services to be available with short mobilisation
periods in order to achieve the desired road availability.
It is recommended that at an appropriate time future winter
maintenance arrangements for both trunk and local road
networks consider this likely pattern of change, in order
to make cost-effective use of resources. It is also
recommended that further research be undertaken on
freeze-thaw patterns relating to night-time and day-time
temperatures, to provide guidance on whether changes to
current winter maintenance practices are required.
The predicted reduction in winter maintenance
requirements may result in road users being less likely to
delay or cancel travel plans in the light of individual
winter weather events, having become used to a road network
that is generally available for use. It may be that
additional road user education programmes are required,
which could usefully be extended to cover road user
behaviour in all severe weather events. This is discussed
more fully in a later part of this section, under the
heading 'Road User Information and Behaviour'.
5.5 WIND
5.5.1 Introduction
Wind has two main impacts on the road network,
namely:
- Effect on Structural Elements/Roadside
Furniture
- Effects on Operation of the Road Network

Figure 5.8 - Wind Damage to Road Sign,
Edinburgh, 2005. Photograph © The Scotsman Publications
Ltd.
5.5.2 Effect on Structural Elements/Roadside
Furniture
Extreme wind events are used in the design of many
elements of the road network. The achievement of
satisfactory operational performance is dependent on the
results of this evaluation. Hence, extreme winds may affect
the built environment, for example traffic signs. In
addition, they may also affect landscaping adjacent to the
road network and significant disruption may result as a
consequence of damage to large elements, such as trees.
The effect of an increase in wind speed is dependent on
the pressure of the wind, which is proportional to its
velocity squared. For example, an increase in wind speed of
10% has the effect of increasing the structural loading on
traffic signs by 20%. While this should have little effect
on the vast majority of well built structures, damage may
occur as a result of the increased loading where elements
have not been correctly designed, fabricated or
installed.
While the predicted climate change trends suggest that
there will be slight changes in extreme winds, it is also
noted that this is an area where significant uncertainty
exists. The annual average is shown to reduce in the Fair
Isle, Faeroes and Hebrides shipping areas, with small
increases of up to 4% along coastlines and in the North
Sea. However, wind direction and duration must also be
considered, as changes in the extreme and prevailing
directions, or relative changes in their speeds, may be
significant. Currently little is known on these issues.
While high winds are considered by the Managing Agents
to be an area of concern, it is not considered that a
greater level of failures of structural elements or
roadside furniture is being observed than was previously
the case. In most instances failures of elements such as
road signs following high winds are considered to be due to
inadequate foundations, rather than necessarily being the
effects of extreme high winds.
In light of the uncertainty that exists in relation to
the predicted climate change trends in wind, it is
recommended that further research be carried out on this
subject, to enable more definitive guidance to be
provided.
5.5.3 Effects on Operation of the Road
Network
Extreme winds can disrupt operation of the road network
through impacts on high sided vehicles. As their speed
increases, high sided vehicles become increasingly unstable
in gusts of over 20 m/s (45mph). Therefore, to maintain
stability drivers need to slow down when experiencing high
winds. At some sites, such as major bridges, closure of the
road to high sided vehicles is required to prevent their
exposure to these winds. This usually results in such
traffic, generally heavy goods vehicles, being diverted
from major roads to less suitable local roads. This can
cause disruption on, and potential damage to, these
roads.

Figure 5.9 - High sided vehicle blown off the
road. Photograph ©
EMPICS/
PA/
AP.
As noted above, while the predicted climate change
trends suggest that there will be slight changes in extreme
winds, this is an area where significant uncertainty
exists.
The Managing Agents noted that where vehicles are blown
off the carriageway, it is usually necessary to temporarily
close some or all lanes to recover the vehicles. This
creates additional disruption to road users. It was also
noted that the decision on the closure of roads to high
sided vehicles is normally taken by the Police and/or a
Toll Operating Company. In making this decision the Toll
Operating Companies follow defined procedures, which
include assessing the implications of both wind speed and
direction. At present closures on other roads do not
usually follow any defined protocols. Recent events have
identified this as an area that requires clarification of
roles, responsibilities and the decision making process. In
addition, the Managing Agents expressed concerns that
insufficient measures exist for advance signing and the
provision of parking/turning areas for high-sided vehicles
when sections of the road network are closed.
One method of avoiding the need for such closures would
be the inclusion of wind barriers at exposed sites. It is
recommended that sites which are regularly closed to high
sided vehicles are reviewed to determine whether they have
the potential to be fitted with wind barriers. This
assessment should include a cost/benefit analysis. It is
acknowledged that it may not be technically feasible or
economically justifiable for many such sites to be fitted
with wind barriers. It is also recommended that all new
road schemes which include sites likely to be exposed to
high winds be reviewed at the design stage. This would
enable an early decision to be taken on the inclusion or
otherwise of wind barriers, at a stage when the economic
implications of inclusion are at a minimum.

