« Previous | Contents | Next »
Listen
1 INTRODUCTION
In August 2004 Scotland experienced rainfall
substantially in excess of the norm. Some areas of Scotland
received in excess of three times the 30-year average
August rainfall. In the Perth and Kinross area figures of
the order of between two and a half and three times were
typical. While the percentage rainfall during August
reduced to the west, parts of Stirling and Argyll &
Bute still received between two and two and a half times
the monthly average
1.
The rainfall was both intense and long lasting and a
large number of landslides, in the form of debris flows (
see Section 2), were
experienced in the hills of Scotland. A small number of
these intersected with the trunk road network, notably the
A83 between Glen Kinglas and to the north of Cairndow (9
August), the A9 to the north of Dunkeld (11 August), and
the A85 at Glen Ogle (18 August).
While major injuries were avoided, some 57 people were
taken to safety by helicopter after being trapped between
the two debris flows on the A85 in Glen Ogle (
see picture (© Perthshire
Picture Agency, PPA:
www.ppapix.co.uk)).
The A85, carrying up to 5,600 vehicles per day
2, was closed for four days. The A83, which carries
around 5,000 vehicles per day, was closed for two days; and
the A9, carrying 13,500 vehicles per day, was closed for
two days prior to reopening. The disruption experienced by
local and tourist traffic, as well as to goods vehicles,
was substantial.
Debris flows occur with some frequency in Scotland,
albeit affecting the trunk road and the main local road
network only rarely. However, when they do impact on the
road network the degree of damage, in terms of the
infrastructure and the loss of utility to road users, can
have a major detrimental effect on both economic and social
aspects of the use of the road network. Additionally, there
is a high potential for such events to cause serious injury
and even loss of life although, fortuitously, such
consequences have been limited to date.
Within the recent past, debris flow activity in Scotland
has occurred largely in the periods July to August and
November to January, but there is no certainty that such a
pattern will be continued in the future. However, eastern
parts of Scotland do receive their highest levels of
rainfall in August. Additionally, climate change models
indicate that rainfall levels will increase in the winter
but decrease during the summer months but that intense
storm events will increase in number. These factors,
therefore, may change both the frequency and the annual
pattern of debris flow events.
The impacts of such events are particularly serious
during the summer months due to the major contribution that
tourism makes to Scotland's economy. Nevertheless, the
impacts of debris flow events during the winter months
should not be underestimated.
The need to act has been recognised by the Scottish
Executive and this initial study (Study 1, Part 1) has been
commissioned alongside a second study (Study 2). Study 2 is
designed to identify the potential impacts and consequent
necessary actions in the light of anticipated climate
change and is not considered further in this report,
although it is important to note that action has been taken
to ensure that the two studies are complementary.
As indicated above, this study, termed
Study 1, comprises two parts and it is
Part 1 that is reported here. Part 1 deals
with the following activities:
- Considering the options for undertaking a detailed
review of side slopes adjacent to the trunk road
network and recommending a course of action.
- Outlining possible mitigation measures and
management strategies that might be adopted.
- Undertaking an initial review to identify obvious
areas that have the greatest potential for similar
events in the future.
This work will lead to
Study 1,
Part 2 which will include the development
of a system to allow a detailed review of the network to be
undertaken to identify the locations of greatest hazard and
for those hazards to be ranked and appropriate mitigation
and/or management measures to be selected.
The overall purpose of these studies is thus to ensure
that the Scottish Executive has a system in place for
assessing the hazards posed by debris flows. In addition,
the system will rank the hazards in terms of their
potential relative effects on road users. This will ensure
that the exposure of road users to the consequences of
future debris flow events is minimised whilst acknowledging
that it is not possible to prevent the occurrence of such
events.
A consistent, repeatable and reproducible system is
required. This is especially important as a variety of
consultants is likely to be involved in the data gathering,
analysis and interpretation process. It is apparent at the
outset that a unified system acceptable to all of the major
players in the industry is required.
It was thus recognised at an early stage of the
development of the work that the input of a wide range of
experts and stakeholders would be required in order for the
studies to be completed successfully.
A Project Workshop was held in order to capture the
knowledge vested with individual experts. The Project
Workshop was facilitated by Professor Malcolm Horner of the
University of Dundee and comprised presentations given by
acknowledged experts followed by focussed discussion
sessions designed to open out the knowledge base and
determine the way forward with the project.
Following the Project Workshop the Report Editors
assigned tasks to individuals (including to themselves) in
terms of the preparation of a Technical Report (Winter
et al., 2005). The individuals were selected in
order to enable those most suited to the various tasks to
bring their knowledge, expertise and experience to bear on
the relevant issues. The individuals involved and their
affiliations are detailed on page 6. The work has been
funded through a variety of existing contracts with the
close and active involvement and support of Scottish
Executive engineers as key members of the Working
Group.
The Technical Report is intended to assist the
professionals charged with taking the work on landslides
forward to implementation and also to provide information
for the wider professional community. This Summary Report
is intended to inform a wider audience of the Scottish
Executive's actions both since the events of August 2004
and planned for the future.
Section 2 of the Summary Report gives the background to
the Study as a whole. It describes the different types of
landslide, focussing on debris flows as recently
experienced, and illustrates the recent history of debris
flows in Scotland with examples right up to the present. It
also deals with climatic issues and identifies data
relevant to future work on landslides.
Section 3 describes the proposed assessment methodology
in terms of hazard assessment and approach for Study 1,
Part 2 and also details the hazard assessment and exposure
factors that will form the core of the methodology for the
detailed assessment.
Section 4 identifies areas of high hazard that are
considered to have the greatest potential for similar
debris flow events in the future and sets out opportunities
for early actions.
