« Previous | Contents | Next »
Listen
REGULATORY IMPACT ASSESSMENT
1. Introduction
1.1 The Water Framework Directive (Directive 2000/60/
EC) came into force in 2000. It was
transposed into Scots Law by the Water Environment and
Water Services (Scotland) (
WEWS) Act (2003). Among other things,
the Directive requires that Scotland has a system of
regulatory controls for the following activities:
- Point source discharges and diffuse sources liable
to cause pollution;
- The abstraction of water from the water
environment;
- The impoundment of surface water;
- Alterations to the structure and condition of
surface water habitats; and
- Artificial recharge or augmentation of
groundwater
1.2 Although we already have a control system for point
source discharges, we do not have comprehensive systems of
control for the other activities. Section 20 of the
WEWS Act gave Scottish Ministers powers
to make Regulations to introduce such controls. The
Controlled Activities Regulations ('the Regulations' or '
CAR') are being introduced by the
Scottish Executive to provide the required controls, except
for controls over diffuse pollution which are being
considered separately.
1.3 The Directive's overall objectives are to prevent
deterioration of the status of the water environment and to
aim to restore waters to good status by 2015. This will be
achieved through the river basin management planning
process. A draft plan must be prepared by 2008, with the
full plan in place by 2009. This plan must set a programme
of measures to meet the Directive's good status
objectives.
1.4 The introduction of the Regulations at this time is
necessary for three reasons:
- to prevent deterioration in status;
- to ensure that the regulatory process of
identifying and agreeing the control measures and the
environmental improvements they will deliver can be
completed by the Directive's deadline in 2009; and
- to provide stakeholders with sufficient certainty
for investment planning purposes and a longer lead-in
time for delivering the necessary improvements.
2. Scope of this Regulatory Impact
Assessment
2.1 A Regulatory Impact Assessment (
RIA) for the
WEWS Act was presented to the Scottish
Parliament in 2003. This
RIA for the Controlled Activities
Regulations does not consider those costs that would arise
irrespective of their introduction. Such costs include
those resulting from the
WEWS Act requirements for river basin
management planning and environmental monitoring.
2.2 As noted above, the overall objectives of the
Directive are to prevent deterioration of the status of the
water environment and to aim to restore waters to good
status by 2015. In transferring existing authorisations
into the new
CAR regime
SEPA will set conditions which reflect
existing conditions or practice.
SEPA's review of licences, planned from
2006 onwards, will focus on water bodies at risk of not
meeting the Directive's environmental objectives. As part
of that review
SEPA will identify and agree with
businesses the measures required to meet those objectives.
That discussion process will help to inform the river basin
management planning process. The Regulations will enable
specific conditions to be placed on the operation of
controlled activities. Water users must take the measures
necessary to comply with the agreed conditions by 22
December 2012, in order to meet the Directive's objectives
by 2015.
2.3 However during the process of designing improvement
programmes alternative objectives can be identified. For
example, if the measures needed to achieve good status by
2015 would be disproportionately expensive, the timetable
for achieving good status can be extended or a less
stringent objective than good status can be set.
2.4 The process of developing a first programme of
measures and setting environmental objectives has to be
completed as part of the development of the draft river
basin management plans, due to be published at the end of
2008 and setting out the proposed objectives. The full
compliance costs of delivering those objectives cannot be
properly estimated until then.
2.5 In summary, whilst these Regulations will be the key
tool for delivering our environmental objectives, it is the
river basin planning process which will drive compliance
costs, not the Regulations themselves. This
RIA's main focus is therefore on the
costs and benefits of the proposed regulatory regimes
themselves rather than the costs and benefits of the longer
term compliance measures that may be required of water
users. Further information on the costs and benefits of the
measures required will be provided when the draft plan is
produced in 2008.
2.6 The costs incurred by
SEPA in operating the regulatory regimes
will be recovered through charging to operators. These
costs may be offset by grant-in-aid allocated by Scottish
Ministers under the spending review process. The Scottish
Executive has worked closely with
SEPA to ensure that both the structure
of the regulatory regimes and the way in which they will be
implemented by
SEPA strike the right balance between
costs and effectiveness.
3. Purpose of Controlled Activities
Regulations
3.1 The proposed Regulations will establish a framework
allowing
SEPA to control certain activities that
could have, or are having, an adverse impact on the water
environment.
