« Previous | Contents | Next »
Listen
Appendix C: - Case study
C.1 Menstrie case study
C.1.1 Background
The flood event on the 9 August 2004 caused flooding to
approximately 30 properties in Menstrie. Menstrie lies at
the foothills of the Ochills in the River Devon catchment
and is bisected by Menstrie Burn. Upstream of Menstrie the
Burn flows through a heavily wooded gorge with a steep
channel slope. In Menstrie the burn gradient gradually
slows as it enters the Devon valley. Currently three
crossings exist over Menstrie Burn, the Ochill Road Bridge,
the A91 road bridge and a vehicular access track. In the
August 2004 flood event a footbridge upstream of Burnside
Road was washed onto the access bridge immediately
downstream of Burnside Road.
Flows in the burn were within channel in the upper part
of Menstrie but caused a blockage on a footbridge and
access road bridge at Burnside Road. The footbridge was
washed away and debris caught on the access road. Flood
water left the channel and caused flooding immediately
above the footbridge and more substantially along Burnside
Road and in the new development at Holly Grove, as shown in
Figure C-1.
No records of flood events were found on the Chronology
of British Hydrological Events
21 for either Menstrie Burn or the River Devon. However,
residents who were flooded during this event recall that
there had been 2 similar events during the past 20 years.
Clackmannanshire Council developed a detailed hydraulic
model of the Menstrie Burn and part of the Devon. Cross
sections were taken shortly after the event and wrack marks
of the flood event were surveyed to allow calibration of
the model.
Figure C-1: Flood Extend Menstrie Burn August
2004

C.1.2 Local rainfall
The nearest rainfall station is at Glenochil on the
River Devon. The
FEHCD-
ROM was used to determine the event
rarity for both the 2 hour 15 minute and 20 hour durations
for over both the Glenochil and Menstrie catchments. Table
C-1 displays the results of assessing the event rarity of
the recorded rainfall from the Glenochil station. The
estimated return periods suggest that the 2.25 hour and 20
hour periods of rainfall could be placed at an approximate
25 year and 9 year return period (4% and 11.1%
AEP) respectively.
Table C-1: Design Rainfall Estimates
Location | Duration | Rainfall Depth | Estimated Return Period |
|---|
Hours | mm | Years |
|---|
Glenochil Catchment River Devon | 2.25 | 28.2 | 42 |
Glenochil Catchment River Devon | 20 | 55.6 | 7.9 |
Menstrie Burn Catchment | 2.25 | 28.2 | 25 |
Menstrie Burn Catchment | 20 | 55.6 | 9.2 |
C.1.3 Design Flood Estimates for Menstrie
Burn
As Menstrie Burn is ungauged, initial estimates of
QMED were made from
FEH catchment descriptors for the site.
The initial
QMED estimate from catchment descriptors
was 4.94 m3/s. As it is not recommended to rely on the
catchment descriptors for the
QMED estimate, analogue sites were used
to adjust the
QMED estimate.
A search of the
FEH database identified one suitable
HiFlow site within 40 km of Menstrie Burn to use as an
analogue. Three other stations from the
WINFAP-
FEH pooling group were added as
analogues to estimate the
QMED value in Menstrie Burn as 6.85
m3/s. A flood growth curve for Menstrie Burn was then
calculated using
WINFAP-
FEH and the
UKHiFLOWs dataset. A 200 year target
pooling group was established where the resulting total
number of station years required in the pooling group is 5
times the target return period.
Changes were made to the default pooling group for
Menstrie Burn and the frequency distribution to give the
best fit to the pooled growth curve for Menstrie Burn was
found to be the
GL distribution. Details of the
resulting growth factors and flood frequency curve are
shown in Table C-2.
Table C-2: Design Flood Estimates Menstrie
Burn
Return Period | Growth Factor | Peak Flow (m3/s) at Upstream
Extent |
|---|
2 | 1 | 6.85 |
5 | 1.326 | 9.09 |
10 | 1.531 | 10.49 |
25 | 1.778 | 12.18 |
50 | 1.952 | 13.38 |
100 | 2.119 | 14.52 |
200 | 2.279 | 15.62 |
1000 | 2.625 | 17.99 |
100 + cc | | 18.15 |
These flows were then modelled in a steady state
hydraulic model and an attempt to calibrate the flows
against the known flood levels was made. This proved
difficult to achieve as the wrack marks were much higher
than the modelled flow levels for a 100 year event. In
areas around the bridge blockage the anomalies could be
readily explained by reduction in channel capacity. On
reaches unaffected by blockage the anomaly was not readily
understood. Local residents also explained that they had
suffered similar flooding twice before within the last
15-20 years. There are no definite dates for these events
but if they were of a similar size it would suggest that
the flood in August was no more than a 30 year event.