Section 5 presents a brief summary of this report and
makes recommendations for the way forward. In terms of
management, the logical and sequential approach of
Detection, Notification and Action (
DNA) is used. This approach is set out
in terms of a response to both precursor conditions, such
as intense rainfall, and also to the management of future
debris flow events.
2 BACKGROUND
2.1 Landslides
Recent extreme rainfall in Scotland has led to events
that have been described in the media using the generic
term 'landslide'. These events have intersected with the
A83 (between Glen Kinglas and to the north of Cairndow), A9
(to the north of Dunkeld) and A85 (Glen Ogle) trunk
roads.
While the recent happenings have been of both high
magnitude (in terms of the amount of material moved) and
severe (in terms of their impact on the trunk road network
and the exposure of its users) it is important to
understand that they are by no means unique. Similar events
have been observed in recent years by Nettleton
et al. (In Press) at Invermoriston, intersecting
the A887, and at Stromeferry, intersecting the A890 local
road. Other events have been observed at A83 Rest and be
Thankful, A9 Slochd, A95 Craigellachie and A84 Strathyre,
for example.
Figure 2.1 presents the five distinct types of landslide
identified by Varnes (1978), as follows (after Escario
et al., 1997).
Figure 2.1 - Types of landslide: (a) falls, (b)
topples, (c) slides, (d) flows, and (e) spreads (after
Escario
et al., 1997).

Varnes (1978) also presented a sixth mode of movement,
Complex Failures. These are failures in
which one of the five types of movement is followed by
another type (or even types).
The recently observed landslide events have been typical
of flow-type landslides. The influence of substantial flows
of water, the stripping of superficial deposits, and the
speed with which debris has both flowed and been deposited
have all been apparent. In many cases the initial trigger
appears to have been the displacement of relatively small
amounts of material, often into a stream channel. This has
added a substantial debris charge to already high and
potentially damaging water flows. The combination of water
with high sediment loadings then has substantial erosive
power. In other cases highly saturated materials have
slumped rapidly downslope in a manner not dissimilar to
that illustrated in Figure 2.1(d).
Such events are typically described as 'debris flows'.
They are distinguished from many other types of landslides
involving shear by their rapid movement as opposed to
relatively slow movements experienced in other failure
types. This is an important distinction and not simply an
academic nicety. Failure to make such a distinction could
very easily lead to inappropriate data being collected and
inappropriate approaches being proposed.
Rockfall-type landslides (Figure 2.1(a) and (b)) are
already the subject of a hazard assessment and ranking
system (McMillan and Matheson, 1977) on the Scottish trunk
road network. While it is important that any system to
emerge from this work on debris flows is compatible with
this system (see Section 3) such falls need not otherwise
be considered further here. Of the remaining types it is
flows, including debris flows and peat flows, which have
most adversely affected the trunk road network in the
recent past and are likely to continue to do so in the
future.
Flows are largely dynamic in their trigger mechanisms
and are generally characterised by rapid erosion and
movement with high proportions of either water or air
acting as a lubricant for the solid material that generally
comprises the bulk of their mass.
Debris flows occur, in the main, because of the
character of natural slopes, the deposits of which they are
comprised, and the amount and duration of rainfall (and
consequent infiltration) to which they are subject. The
fact that they impact on a road network is, irrespective of
the consequences, coincidental in the phenomenological
sense. Debris flows affecting the trunk road network are
not caused by its construction and/or management, except in
unusual circumstances. However, some aspects of the built
environment, including a road network, may contribute to
the outcomes of such events.
It is important to note that debris flows are neither a
recent phenomenon nor an uncommon occurrence. The first
church in the Falkland Islands, for example, was wrecked in
1886 when a "river of liquid peat … roared down from the
hills" (Winchester, 1985). Closer to home, a cloud burst in
1744 resulted in the flow and associated erosion of the
gulley below the summit of Arthur's Seat known today as the
Gutted Haddie (McAdam, 1993). Innes (1983) made a survey of
Scotland based upon aerial maps and marked those 10km by
10km grid squares that showed some sign of debris flow
activity (Figure 2.2), clearly indicating that such
activity is far from unusual.
It is clear that the August 2004 events in Scotland had
the potential to cause injury and even death. However, such
potential was not on the same scale as the reality that is
experienced elsewhere in the world on a regular basis. For
example, in September 2004, torrential rain triggered
massive floods and landslides in
SW China, killing in excess of 170
people and injuring many dozens more
3.
Figure 2.2 - The extent of recorded debris flow
activity in Scotland (from Jones and Lee, 1994; after
Innes, 1983). Note that the figure does not record any
activity in the area around the Rest and be Thankful,
for example. It seems unlikely that there was no such
activity prior to 1983 when the figure was first
published and the data set should thus not be seen as
exhaustive.

2.2 Recent Debris Flows
In recent years debris flow events appear to have had an
increasing effect on the Scottish trunk and local road
network, and the Scottish rail network. At face value this
suggests that such events have become more common. Such a
conclusion would however be somewhat speculative as
comprehensive, detailed records are not generally available
for events that do not impact upon man's activities. What
does appear clear from simple observation is that many
debris flows are initiated on the Scottish hills. However,
only a relatively small number turn into major events that
impact upon road networks or other forms of infrastructure.
This implies that in order to manage the impacts of debris
flows it is necessary to understand the preparatory factors
(that make a slope vulnerable to debris flows), the trigger
factors (that lead to initiation of flows) and any
propagation and/or magnification factors.
A number of debris flows have historically occurred in
the month of August. One example is an event that
intersected the A887 at Invermoriston in 1997 (Figure 2.3).
This event was studied in detail and found to have been
triggered at a point almost 300m vertically and around
2,000m horizontally from the road, close to the source of
the stream which subsequently contained most of the event.
A number of contributory factors were established
(Nettleton
et al., In Press), including the following:
- The lack of water storage volume within the
catchment, both above and below ground.