3.2 The controlled activities are:
- activities liable to cause pollution of the water
environment
- abstraction of water from the water
environment
- the construction, alteration or operation of
impounding works in surface waters or wetlands
- carrying out building, engineering, or other
works
- in inland water other than groundwater, or
wetlands, or
- in the vicinity of inland water or wetlands, and
likely to have a significant adverse effect on the
water environment
- artificial recharge or augmentation of
groundwater.
3.3 In its recently completed pressures and impacts
analysis,
SEPA estimated the extent of rivers and
lochs likely to be adversely affected by these activities.
The results are summarised in Table 1.
Table 1: Waters identified by
SEPA's pressures and impacts
analysis as being at risk of failing to achieve good
status
| Rivers | Freshwater lochs |
|---|
Total length/ area assessed | 25,000 km | 1,000 km2 |
|---|
Waters affected by pollution | 8,000 km | 450 km2 |
|---|
Waters affected by abstraction or
impoundment | 7,000 km | 420 km2 |
|---|
Waters affected by building, engineering or
other works | 9,000 km | 450 km2 |
|---|
3.4 There are currently disparate and, in many
instances, only partial controls on the abstraction of
water, the impoundment of surface water and on engineering
works affecting the water environment. The introduction of
comprehensive control regimes for these activities is
expected to be the most significant effect of the
Controlled Activities Regulations.
3.5 At present, point source discharges are controlled
through the Control of Pollution Act (
CoPA) 1974. The Regulations will not
significantly affect the overall costs of regulating point
source discharges in the period to 2009. However, the new
regulatory structure will reduce the cost of regulating low
risk discharges. This will enable
SEPA to concentrate more regulatory
effort on tackling those discharges that are presenting a
significant risk to the water environment.
3.6 Some of the measures included in
CAR, especially the general binding
rules, can be expected to have an effect on diffuse
pollution, and their costs and benefits are thus estimated
in this
RIA. However, further controls will be
needed to tackle diffuse pollution both in rural and in
urban settings. This will be the subject of separate
consideration by the Scottish Executive.
3.7 At present, artificial recharge or augmentation of
groundwater is not a common practice in Scotland.
3.8 The Directive does not require environmental
improvement measures to be in place until the end of 2012.
However, the process of identifying and agreeing the
objectives and the measures needed to achieve them has to
be completed by the end of 2009. As outlined above, the
Scottish Executive is introducing the Regulations at this
time to:
- Enable deterioration of the status of the water
environment to be prevented. Among other things, this
will protect the water environment from damage that, if
it occurred, might subsequently need to be remedied
using costly restoration measures;
- Minimise the period in which there is uncertainty
for businesses over the measures that will be required
of them from 2012 to achieve the objectives of the
Directive; and
- Provide sufficient time for the development of a
programme of measures before the first river basin
management plans must be finalised in 2009.
Reducing the regulatory burden
In line with the aims of the Hampton Report, the
Scottish Executive's intent in introducing the Controlled
Activities Regulations is to provide for selective,
proportionate and streamlined control regimes. To achieve
this, the Regulations will establish:
- A new comprehensive control regime for each
controlled activity. This will facilitate consistent
and readily understood regulation
- A simple and flexible system of regulatory control
options, including general binding rules, registration
and licensing. This will enable regulatory effort to be
focused on those activities posing the greatest risks
to the water environment
- A common structure and operating procedure for all
the control regimes. This will enable streamlined
approaches, such as the use of a single licence to
authorise several different controlled activities being
conducted by a water user
- A single regulatory authority,
SEPA. This will provide for
cost-efficiencies in the management of the control
regimes
4. Estimates of impacts and environmental benefits
4.1 The recent pressures and impacts analysis provides
information on the pressures on the water environment by
sector. From this, it is possible to predict where the
majority of the impacts of the Regulations are likely to
fall:
ii) Abstractions: The biggest impact is likely to
be on the public water supply sector, the hydropower
sector, the drinks manufacturing sector and the agriculture
sector. There may be moderate impacts on other sectors,
such as mining.
iii) Impoundments/flow regulation: The largest
impact is likely to be on the hydropower sector and the
water supply sector. There may be moderate impacts on some
other sectors.
iv) Engineering work: A modest impact is likely on
local authorities, the construction sector and the
agriculture sector. There may be limited impacts on other
sectors.
4.2
SEPA has made a first tentative estimate
of the scale of environmental improvements that are likely
to be delivered through the Controlled Activities
Regulations.