Figure 5.10 - Wind barriers at the Second
Severn Crossing. Photograph © Severn River Crossing
PLC (
SRC), used with permission of
SRC and Highways Agency.
It is noted that a High Winds Strategy is currently in
development for the trunk road network. This will address
the procedures to be followed, including diversion
requirements, in the event of closure of sections of the
trunk road due to high winds. It is recommended that this
strategy take account of any future information on
predicted climate change trends in wind, should such become
available.
It is also recommended that consideration be given to
the physical measures necessary to accommodate
parking/turning of traffic affected by areas of the road
network that are regularly closed due to high winds.
Recommendations in respect of road user behaviour in high
winds are discussed in a later part of this section, under
the heading 'Road User Behaviour'.
5.6 FOG
Fog impacts upon the safe operation of the road network
through reducing visibility and thus creating a road safety
hazard.

Figure 5.11 - Forth Road Bridge, Edinburgh.
Photograph © The Scotsman Publications Ltd.
Predicted changes in fog are not routinely output by
current climate models, although it is a current area of
active research. At present the predictions, which suggest
a reduction in the number of fog days, must be seen as
provisional until a better understanding can be
reached.
Although the Managing Agents noted that fog was an
ongoing concern, they had no particular comments on this
issue.
The concerns in respect of safe operation of the road
network in fog conditions are capable of being addressed
through improved road user behaviour, and this is discussed
more fully in a later part of this section, under the
heading 'Road User Behaviour'.
5.7 COASTAL FLOODING
The predicted trends in climate change for coastal
flooding, including the implications of surge heights,
suggest that this has the potential to affect low lying
roads in coastal areas. This may result in damage to the
road, road closure, or the occurrence of road safety
hazards, as seen following the severe winter storm of
January 2005. It should be noted that the roads at risk are
predominantly part of the local, rather than the trunk,
road network.
The Managing Agents considered that there are few areas
of the trunk road network susceptible to coastal flooding.
In addition to flooding, there were concerns expressed that
coastal erosion may affect sections of the road
network.

Figure 5.12 - Coastal Damage in South Uist,
2005. Photograph courtesy Mr D I Caimbeul.
It is recommended that the road network be reviewed to
identify areas of potential risk from coastal flooding,
taking account of the cumulative effects of sea-level
changes and storm surges. Areas at risk may then be
addressed through a combination of warning signage,
edge-strengthening or introducing sea-defences. In extreme
cases, consideration could be given to whether re-routing
is appropriate. It is also recommended that any new
projects proposed in low-lying areas should be reviewed
with respect to these risk factors, to enable appropriate
decisions to be taken at the design stage.
5.8 ROAD USER BEHAVIOUR
In addition to the impact of severe weather on
performance of the road network discussed previously, road
users are also affected in other ways by severe weather
events, such as:
- Heavy rainfall and/or poor surface water drainage,
which can result in excessive spray, reducing
visibility, and wet pavements providing poorer skidding
resistance
- Flooding, whether catchment or coastal in origin,
which can create areas of deep ponding that may not be
apparent to road users
- Winter conditions, which can result in poorer
skidding resistance
- High winds, which can result in unexpected forces
being applied to vehicles, affecting driving
behaviour
- Fog, which can reduce visibility
While the occurrence of some of these events, such as
winter conditions and fog, may reduce in the future,
instances of others are expected to increase. Due to
natural variability in weather events, it is not possible
to eliminate all of these potential effects completely
through design. Therefore, there is the potential for road
safety hazards to continue to occur. Although effective
management of the road network can provide additional
information to road users, the avoidance of these hazards
is largely dependent on road users modifying their
behaviour in response to this information. It is considered
that ongoing road user education is an essential component
in raising the awareness of the need to modify behaviour
during severe weather events. It is also considered that
the provision of relevant information to road users in
respect of such events would assist in encouraging modified
behaviour.
The Scottish Executive already supports a range of road
user education programmes, including anti drink-driving and
speed reduction campaigns. An example of this in relation
to weather is the guidance provided to drivers relating to
winter weather conditions. It is recommended that
consideration be given to developing a similar approach for
all severe weather events where modified driver behaviour
would be desirable. This could clearly identify specific
messages, such as the need to reduce speed in poor
visibility.
To further support this road user education programme,
it is recommended that the specific messages for driver
behaviour in severe weather conditions be incorporated into
the information provided to drivers through the Variable
Message Signs (
VMS) operated by
NADICS. This would have the benefit of
reinforcing the specific messages. It could also encourage
improved road user behaviour than is observed at
present.

Figure 5.13 - Variable Message Sign on the M8
near Glasgow
In addition, it is recommended that consideration be
given to the use of
VMS's to convey additional information
relating to severe weather events. This would be of local
relevance and, for example, could indicate the risk of
heavy rain, or the likelihood of fog. These messages,
conveyed in terms of probability, would inform road users
of changing circumstances. It is understood that expansion
of the
VMS network is planned and this would
afford the ability to convey locally relevant information.
It is acknowledged that the systems required to support
dissemination of this information would entail additional
capital expenditure. However, it is considered that
opportunities exist to integrate these with existing
weather monitoring and prediction systems, thus minimising
the expenditure required.