- The ploughing of agricultural land increases and
accelerates runoff into streams.
- The presence of downslope bedding planes.
- Low permeability bedrock.
- The presence of forestry bridges which temporarily
arrested the flow allowing material to accumulate and
subsequently remobilise with greater erosive
power.
- The presence of a buried cliff providing a large
amount of debris at a point close to the road.
- A steep slope close to the road.
Figure 2.3 - Debris flow at Invermoriston
(A887) in August 1997. (Courtesy of Northpix.)

Many of the features of the slope at Invermoriston, such
as its convex shape (
i.e. steepening downslope) are characteristic
of glacial valleys which are in turn typical of much of the
landscape of Scotland. The event was preceded by rainfall
of both long duration and high intensity. As a result of
the debris flow the road was closed, damage was sustained
to vehicles and a local hotel only narrowly escaped
substantial physical damage.
Debris flow events have also been observed at other
times of the year. They have affected both the A890 and the
railway at Stromeferry in January 1999, October 2000 and
October 2001 (Figure 2.4). The January 1999 and October
2000 events were characterised by the mobilisation of
material from a pre-existent landslide which slipped into a
gully thus providing the source material for the debris
flow event. The October 2001 event was propagated from a
gully that had been infilled with silt, gravel and cobble
fractions. In each case disruption to the road and railway
was experienced.
Figure 2.4 - Debris flow at A890 Stromeferry in
October 2001. (Courtesy of and © copyright Alex
Ingram.)

The effects of forestry have frequently been identified
as, at least, partial causes or propagators of debris flows
in areas such as the Pacific
NW of the
USA (Brunengo, 2002). Logging or
deforestation can have a dramatic effect on the drainage
patterns of a slope, reducing root moisture uptake, slope
reinforcement due to the root systems, and the physical
restraints on downslope water flow for example. Such
effects were especially noted as factors in the triggering
of a translational landslide (not a debris flow) at Loch
Shira adjacent to the A83 trunk road near Inverary in
December 1994.
Returning to the more recent debris flows of August
2004, these occurred at three main locations as discussed
in the following paragraphs.
The A83 was blocked at two locations in Glen Kinglas and
at a point approximately 1km north of Cairndow (Figure 2.5)
and the road here was closed for two days. Numerous smaller
debris flows were also observed on the hill slopes either
side of the glen.
The A9 was blocked by three main debris flows, two of
which corresponded with areas of instability adjacent to
the old A9 which runs parallel to, and upslope from, the
present trunk road (Figure 2.6). In such circumstances both
forest roads and minor roads can act to slow and
concentrate the downslope flow of water and thus aid its
penetration into the slope below. Such a mechanism has been
a factor in a number of previous events such as the washout
that blocked the A83 Rest and be Thankful in the vicinity
of Roadman's Cottage, in 1999.
Figure 2.5 - Debris fan containing boulders
(estimated up to 9 tonnes) at A83 Cairndow.

Figure 2.6 - Hillslope flow which has formed
its own channel by erosion (A9 north of Dunkeld, August
2004). (Courtesy of Alan MacKenzie,
BEAR.)

However, in the A9 Slochd failure of July 2002 it was
the presence of the trunk road that contributed to the
failure of the old road (used as a cycle path) and
consequently to its own failure by undercutting. The
presence of forest tracks was also identified as a factor
in the debris flow at Invermoriston.
In the A85 incident the road was blocked by two
landslides. The southerly slip occurred first and as advice
was being offered to motorists by Operating Company staff a
second landslide occurred to the north of the first (Figure
2.7). The two landslides effectively trapped 20 vehicles,
and 57 occupants were airlifted to safety by
RAF and Royal Navy helicopters (see
cover photograph). In its latter phases the northerly
debris flow surmounted a spur of rock and an unoccupied
Operating Company vehicle that had been parked in the lee
of the spur was swept over the edge of the road and some
distance downslope before it came to rest against a
tree.
Figure 2.7 - View of the second and larger of
the A85 Glen Ogle debris flows, showing the sharp bend
in the channel just above road level.

Since August 2004 further landslides have affected the
Scottish road network on the A82 near Letterfinlay
alongside Loch Lochy (January 2005). In addition rock falls
have affected the A832 near Kinlochewe (December 2004) and
the A82 1.5 miles north of the Corran Ferry junction
(January 2005).
2.3 Climatic Issues
The climate of Scotland in terms of its rainfall may be
very broadly divided into east and west (see Figures 2.8
and 2.9). Data presented by the Meteorological Office
(Anon, 1989) indicates the following key comparisons:
- In the east rainfall generally peaks in August
while in the west the maximum rainfall levels are
reached during the wider period September to January
(Figure 2.8).
- Although rainfall levels in the west are relatively
low in August they increase from a low point in
May.
Both of these scenarios indicate that the soil may be
undergoing a transition from a dry to a wetter state at or
around August, indicating an increased potential for debris
flow and other forms of landslide activity.
The central area, as represented by Pitlochry in Figure
2.8, experiences a mix between the rainfall characteristics
of the 'east' and the 'west'.
Figure 2.8 - Annual average rainfall data for
points in Scotland.

The soil water conditions necessary for debris flows may
be generated by long periods of rainfall or by shorter
intense storms. It is however widely accepted that Scottish
debris flow events are usually preceded by both extended
periods of heavy rainfall (otherwise known as antecedent
rainfall) and intense storms.
A number of important points in relation to landslide
activity may be drawn from climate change model predictions
for Scotland in the 2080s
4, as follows:
- In the summer precipitation will decrease but
increase in the winter.
- That the models are less good at predicting
localised summer storms.
- Such storms are believed to be at least partially
responsible for triggering the events of August
2004.
- Climate data may not give a full picture of the
relationship between precipitation and landslides.