4.3 These estimates are based on:
- The results of the analysis of the pressures and
impacts on the water environment, which has recently
been completed by
SEPA;
- An assessment of the potential measures that would
be required to address the impacts indicated by the
pressures and impacts analysis; and
- The results of the Quality and Standards III
planning process, which has recently been undertaken by
the Scottish Executive to determine the level of
investment to be made in environmental improvements by
Scottish Water.
Table 2: First estimate of the improvements in
water quality to which the Regulations are expected to
contribute by 2015
| Rivers | Lochs |
|---|
Estimate of total adversely affected by
point source pollution
1 | 4,000 km | 230 km2 |
|---|
Initial estimate of improvements to which
the Regulations will contribute | 1,600 km | 15 km2 |
|---|
Proportion improved of the total affected by
point source pollution | 41 % | 7 % |
|---|
Table 3: First estimate of the improvements in
river flows and loch water levels expected to be
delivered by the Regulations by 2015
| Rivers | Lochs |
|---|
Estimate of total adversely affected by
abstraction and impoundment | 7,000 km | 450 km2 |
|---|
Initial estimate of improvements expected to
result from the Regulations | 1,100 km | 70 km2 |
|---|
Proportion improved of the total affected by
abstraction and impoundment | 16% | 16% |
|---|
4.4 The Regulations do not provide for the restoration
of damage to the physical habitats of surface waters
resulting from past engineering works. Consequently, the
Regulations' effectiveness in remedying existing physical
damage will be limited to securing improved practices in
relation to on-going maintenance works, such as river
channel dredging. It has not been possible at this stage to
estimate the scale of improvements that controls on such
on-going works may be able to deliver.
5. Risk Assessment and Directive
compliance
5.1 The
UK is under an obligation to comply with
EU Directives. Failure to do so may
result in proceedings in the
EU Court of Justice.
5.2 Article 11(3)(e) of the Directive requires Member
States to establish controls over the abstraction of fresh
surface water and groundwater, and impoundment of fresh
surface water.
5.3 Article 11(3)(f) of the Directive requires Member
States to establish controls on artificial recharge or
augmentation of groundwater bodies.
5.4 Article 11(3)(g) requires Member States to establish
controls on point source discharges liable to cause
pollution.
5.5 Article 11(3)(h) requires Member States to establish
controls on diffuse sources liable to cause pollution.
5.6 Article 11(3)(i) requires Member States to establish
controls on other activities liable to adversely affect the
water environment, such as engineering works on rivers and
lochs.
5.7 Article 11(3)(j) requires Member States to establish
a general prohibition on direct discharges to
groundwater.
5.8 Article 11(7) requires that Member States establish
a programme of measures by 22 December 2009, at the
latest.
5.9 Article 11(7) requires that the programme of
measures be fully operational by 22 December, 2012, at the
latest.
6. Implementation options considered by the
RIA
6.1 The Controlled Activities Regulations will establish
a requirement for prior authorisation of controlled
activities. Authorisation will take one of three forms:
- General Binding Rules(
GBRs): The Regulations will
provide authorisation for specific activities
undertaken in accordance with the relevant rules. Many
low risk and small scale activities, such as
abstractions of less than 10 m3 per day, would be
authorised directly by the Regulations;
- Registration: A range of other small scale activities, such as
septic tank discharges, would be authorised by
registration with
SEPA. This will provide
SEPA with the information needed to
manage the risk of cumulative impacts; and
- Licensing: Large scale and higher
risk activities would be authorised under the
conditions of a licence issued by
SEPA.
6.2 For the purpose of assessing the regulatory impact
of the proposed regulatory framework, a number of options
have been considered. These are:
- Option A: Point source pollution would
continue to be controlled by
SEPA under
CoPA. Controls on other activities
would not be introduced until 2009;
- Option B: The proposed Regulations, as
produced following our consultations in April 2004 and
March 2005;
- Option C: All controlled activities
would as a minimum have to be registered with
SEPA. Medium risk activities would
have to be registered and comply with general binding
rules. Large scale and high risk activities would
require authorisation under the conditions of a licence
issued by
SEPA; and
- Option D: All activities falling under
the scope of the Regulations would need to be licensed
by
SEPA.
6.3 Table 4 summarises the approximate number of
activities
SEPA estimates would be authorised by
the different mechanisms provided for in option B, C and D.
Option A would move to one of these three options from 2009
when river basin management plans and programmes of
measures must be finalised.