In order to accommodate the uncertainty in the
QMED estimate for Menstrie Burn the
FEH describes a method to estimate
confidence intervals for
QMED estimates made from catchment
descriptors and adjustment from analogue sites. This is
considered to be a reasonable approach to increase the flow
estimates whilst still adhering to recommendations within
the
FEH. For Menstrie Burn the 68%
confidence intervals for
QMED are estimated to be 4.4 to 10.6
m3/s. Using the upper limit of
QMED for data transfer, revised peak
flow estimates have been derived.
Table C-3: Revised Flood Estimates
Return Period | Growth Factor | Peak Flow (m3/s) at Upstream
Extent |
|---|
2 | 1 | 10.6 |
5 | 1.326 | 14.1 |
10 | 1.531 | 16.3 |
25 | 1.778 | 18.9 |
50 | 1.952 | 20.7 |
100 | 2.119 | 22.5 |
200 | 2.279 | 24.2 |
1000 | 2.625 | 27.9 |
100 + cc | | 28.1 |
In order to determine the peak flow of the flood event
that occurred in Menstrie Burn on the 9 August 2004,
rainfall data of the event needs to be translated into
run-off. The rainfall data for the event was obtained from
the continuous raingauge located at the Glenochil gauging
station. Figure C-2 shows the recorded rainfall at the
station over a 20 hour period from 23:00
GMT 8 August till 19:00
GMT 9 August 2004. The recorded rainfall
depth over the 20 hour period was 55.6 mm. The most intense
burst of rainfall during the event occurred in a period of
2 hours and 15 minutes from 15:15 - 17:30 on the 9 August.
During this period 28.2 mm of rain was recorded.
There are a number of problems in relating the recorded
rainfall at the Glenochil station to generate an estimated
flow for the flood event that took place in Menstrie Burn
on the 9 August 2004. Firstly assessing the rarity of a
storm is a subjective process which involves defining the
start and end of the rainfall event and simplifying the
spatial and temporal variation in rainfall that occurs over
the catchment. The Glenochil station is outside the
catchment for the Menstrie Burn and is situated in
topography that is not typical of the Menstrie catchment.
Therefore there is a degree of doubt over the suitability
of using the Glenochil rainfall as representative of the
rainfall that fell over the Menstrie catchment during the
flood event.
The
FEH module of
ISIS was used to generate a hydrograph
from the recorded Glenochil rainfall for the 20 hour
duration. Catchment characteristics for the Menstrie
catchment were imported from the
FEHCD-
ROM. Due to the lack of rainfall and
flood data for Menstrie Burn the unit hydrograph was
calculated from the
FEH catchment characteristics and a time
to peak (Tp) of 2.25 hours was calculated for the Menstrie
catchment. The standard percentage run-off (
SPR) for the catchment should ideally be
calculated from flood event data, however in this case it
was again estimated from the
FEH catchment descriptors as 44.8. The
calculated hydrograph is shown in Figure C-2 and with a
calculated flood peak of 14.66 m3/s at 18:45
GMT. The modelled peak of 14.66 m3/s is
roughly equivalent to the estimated 100 year peak flow for
Menstrie Burn using the initial statistical method
adjusting the predictions and using the upper confidence
limit revises the flow to one between a 5 and 10 year
event.
When considering that the estimated return period for
the rainfall event was calculated as 25 years (4%
AEP) and three events of similar
magnitude have occurred over less than 20 years the lower
return seemed more reasonable. The rainfall run off model
was tested for sensitivity of the
SPR values by adjusting it by +/- 10%.
The estimated flood peaks and there equivalent peak flow
return periods from the statistical method are shown in
Table C-4. It shows that the generated hydrograph is
sensitive to the adjustment of the
SPR value and that it can have a
significant effect on the estimated peak flow and the
estimated return period of the flood.
Table C-4: Sensitivity of Rainfall Run-off
Model
| Standard Percentage Run-off (
SPR) | Rainfall/Run-off Peak Flow
(m3/s) | Estimated Return Period from
initial Statistical Flows (Years) | Estimated Return Period from upper
confidence limit Flows (Years) |
|---|
SPR-10% | 40.32 | 12.39 | 30 | 2-5 |
|---|
SPRFEH | 44.80 | 14.66 | 100 | 5 |
|---|
SPR+10% | 49.28 | 15.14 | <200 | <10 |
|---|
Figure C-2:
ISIS computed hydrograph of the
flood event in Menstrie on the 9th August 2004

It was thus concluded that the August 2004 event on the
Menstrie Burn was closer to a 10 year fluvial flood.
« Previous | Contents | Next »