- As climate models generally predict averages the
error limits can be substantial.
- Predicted changes in the number of 'intense' wet
days generally indicate a net increase of less than one
day per annum by the 2080s, with slightly fewer intense
wet days in the summer and more in the winter.
- However, by the 2080s extreme storm event rainfall
depths are predicted to increase by between 10% and
30%, with intense winter rainfall increasing slightly
more than this and that in spring/autumn by slightly
less.
- Summer extreme rainfall depths are predicted to
increase by between 0% and 10%.
- Peak river flows are anticipated to increase
progressively during the 21
st century. Eastern Scotland is expected to
experience larger increases than north-west Scotland
for example.
- The occurrence of snow and the associated
contribution of snowmelt to both river flow and
groundwater are, on the other hand, predicted to
decrease.
- Reductions in snowfall are predicted to be greater
for the eastern and southern parts of Scotland and
least for the central upland areas.
Changes in the factors discussed above coupled with
increased evaporation and plant transpiration, particularly
in the summer, and a longer growing season, leading to
increased root water uptake, are expected to have
substantial effects on soil moisture. The models predict a
10% to 30% decrease in soil moisture for summer/autumn and
an increase of 3% to 5% in the winter. The winter figures
reflect the fact that soils can only contain so much water
and most Scottish soils are already close to saturation in
the winter.
Figure 2.9 - Example of Meteorological Office
30-year monthly average rainfall data for October
(image courtesy of the Meteorological Office).

Reduced soil moisture during the summer and autumn
months may mean that potentially high suction pressures are
generated in the soils that make up some slopes. This may
in turn make the slopes more vulnerable to the effects of
intense storms as the suction pressures can draw water into
the dry slope very rapidly. Cracking of the dry soil may
also aid such effects. These issues are explored in more
detail by Winter
et al. (2005).
The
UKCIP (
UK Climate Impacts Programme) report
considers three periods: the 2020s, the 2050s and the
2080s. In general terms small changes are noted in the
predictions for the 2020s. These changes increase slightly
for the 2050s and slightly further still for the
predictions for the 2080s, reflecting the temporal trends
in temperature and precipitation. Whilst climate models
generally predict averages and the associated error limits
can be substantial, it is also important to note that
inter-annual variability is predicted to increase for many
climate factors. This means that average changes, as
discussed above, may mask more important variability
effects.
2.4 Relevant Information Sources
There is a wide range of information and data available
that is relevant to landslide activity in general and to
debris flows in particular in Scotland.
In the Technical Report a detailed review of the
available data in relation to landslides is presented. Such
data includes that relating to the geology, climate, river
and streams and land use of Scotland. Also of relevance are
traffic data held by the Scottish Executive and
commercially available digital terrain models.
A thorough literature review of more than 100 papers,
articles, publications, reports and books was undertaken.
The results of the review are presented in the main report
and are somewhat beyond the scope of this summary report.
Similarly the many factors influencing debris flow activity
and exposure to such activity identified from the Project
Workshop are also presented in the main report. Also
included in the main report are reviews of debris flow
types and mechanisms and the key contributory factors to
debris flows.
The interested reader is referred to Winter
et al. (2005).
3 PROPOSED METHODOLOGY
3.1 Hazard Assessment
The purpose of the proposed hazard assessment is to
determine stretches of the trunk road network most likely
to be affected by debris flow activity. This will involve
the sequential discarding of unlikely areas, at least in
the early stages.
Two initial sifts are likely to be undertaken. The first
will differentiate between peat and non-peat drift
deposits. The second will be based on slope angle. A
relatively high slope angle (around 26
o to 50
o) will be applied to debris flow formation in
non-peat deposits with a slope angle of around 8
o applied to the run-out zone (between, for
example, the area in which debris flows might form and a
trunk road). Soils that are known to exhibit cohesion may
have a hazard reduction factor applied as they may be less
susceptible to debris flow activity. A relatively low slope
angle (possibly as low as 5
o) will be applied to areas that are covered by
peat. This approach means that most effort in assessing
hazard is expended in those areas of greatest actual hazard
rather than an initial 'blanket' approach which expends
considerable effort in all areas.
The National Landslide Hazard Assessment (
NLHA), based upon NEXTMap and other
data, for landslide hazard zonation (see Winter
et al., 2005) can be rapidly adapted to suit the
purposes of a bespoke initial assessment. In addition to
the factors described above, some account of engineering
soil type is also incorporated. The
NLHA data set incorporates information
from both published and unpublished drift and bedrock
geology maps, the unpublished information not being
otherwise readily available to any other form of
assessment. Proxy data in respect of friction angle (
f') have been developed from drift and bedrock
geology descriptions and are held within the data set.
It is understood that the Meteorological Office have
data on regular storm tracks for intense rainstorms across
England and Wales. While it is not entirely clear whether
such information is currently available for Scotland, it
would be a very useful means of refining the initial
evaluation of hazard if available.
It is also perfectly feasible to attach a higher
assignment of hazard for conditions relating to stream
channel and catchment areas, thus emphasising the perceived
hazard of debris flow development associated with stream
beds.
Once areas of high potential hazard are identified then
more substantive, site specific efforts may be expended in
using a system developed on the basis of the assessment
factors described in Section 3.3. As a first step it is
proposed that a 'ground-truthing' exercise be undertaken by
making a desktop comparison of the results from the initial
Geographical Information System-based (
GIS-based) assessment with those areas
of high hazard assessed during the Project Workshop and
detailed in Section 4.
In terms of the site specific work it is crucial that a
range of sites representing as fully as possible the full
range of conditions likely to be encountered relative to
debris flows in Scotland is evaluated. Further, while the
evaluation of each site should be undertaken by one member
of the Working Group an independent check should be
undertaken by another member of the Working Group. In each
case the results must be compared, evaluated and audited by
the Project Team.