Table 4:
SEPA forecasts for the total number
of activities authorised by the different mechanisms
provided for in the options considered by this
RIA
Authorisation mechanism | Directly by a
GBR in the Regulations | Registration with
SEPA | Registration with
SEPA under a
GBR | Licensed by
SEPA |
|---|
Option B | 50,000 | 80,000 | n/a | 15,000 |
|---|
Option C | n/a | 100,000 | 30,000 | 15,000 |
|---|
Option D | n/a | n/a | n/a | 145,000 |
|---|
6.4 Approximately 100,000 of the activities included
under each option in Table 4 are point source discharges
covered by the provisions of the existing
CoPA regime. The additional 45,000
activities are mainly abstractions, with some impoundments
and engineering works.
7. Analysis of the costs and benefits of the
implementation options
7.1 Table 8 at the end of this report provides a
detailed summary analysis of the costs and benefits of the
four regulatory options considered by this
RIA.
The main benefits of Options B, C
and D compared to Option A are: - Enabling compliance with the
requirements of the Water Framework
Directive;
- Enabling
SEPA to prevent
deterioration of the status of the water
environment prior to 2009;
- Significantly reducing the period of
uncertainty for businesses about the
measures that will be required of them to
implement the Directive from 2012;
- Providing
SEPA with the additional
information on water use it needs to
establish alternative objectives and
prepare a coherent river basin management
plan for 2009; and
- Providing
SEPA with the additional
information on water use it needs to design
cost-effective environmental monitoring
programmes by 2006.
|
7.2 Option A does not provide any of the above benefits.
It provides a benefit to water users by delaying the
levying of charges to recover
SEPA's costs by three years until after
2009. However, as outlined in paragraph 8.15 below, this
benefit may be counteracted by increased costs after
2009.
Environmental benefits
7.3 After 2009, all four options would provide an
effective means of delivering progressive improvements in
the status of the water environment. The extent of these
improvements would depend on what could be achieved without
incurring disproportionate expense.
7.4 Options B, C and D may also deliver environmental
benefits prior to 2009 as a result of
SEPA's plan to specify the conditions
required of water users from 2012 when carrying out licence
reviews. There are clear informational benefits to business
from this as it will allow business greater time to plan
the necessary investment needed to comply with the
authorisation conditions. In some cases, businesses may
decide to implement compliance measures prior to 2012. This
will result in the early achievement of environmental
improvements.
Informational benefits
7.5 The information collected through the Regulations on
the scale and location of pressures (e.g. from applications
for authorisation) is necessary to inform the river basin
planning process and in particular the processes of
developing a programme of measures and designing
environmental monitoring programmes.
7.6 Under Option A, no new information would be obtained
through a regulatory process prior to 2009. This would pose
serious problems for the river basin planning process. It
is likely that
SEPA would be unable to develop a
coherent programme of measures for addressing abstraction
and impoundment pressures in time for the first River Basin
Management Plan. This would also expose Scotland to a
serious risk of infraction proceedings.
7.7 Options C and D could provide
SEPA with information on the location of
all activities, including small scale and low risk
activities. The availability of such information would help
SEPA identify and address those
circumstances in which small scale activities contribute,
in combination with other activities, to a cumulative
impact on the water environment. It would also provide
SEPA with a means of taking into account
the needs of small scale activities when taking other
regulatory decisions, such as authorising a large
abstraction that might affect the resource available to a
small scale abstraction.
7.8 Under Option B,
SEPA would be able to obtain, through
the Regulations, the information needed to manage the risks
to the achievement of good status identified in the
pressures and impacts analysis.
SEPA would have to use alternative
sources of information for identifying circumstances in
which small scale activities not registered with
SEPA might be contributing to a
cumulative impact. Such alternatives could include
environmental monitoring, one-off surveys and the use of
information available from other public bodies. For minor
abstractions
SEPA will be able to utilise data
gathered under the proposed Private Water Supply
Regulations
Costs
7.9 The main costs common to all the Options, although
incurred later under Option A, are:
- costs incurred by
SEPA - regulation, administration
and enforcement costs which will be recovered from
water users; and
- costs incurred by businesses - administrative costs
of obtaining authorisation and the costs of compliance
measures.
Regulatory costs
7.10 Table 5 provides estimates of the costs of
regulation, administration and enforcement incurred by
SEPA under the different options in the
period 2005/6 to 2009/10.
Table 5: Estimated costs incurred by
SEPA in implementing the different
options
Option | Average annual costs for the period
2005/6 - 2009/10 |
|---|
Option A
[Introduction of regulations postponed
until after 2009, then option B, C or D] | None |
|---|
Option B
[The proposed Regulations] | £3.5 million |
|---|
Option C
[All activities would require as a
minimum to be registered with
SEPA] | £4.0 million |
|---|
Option D
[All activities would require a
licence] | £4.5 million |
|---|
7.11 The costs shown in Table 5 are the costs incurred
by
SEPA that are directly attributable to
the introduction of the regulatory regimes for abstraction;
impoundment and engineering. They do
not include the costs of:
- Implementing
WEWS Act's requirements, such as
river basin management planning and environmental
monitoring; nor the capital costs of the monitoring
network. These costs will be incurred irrespective of
whether the Regulations are introduced;
- Regulating point source discharges. The costs of
such regulation are not significantly different to the
overall costs of regulating point source discharges
under
CoPA.
7.12 The costs presented above will be recovered from
operators through
SEPA's charging scheme.
SEPA's charging scheme will also recover
the costs associated with those
WEWS Act requirements for environmental
monitoring.
7.13
SEPA are in the process of developing a
charging scheme with stakeholders and there will be a full
consultation before the Regulations come into force. In
addition,
SEPA have already provided stakeholders
with briefing on issues such as indicative application
costs.
Costs to businesses
7.14 The Regulations provide for the authorisation of
several different activities (e.g. a discharge and an
abstraction) in one licence. The ability to licence
discharges and other activities using the same regulatory
framework is expected to reduce administrative costs to
businesses compared to the introduction of additional
disparate control regimes.
7.15 Under Option A, the administrative and compliance
costs to businesses in the period to 2009/10 would be zero.
However, it is anticipated that beyond 2009/10 the costs to
businesses would be higher than under Option B. This is
because businesses would have less time to plan and
implement measures and therefore could have fewer choices
on how to meet the conditions of their authorisation.
SEPA would also be unable to prevent
deterioration of status before 2009. This could add to the
costs to businesses by increasing the extent of improvement
required after 2009.
7.16 Under Option B, many small scale and low risk
activities, such as abstractions of less than 10 m3 a day,
would not normally incur any administrative costs. Under
Options C and D, businesses operating these activities
would incur the administrative costs associated with
registration and licensing requirements, respectively.
7.17 The administrative costs incurred by businesses in
applying for authorisation by registration or licence will
vary. For registration, the administration costs to
businesses are expected to be very low. Businesses would
simply be required to inform
SEPA about the details of the controlled
activity, including its location.
SEPA is developing a simple web-based
registration facility to help minimise the administrative
costs of applying for registration.
7.18 For licence applications, the administrative costs
to businesses will depend on the scale, complexity and
risks posed by the activity. For relatively small scale and
medium risk activities, the administrative costs to
businesses of making an application for a licence would be
expected to be only slightly higher than those for
registering an activity with
SEPA. For higher risk activities,
SEPA may require detailed information to
support a licence application, including an environmental
report. In the most complex cases, applicants may need to
employ consultancy advice and commission environmental
surveys in compiling such reports. However it is also
expected that activities providing an environmental benefit
will not incur charges.
7.19 The main difference in administrative costs between
the options is in relation to small scale and low risk
activities. Table 6 provides a comparison of the relative
administrative costs associated with applications for
authorisation.
Table 6: Relative administrative costs to
businesses associated with applications for
authorisation
Option A | No administrative costs until after 2009
then as Option B, C or D |
|---|
Option B | No administrative costs for around 50,000
activities authorised directly by the
Regulations and which therefore would not need
to apply to
SEPA for authorisation Low, one-off administrative costs for around
80,000 activities that would require
authorisation by registration with
SEPA Medium-high administrative costs for around
15,000 activities that would require
authorisation by licence, and additional
administrative costs would be incurred each
time the responsible person for a licensed
activity was changed |
|---|
Option C | Low, one-off administrative costs for up to
around 130,000 activities that would require
authorisation by registration with
SEPA Medium-high administrative costs for around
15,000 activities that would require
authorisation by licence, and additional
administrative costs would be incurred each
time the responsible person for a licensed
activity was changed |
|---|
Option D | Medium-high initial administrative costs
than Option C for the estimated 145,000
activities that would require authorisation by
licence rather than by registration with
SEPA Subsequently, additional administrative
costs would be incurred each time the
responsible person for a licensed activity was
changed |
|---|
7.20 The compliance costs to businesses would not be
expected to differ between the options. Under all options,
including Option A, conditions requiring any significant
changes to existing operational practice would not come
into effect until 2012. Under all the options, a licence
would include only those conditions necessary to manage the
risk posed by the activity to the water environment. The
cost to businesses of complying with any particular
risk-based condition is likely to vary depending on local
circumstances.