It is important to emphasise that any form of hazard
assessment will determine the most likely areas to suffer
debris flow activity. It remains possible that areas
identified as having lower likelihood may experience such
events if circumstances come together to provide the
necessary triggers. As has been pointed out on many
occasions the precise nature of the ground is uncertain and
residual hazards must be expected. However, the judicious
use of a system such as that proposed should ensure that
apparently anomalous events are rare and that the hazards
are managed to the best effect within budgetary
constraints.
3.2 Hazard Ranking
The assessment of hazard in isolation simply details the
areas most likely to be affected - the likelihood of
occurrence; it does not consider the consequences of such
events. In order to enable the appropriate prioritisation
of management budgets for potential debris flow activity on
the trunk road network the exposure due to the interaction
of debris flows on the network must also be evaluated.
Traditionally the product of the
hazard and
exposure (or consequence) is defined as
the
risk. However, there are a number of ways
in which exposure might be considered. In an ideal world
the exposure resulting from debris flow activity would be
determined in all its contexts. Such contexts include the
exposure to life and limb, social/employment factors
(including the effect upon tourism), environmental factors
and economic factors. To include all such factors would be
a major undertaking and is almost certainly beyond current
capabilities in terms of fully understanding the
interaction between the factors and ensuring that there is
no double-counting (or even treble-counting) of the
exposure factors.
Accordingly the product of hazard and exposure is
referred to in the limited, but direct, sense in which it
is evaluated as a
hazard ranking. The hazard ranking may be
seen as a qualitative/semi-quantitative risk assessment as
opposed to the fully quantitative conventional risk
assessment approach.
The complexity of the interactions of exposure factors
means that many are underpinned by a few relatively simple
measures such as traffic flow, road geometry (especially
sightlines), and the length and, indeed, the existence of a
diversion route. These factors are capable of capturing a
simplified assessment of exposure and thus being imposed on
the basic assessments of hazard to provide the hazard
ranking described above. The process does not, however,
represent a full risk assessment and nor is such a process
either necessary, or desirable, in this case.
Clearly, debris flow activity on the busy A9 to the
north of Perth (traffic flow around 13,500 vehicles per day
- all vehicles two-way, 24 hour
AADT5) would have a far greater effect due to the higher
traffic flows (and higher number of people dependent upon
such traffic movements) than on the much more lightly
trafficked A835 between Ullapool and Braemore Junction
(traffic flow around 2,900 vehicles per day), for example.
If two such lengths of road are found to have the same
level of debris flow hazard (
i.e. the same likelihood of a debris flow
interacting with the road) then some means of
distinguishing between the two and adopting a
prioritisation approach to management and mitigation is
required.
Using the simplified exposure evaluation technique
described above, it is thus almost certain that of the two
examples cited the A9 would be assigned a higher priority
than the A835. This is entirely appropriate as the
interests affected (businesses, commuters, tourists, etc)
by such events would be much greater than on the A835. In
addition, the traffic flows on the A9 are much higher and
the chances of personal injury are therefore
proportionately higher, albeit that this aspect is offset
to some extent by the presence of generally better
sightlines and geometry on the A9.
Accordingly it may be seen that once the level of hazard
has been determined then a further assessment of the
exposure must be applied to a given situation to yield what
we describe henceforth as a hazard ranking. The purpose of
this hazard ranking is primarily to distinguish between
areas with similar hazard levels to allow budgetary
decisions to be made on an informed basis. Secondly, as
indicated above, it is clear that areas with lower hazard
levels may yield higher hazard rankings than areas with
higher hazard levels which may yield lower hazard rankings.
The foregoing, purely hypothetical, comparison of the A9
with the A835 may well be a typical example of such a
situation. The effects of an event on the A9 being so much
greater than one on the A835 that the actual level of
hazard alone does not determine the need for action or
otherwise.
3.3 Detailed Assessment Factors
A very detailed and comprehensive set of factors was
generated at the Project Workshop (see Winter
et al., 2005). However, it is clear that many
factors have the same, or similar, root. For example it
could be argued that depositional regime is the root factor
for others such as density, relative density, air voids,
void ratio, permeability and even saturation.
In this context it is clear that some effort is required
in simplifying the factors determined from the Project
Workshop. Indeed, this section does not address how they
will be defined, but merely identifies the most important
combined factors. Combining the factors and the method for
doing so is a matter to be addressed at an early stage of
Study 1, Part 2.
The factors given below are considered to be a strong
reflection of those that must be incorporated into a hazard
assessment and ranking system. Clearly some are likely to
be used at a very early stage (
e.g. a
GIS-based assessment) while others will
be incorporated into a site-specific assessment
methodology. However it is also recognised that some
refinement of these factors will be undertaken as the
construction of a working hazard assessment and ranking
system is constructed.
3.3.1 Hazard Factors
The first stage assessment, as described in Section 3.1,
considers two categories of debris flow hazard
assessment.
- The first will effectively seek areas of peat on
slope angles of 5
o or greater. While the presence of streams
in the peat will be evaluated these will almost
inevitably be present and further work on a site
specific basis will be required.
- The second will deal with all other types of
surface deposit. The slope angle, engineering soil type
and presence or otherwise of a stream will all be taken
account of. Note that the presence of a trunk road
above, not just below, a hazard zone may present a
threat to that road.
Other factors will be incorporated as the availability
of data permits.
Once the first stage assessments have been undertaken
then more detailed examinations of areas of high hazard
will be required. It is likely that all areas of high
hazard in peat will require site specific assessments. The
key issues for further desk-based assessment of areas of
high hazard in non-peat deposits are as follows:
- The presence of a trunk road within the area of
high hazard or the presence of a suitable run-out zone
(slope angle 8
o or greater) between the area of high
hazard and the trunk road.