7.21 For example, to manage the risk to the water
environment from an abstraction,
SEPA will require information on the
magnitude of the abstraction. This is likely to be one of
the few new conditions that would apply before 2012. The
accuracy required of such information will be proportionate
to the risk posed by the abstraction, with greater accuracy
generally being required where the risk is high. For low
risk abstractions, including those covered by
GBR or registration under Options B and
C, a simple estimate of the volume to be abstracted and
some means of demonstrating that the volume will not exceed
the authorised limit is all that is likely to be needed.
For high risk activities, more accurate information on the
abstraction will need to be collected and maintained. Water
users may have a number of options for providing such
information depending on the accuracy required and the
means by which they abstract. For example, some water users
will already be metering their abstraction for their own
purposes. Others may be able to calculate the rate of
abstraction based on the characteristics of the pump they
use for the abstraction or on other physical limits or
constraints on the abstraction rate within their
abstraction works. Where an abstractor needs to install a
meter for the purposes of providing
SEPA with the information it requires,
the costs are likely to range from £200 to £300 for a
medium sized abstraction (100 m
3/day) up to around £3,000 to £5,000 for a very
large abstraction (100,000 m
3/day). On occasions there may be additional
costs of installation or access to consider on top of the
set up estimates.
| Quality & Standards 3 (Q&S 3)
is the capital investment programme proposed
for the water industry in Scotland that will
operate between 1st April 2006 and 31st March
2014. In that time period capital projects will
be delivered during the first Programme of
Measures for the Water Framework Directive (
WFD). The same period also
sees the alignment of the objectives of many
existing Directives to the measures required
under the
WFD, and it is with the
objectives of those Directives, and the
overarching aims of the Water Framework
Directive in mind, that the scope of the
investment programme has been developed. Given
that much of the identified investment is being
made on the basis of current requirements, and
that capital will often benefit multiple
environmental drivers, including
WFD objectives, it is not
possible to separate out the capital costs
solely for compliance with
WFD that may be implemented
within the Q&S 3. |
Costs to the Scottish Executive
7.22 Under Option A, the costs of the
WEWS Act requirements for environmental
monitoring other than for water quality in the period
2006/07 - 2008/09 would have to be funded entirely from the
public purse. Under Option B, C and D, the costs of
environmental monitoring directly attributable to
abstraction, impoundment and engineering works would be
recovered from those responsible for the pressures on the
water environment.
7.23 Costs to the Scottish Executive are likely to be
incurred if the requirements of the Water Framework
Directive are not met. Compliance with the Directive is a
legal obligation and failure to do so may result in legal
proceedings. Table 7 summarises the compliance assessment
for each of the options considered by this
RIA.
7.24 Adopting Option A would place
SEPA in a position of being unable to
develop a programme of measures by the Directive's 2009
deadline for doing so and unlikely to be able to make a
programme of measures fully operational by 2012. A failure
to do either would mean non-compliance with the Directive's
requirements.
7.25 Options B, C or D would be expected to enable
compliance with the Directive's requirements.
Table 7: Summary of compliance
assessment
Option A | Non compliance with the requirements of the
Water Framework Directive. High risk of legal proceedings by the
European Court of Justice |
|---|
Option B | Would enable compliance with the Water
Framework Directive's requirements |
|---|
Option C | Would enable compliance with the Water
Framework Directive's requirements |
|---|
Option D | Would enable compliance with the Water
Framework Directive's requirements |
|---|
8. Small Firms Impact Assessment
8.1 In drawing up these proposals for regulation
specific consideration was given to the potential impact of
controls on small businesses, such as rural hotels and
agricultural activities. For many small hotels there will
be a limited impact by the new proposals. In many cases it
will be their use of a septic tank which bring them within
the scope of the Regulations. For agricultural operators it
is more likely to be small abstractions or minor
engineering activities such as dredging ditches which
brings them into the regime.
8.2 Those using septic tanks should already be licensed
through the existing
CoPA scheme. The proposals would be
beneficial to these operators, as the introduction of
registration under
CAR would replace the
CoPA licence. This would be a lower
regulatory control for these businesses.