- The presence of other topographical features that
may enhance the likelihood of debris flow occurrence.
These include terraces, ditches (natural or otherwise)
or breaks in the slope which may have either a positive
or negative impact on debris flow formation and
transportation and rock outcrops and other natural or
artificial barriers that may retard the formation or
passage of a debris flow.
- The existence of a history of landslide activity at
the location. Such information is available from the
National Landslide Database and
BGS digital maps as well as from
experience and observation.
- Factors relating to bedrock will require some
further investigation. Much of the available research
on Scottish debris flows has indicated a limited
history of debris flows in areas of schist bedrock
materials for example. However, much on-the-ground
experience contradicts this, especially in localities
where the direction of bedrock dip has been found to
approximately coincide with the slope aspect.
- Catchment data such as runoff coefficients and the
catchment size and shape (Anon, 1999).
- The presence of spring lines.
- Deforestation and afforestation as factors
potentially increasing and decreasing the likelihood of
debris flow activity at a given location. In the case
of deforestation the direction of old planting furrows
should be taken into account as these may direct water
into the area of high hazard. Afforestation is a
particularly important factor to consider in the
context of arresting or retarding debris flow
runout.
- The presence of features such as public or forest
roads between the area of high hazard and the trunk
road. These may slow the progress of water and thus
increase the deleterious effects of water ingress
immediately below the feature and/or the presence of
culverts passing under such roads may delay the
downslope passage of debris and thus increase the
debris load of future events.
Storm track data will be incorporated if available, and
30-year average rainfall data will be used as a proxy for
antecedent rainfall if the advice of the Meteorological
Office concurs with its use in this context.
Slope height, slope aspect, earthquakes and the
underlying geological formation are all considered to be
factors that have limited influence on the potential for
debris flow development. However, where slope angle and the
dip/direction of bedrock are known to be coincident then
this might be a factor that adds to the perceived level of
hazard. In addition the presence of a layer of drift and/or
weathered bedrock deposits is considered vital for the
development of debris flows: this must be neither so thin
as to provide inadequate material to develop a debris flow
nor so thick as to damp the dynamic flow.
Detailed geotechnical factors, other than as described
above and including the location of the water table, are
unlikely to be available at other than a detailed site
appraisal stage in which specific mitigation measures are
being evaluated.
3.3.2 Exposure Factors
There are three main factors that would ideally be
incorporated into the assessment of exposure for the
system. These are as follows:
- Traffic flows which not only give an estimate of
the likely number of vehicles that will be delayed due
to an event, but also give an, admittedly indirect,
evaluation of factors such as the potential for
personal injury and indeed the potential damage to the
local economy.
- Factors related to road geometry, such as
sightlines and carriageway width, determine the forward
visibility available to drivers at a given location.
This, in turn, describes the potential visibility of a
hazard and therefore the potential for the driver to
see it in time to stop or take other appropriate
avoiding action. Clearly sightlines will become less
relevant at night when the distance that a driver can
see will be determined by the efficacy of the vehicle
lighting.
- Diversion length improves the estimate of the
potential damage for the local economy, albeit still in
an indirect sense. This will be improved if the
suitability of the diversion for the disrupted traffic
levels, see item (a) above, and for
HGVs can be assessed. Clearly if
there is no diversion then the hazard ranking will need
to reflect this fact.
3.3.3 Compatibility with Existing
Systems
Having discussed these factors it is also clear that the
other landslide hazard assessment and ranking system in use
on Scotland's trunk road network needs to be taken into
account. The Rock Slope Hazard Index system (
ROSHI), developed by McMillan and
Matheson (1997) for the Scottish Executive's use on trunk
roads, considers only rock slopes. However, it gives a
hazard ranking for the purposes of budgetary prioritisation
of management and mitigation measures. Clearly having the
two systems running in parallel and on an entirely
different basis would severely restrict the ability of the
Executive to make rational decisions on expenditure and to
compare rock fall hazards with debris flow hazards. As such
it is important that the end results from the two systems
can be compared.
A detailed assessment (Winter
et al., 2005) indicates that the key element that
must be addressed in order to ensure compatibility is the
means of assessing exposure. In addition ensuring that each
system operates with the same number of hazard ranking
categories with a broad degree of compatibility between
them is also necessary.
4 HIGH HAZARD AREAS AND EARLY
OPPORTUNITIES
The early identification of high hazard sites, on a
subjective basis by acknowledged specialists at the Project
Workshop, would serve the joint functions of assisting
prioritisation of areas for action under Part 2 of the
study, whilst providing, in parallel, a shortlist of sites
appropriate for validating the debris flow hazard model in
its development phase.
The areas considered to present a sufficiently high
hazard to warrant concern was defined. After the Project
Workshop, digital Ordnance Survey mapping (1:50,000 scale)
was used to inspect the areas identified in both plan form
and also using a built in digital elevation model.
The sites identified (in the order in which they were
suggested at the Workshop, and not in any order of
perceived hazard or hazard ranking) are as follows:
- 29km of the A83 between Ardgarten and Loch
Shira.
- 8km of the A84 to the South of Strathyre.
- 6km of the A85 in Glen Ogle.
- 18km of the A87 in Glenshiel (plus a further 17km
either end of Glenshiel).
- 29km of the A82 between Fort Augustus and Lochend
(plus a further 9km to the south).
- 16km of the A835 between Ullapool and Braemore
Junction.
- 22km of the A9 between Dunkeld and Drumochter.
- 1km of the A95 in the Craigellachie area.
- 5.5km of the A86 around Spean Bridge.
- 1.5km of the A87 (Skye) between Gleann
Torra-mhichaig and South of the Raasay ferry.