8.3 Under Option A in the short term there would be an
advantage to small businesses in that they would not incur
additional costs until 2009, although for those operating
septic tanks the existing costs under the
CoPA regime would roll forward. Under
Option B there would be some relatively low costs for those
businesses carrying out small scale and low risk
activities, and for businesses discharging from septic
tanks there would be a lower regulatory burden. This option
also provides the fairest approach as there is equity of
treatment for all operators by ensuring the proposals are
proportionate to risk. Under Options C and D the costs to
small businesses would be disproportionately high.
9. Competition Assessment
9.1 Under Option A and in the short term, Scottish firms
would retain any existing competitive advantage in relation
to firms in England and Wales, where controls on
abstraction and impoundment have been in place since the
1960s. Any such advantage is expected to disappear in 2012,
by which time measures must be fully operational across
Europe. The postponement of the introduction of Regulations
until after 2009 would leave little time for Scottish firms
to properly plan the implementation of the measures
required of them. As a consequence, firms in England and
Wales could gain some competitive advantage. The
introduction of the regulations from 2005 would reduce the
period of uncertainty for Scottish firms and provide them
with a longer period in which to plan the implementation of
the required measures.
9.2 Under Option B, Scottish firms operating small scale
and low risk activities would not incur additional
administrative costs. Under Options C or D, such firms
would incur small administrative costs. The scale of these
costs would not normally be expected to affect a firm's
comparative advantage.
9.3 Scotland, as a relatively sparsely populated and
water rich country, is unlikely to suffer a competitive
disadvantage from the introduction of a common standard of
environmental protection across Europe. The widely
recognised high quality of Scotland's water environment
overall compared to that of many other Member States, and
indeed to that of England & Wales, could act as a
source of comparative advantage.
10.
Enforcement and sanctions
10.1
SEPA, as the regulatory body will be
responsible for enforcement. The provisions to enable
SEPA to take appropriate action will
consist of notices, powers of entry, and enforcement
through the courts when necessary.
11. Monitoring and Review
11.1 The Executive intend to review the Regulations
within 4 years of implementation.
12. Summary and Recommendation
12.1 The recommendation is to take forward Option B, the
Regulations as proposed. This option is considered to offer
the appropriate balance between the administrative costs
incurred by water users and the provision of effective
controls for the protection and improvement of the water
environment.
12.2 Option A of postponing the introduction of
Regulations until after 2009 is not considered to be a
viable option. Scotland's ability to complete the river
basin management planning process by 2009 would be
significantly compromised. Businesses would remain in a
position of uncertainty until after 2009 about the measures
they will be required to take from 2012. It would also
result in non-compliance with the Water Framework Directive
and a serious risk of legal proceedings by the European
Court of Justice.
12.3 Options C and D would both produce greater
informational benefits than the recommended option. This
could lead to more informed programmes of measures in the
future. However, in both options it is considered that the
potential additional benefits are outweighed by the
additional administrative costs to
SEPA and water users.
13. Summary analysis of options
Table 8: Analysis of the costs and benefits of
different regulatory options
Option | Benefits | Costs |
|---|
Option A
[Regulations delayed until 2009] | - No environmental benefits would be
delivered prior to 2009;
- Environmental benefits would be
delivered after 2009 but, because of the
short period for planning by businesses,
the achievement of environmental
improvements would be expected to be
delayed compared to other options;
- No informational benefits would be
provided prior to 2009. Unlike Options B, C
and D, prior to 2009
SEPA would not be able
to obtain information on pressures, or on
the costs of measures to address those
pressures, from water users' applications
for authorisation;
- Regulatory costs would not be incurred
until after 2009. Charging of water users
to recover these costs would also only
commence after 2009
| - There would be no certainty for
businesses about the measures required of
them until after 2009. This would leave
businesses with a very limited period in
which to plan, and raise finance, before
the Directive's deadline of 2012 for making
measures operational. There would be a high
risk that the Directive's deadline for
making measures fully operational would be
missed;
- There would be a significant risk that
deterioration of status would not be
prevented in the period prior to 2009. This
could add significantly to post-2009 costs
of water environment improvements;
- The lack of regulatory information on
abstraction and impoundment pressures would
compromise
SEPA's ability to
efficiently target environmental monitoring
programmes in the first river basin
planning cycle. This could waste monitoring
resources and lead to a failure to provide
suitable monitoring data for river basin
management planning;
- The lack of regulatory information on
pressures and on the costs of measures to
address those pressures would compromise
SEPA's ability to
develop the first river basin management
plans. In particular, there would be
inadequate information for making good
judgements about the most cost-effective
combinations of measures for achieving good
status and for justifying the setting of
alternative objectives;
- A programme of measures could not be
established by the Directive's deadline of
2009;
- The introduction of regulations after
the river basin management plan is adopted
in 2009 would limit the flexibility on
authorisation conditions. For example, it
would be difficult to accommodate appeals
by water users against conditions imposed
after 2009 if doing so would compromise the
objectives adopted in the river basin
management plan;
- All environmental monitoring required
by the
WEWS Act in the period
until 2009 would have to be met from public
funds. This would include those monitoring
and planning costs attributable to
abstraction, impoundment or engineering
pressures on the water environment.