In terms of minimising potential contributory factors,
some retargeting of maintenance actions could be
productive. Checking of gullies, ditches and catchpits,
with a wider view to that of merely keeping the roadway
itself clear of water, could be undertaken as part of
regular inspections. Where ineffectiveness of the system,
or underperformance under updated drainage criteria, is
suspected, this should be considered in conjunction with
the inspection regime for the roadside side slopes and
remedial action addressed via an appropriate structured
asset management plan. The principles of such a management
approach are set out in
HD 41/03 (
DMRB 4.1.3: Maintenance of Highway
Geotechnical Assets). Critical review of culvert alignments
ought to be carried out as part of inspection and reporting
procedures.
Monitoring measures are already under consideration -
for example, the installation of a rain gauge close to the
A85 - but the use of any such data gained, in conjunction
with longer-duration data available from the Meteorological
Office, needs to be managed appropriately to serve a
worthwhile and consistent function. At a later stage,
informed selection of locations for discrete placement of
additional rain-gauging facilities could be productive, and
should be considered in the light of experience of managing
the information from current sources.
An important action which could be introduced on an
early basis is bringing
NADICS (National Driver Information
Centre Scotland), including both the current and proposed
future network of variable message signs, into the
management loop with regard to route advice when weather
conditions conspire to create situations where sections of
the network might be considered 'at-risk'.
5 THE WAY FORWARD
5.1 Early Opportunities
A number of areas of early opportunities have been
identified in Section 4. These include the use of the areas
of high hazard identified at the Project Workshop as a tool
for 'ground-truthing' the outputs from future debris flow
hazard assessments using both
GIS techniques and site-based
methodologies.
Opportunities for ongoing maintenance and construction
activities to take account of factors that might lower the
likelihood of debris flow activity by the provision of
improved and/or more effective drainage have also been
highlighted. Similarly the installation of rain gauges at
potentially high risk sites and the need to bring
NADICS into the management loop with
respect to route advice have also been recognised.
5.2 Study 1, Part 2
The initial stage of Study 1, Part 2 will be to develop
the methodology for the assessment of hazard and exposure
to provide a hazard ranking, together with the selection of
an appropriate management approach. The second stage will
be to test the methodology before applying it more widely
to the trunk road network.
Figure 5.1 presents a flowchart of the work to be
undertaken.
The initial stage of this work is itself divided into
four elements and can be summarised as follows:
- Development of a debris flow hazard and exposure
assessment system to provide a hazard ranking of
'at-risk' areas of the road network.
- Undertaking a computer-based
GIS assessment as a first stage in
the hazard assessment process.
- Undertaking site specific hazard and exposure
assessments of areas identified by the
GIS as being of higher hazard.
- The identification and development of appropriate
management processes for each category of hazard
ranking.
The
GIS-based assessment will be
used as a first stage in the hazard assessment process.
This will enable site specific assessments to be targeted
in order to obtain better value from such relatively
resource-intensive activities. It will also allow the
elimination of large areas of the network having minimal
hazard.
It is also particularly important to note that the
site-specific assessment will not be a
'drive-by' survey; it will require a highly specialised
detailed site examination which will need to be carried out
using an overall consistent approach. Prior to undertaking
any site surveys it is important that the system is
established for consistently describing and identifying
hazards and the associated exposure. Some of the factors
that will need to be incorporated in such a system, such as
slope angle and the broad nature of the geology, will be
incorporated into the
GIS assessment. Other, more detailed,
factors such as the effects of forestation will need to be
incorporated into the site-based survey. Once a hazard
assessment has been completed it may be combined with an
assessment of the exposure of the road user to that hazard
to give a hazard ranking. This will allow, in-turn, an
appropriate management option to be selected from the range
of options to be developed.
Figure 5.1 - Management and mitigation options
within Study 1, Part 2.

There are a number of potential options which could be
applied to the management of debris flows. These are
addressed in the following paragraphs.
The
'Do-Nothing' approach is intended to be
applied to sites of low hazard ranking for which
substantial expenditure is inappropriate. For such sites,
whilst it is not possible to eliminate the chance of a
landslide event affecting such areas it is seen as
unlikely, largely unforeseeable and/or the exposure is less
serious than at other locations where resources may be
better expended.
The
'Do-Minimum' option, with the potential to
mitigate the impacts of debris flows to some extent
involves simply ensuring that forward plans are in place to
ensure that diversion routes are available and may be
exploited in an expedient and well organised manner.
Diversion route maps and contingency plans are currently
held for many areas of the trunk road network.
Whilst it is not possible to eliminate the chance of a
debris flow event affecting such areas any occurrence is
seen as unlikely and largely unforeseeable and any residual
exposure cannot readily be quantified and is unlikely to
justify the commitment of additional resources which may be
better expended at other locations.
'Do-Something 1' is the first management
option where site specific action is contemplated. Such
action is essentially exposure reduction by managing the
access to and/or actions of the road-using public on the
network at times either when events occur or precursor
rainfall has indicated a high likelihood of landslides
occurring.
The reduction of exposure lends itself to the use of a
simple and memorable three-part management tool, as
follows:
- Detection: The identification of either the
occurrence of an event, by instrumentation (
e.g. tilt meters or acoustic sensors) or
observation (
e.g. Closed-Circuit Television (
CCTV) monitoring or visual patrols
during high likelihood periods), or by the measurement
and/or forecast of precursor conditions (
e.g. rainfall).
- Notification: The dissemination of information
relating to the hazard(s) and exposure(s), by for
example Variable Message Signs (
VMS) including
NADICS signs, media announcements
(radio,
TV, traffic guidance systems and the
web) and "landslide patrols" in marked vehicles.
- Action: The proactive process by which
intervention reduces the exposure of the road user to
the hazard, by for example road closure, convoying of
traffic
6 or traffic diversion.
In the case of short-term to medium-term reaction to
such occurrences, then this
DNA approach can be implemented by
pre-planned actions such as issuing an advisory warning or
closing the road. There may be a case for reacting to
extremely heavy rainfall events in a similar fashion,
especially with warnings. A caveat to this is the need to
consider carefully at what levels the triggers should be
set, in so far as the relationship between rainfall and
landslides in Scotland is by no means fully understood.
Considering the longer-term approach, precursor
triggering conditions (
i.e. rainfall) may enable many of the actions
described above to be taken prior to the occurrence of
major events. Either an extensively enhanced network of
rain gauges installed across Scotland or access to data
derived from radar and of sufficient resolution would be
required. Such work might initially be concentrated on
known storm tracks, if these are available from the
Meteorological Office, and vulnerable slopes. Clearly, if
this approach is taken then close consultation with both
the Geotechnical Engineering Office in Hong Kong, which has
extensive experience of operating such a system albeit in
different climatological and geological conditions, and the
UK Meteorological Office would be highly
desirable.
It is fully expected that it will take some considerable
time and effort to ensure that sufficient data has been
obtained and analysed so as to be able to introduce a
warning system. Even then it must be expected that atypical
events, which are not the subject of warnings, may occur.
Also a number of false alarms may inevitably be expected. A
programme of public and media education and
awareness-raising is also likely to be desirable to
minimise any potential adverse reaction to such
scenarios.
'Do-Something 2' involves more major works
in order to achieve hazard reduction (as opposed to
exposure reduction in the 'Do-Something 1' case). The
approaches involved entail physical measures such as the
protection of the road, reduction of the opportunity for a
debris flow to occur or realignment of the road away from
the area of high hazard. These might include debris
shelters, similar to the one illustrated in Figure 5.2, and
fences (see Figure 5.3).
Figure 5.2 - Stone shelter on A890 northeast of
Stromeferry.

The challenge with hazard reduction is in identifying
locations that are of sufficiently high hazard and exposure
to warrant spending significant sums of money on
engineering works. The lengths of road that have already
been identified in Section 4 are significant. The costs
associated with installing remedial works over the entirety
of such lengths are almost certainly both unaffordable and
unjustifiable. Moreover the environmental impact of such
engineering work should not be underestimated, having a
lasting visual impact at the least and potentially more
serious impacts. It is considered that such works should be
limited to locations where their worth can be proven.
Notwithstanding the foregoing, simple measures can be
taken such as ensuring that that channels and gullies are
kept open can be effective in terms of hazard reduction.
This requires that the maintenance regime is fully
effective both in routine terms and also in response to
periods of high rainfall, flood and slope movement.
Such options need to be considered in the context of the
policy governing the Scottish Executive's overall trunk
road maintenance and construction programme. In general,
these are likely to be of high cost necessitating their
restriction to the very few areas of highest hazard
ranking.
Figure 5.3 - Flexible catch fence.

Clearly
Monitoring and Feedback is fundamental to
the success of the system and key to deriving best value
from the arrangements proposed. The system developed is an
active one and lessons learned from future landslide
events, whether they occur in areas of high or very high
hazard ranking or not, will produce valuable data which
needs to be taken into account in adjusting the parameters
that form the cornerstone of the assessment
methodology.
There exists a need to ensure that actions identified by
the existing Rock Slope Hazard Index system (as developed
in the early 1990s) are carried out on a priority budget
basis. These will include both maintenance works and
re-inspection activities. While the rock slope system and
the proposed landslide system have very different
structures, great efforts have been made to ensure that the
critical exposure evaluation and the output categories are
capable of being mutually compatible.
REFERENCES
Anon. 1989. The climate of Scotland - some facts and
figures. London: The Stationery Office.
Anon. 1999. Flood Estimation Handbook. Wallingford:
Institute of Hydrology.
www.nwl.ac.uk/ih.
Design Manual for Roads and Bridges. London: The
Stationery Office.
DMRB 4.1.3,
HA41/03 Maintenance of Highway
Geotechnical Assets, November 2004.
Escario, M. V., George, L.-A., Cheney, R. A. &
Yamamura, K. 1997. Landslides: techniques for evaluating
hazard
. Report of
PIARC Technical Committee on Earthworks,
Drainage, Subgrade (C12), 12.04B. Paris:
PIARC, World Road Association.
Innes, J. L. 1983. Lichenometric dating of debris flow
deposits in the Scottish Highlands.
Earth Surface Processes and Landforms,
8, 579-588.
Jones, D. K. C. & Lee, E. M. 1994.
Landsliding in Great Britain. London:
HMSO.
McAdam, D. 1993. Edinburgh - a landscape fashioned by
geology. Edinburgh: Scottish Natural Heritage and British
Geological Survey.
McMillan, P. & Matheson, G. D. 1997. A two stage new
system for road rock slope risk assessment.
International Journal of Rock Mechanics & Mineral
Science,34, 3-4, Paper
No. 196.
Nettleton, I. M., Tonks, D. M., Low, B., MacNaughton, S.
& Winter, M. G. In Press. Debris flows from the
perspective of the Scottish Highlands.
Proceedings, 11
th International Conference on Landslides,
Norway, 1-10 September 2005.
Varnes, D. J. 1978. Slope movement types and processes.
In:
Special Report 176: Landslides: Analysis and
Control. (
Eds: Schuster, R. L. & Krizek, R. J.).
Transportation and Road Research Board, National Academy of
Science, Washington D. C., 11-33.
Winchester, S. 1985.
Outposts: Journeys to the Surviving Relics of the
British Empire. London: Penguin.
Winter, M. G., Macgregor, F. & Shackman, L.
(Editors). 2005. Scottish Road Network Landslide Study.
Edinburgh: Scottish Executive.
« Previous | Contents | Next »