|
Option B
[As per the proposed Regulations] | - SEPA would be able to
prevent deterioration of the status of the
water environment from 2006 onwards;
- Water users would be able to phase in
any improvement measures needed by 2012
from as early as 2006, depending on the
date their authorisation under the
Regulations was reviewed by
SEPA;
- The compliance conditions required of
water users would be identified from as
early as 2006. This would reduce the period
of uncertainty for businesses compared to
Option A and provide time for businesses to
plan, and raise finance for, the necessary
improvements;
- Applications for authorisation would
provide
SEPA with the
information on abstraction and impoundment
pressures necessary to most effectively
target the monitoring programmes for the
first river basin planning cycle;
- Applications for authorisation would
provide
SEPA with both the
information on abstraction and impoundment
pressures and the regulatory process
necessary to establish a programme of
measures and set objectives in time for
inclusion in the river basin management
plan in 2009;
- Environmental monitoring and river
basin planning costs attributable to
abstraction, impoundment or engineering
pressures would be recovered from water
users from 2006 onwards reducing the burden
on the public purse;
- A large number of small scale and low
risk activities, such as all abstractions
of less than 10 m3 a day, would be
authorised directly by the Regulations. In
contrast to Options C and D,
SEPA would not incur any
costs associated with processing
applications for authorisation for such
activities.
SEPA would be able to
focus its regulatory resources on larger
scale and high environmental risk
activities;
- There would be no administrative costs
for operators of significant numbers of
small scale and low risk activities, since
applications for authorisation from
SEPA would not be
required
| - Total financial cost of regulations:
£18 million for regulation by
SEPA in the period 05/06
- 09/10; plus low administrative costs in
respect of 80,000 activities, and
medium-high costs in respect of 15,000
activities;
- Regulatory costs would be incurred, and
recovered by charging water users, from
2006 rather than from 2009 as in Option
A;
- This Option would not require
registration for a range of small scale and
low risk activities, such as abstractions
of less than 10 m3 a day. To identify those
situations where there may be a risk of
cumulative impacts from such activities and
to take account of the needs of these
activities in making its regulatory
decisions,
SEPA would have to use
other means to obtain information on the
location of these activities.
|
Option C
[All activities would require to be at
least registered with
SEPA] | - As Option B except that this Option's
comprehensive registration requirements
would provide
SEPA with information on
the location of all activities, including
small scale and low risk activities. The
availability of such information would make
it easier compared to Option B for
SEPA to identify those
circumstances where there may be a risk of
cumulative impacts and to take account of
the needs of such activities in making its
regulatory decisions
| - Total financial cost of regulations:
£20 million for regulation by
SEPA in the period 05/06
- 09/10; plus low administrative costs in
respect of 130,000 activities, and
medium-high costs in respect of 15,000
activities;
- The requirement to at least register
all activities with
SEPA would impose
administrative costs on operators of small
scale and low risk activities;
- SEPA would incur costs
associated with the processing of large
numbers of applications for authorisation
by registration from operators of small
scale and low risk activities. This could
put pressure on the resources needed to
deal effectively and efficiently with large
scale and higher risk activities;
- The three different levels of
authorisation provided for under this
Option (registration; registration under a
GBR and licensing) would
make this a more complicated regime than
Options B and D. Consequently, the regime
could be more difficult to manage and for
water users to understand.
|
Option D
[All activities would require a
licence] | - As Option C, except that the benefits
attributed to the registration of small
scale and low risk activities would be
delivered by the requirement for such
activities to be authorised by
licensing;
- This Option offers a simpler regulatory
structure than either Options B or C. This
may be easier to understand and
operate.
| - Total financial cost of regulations:
£22 million for regulation by
SEPA in the period 05/06
- 09/10; plus medium-high costs in respect
of 145,000 activities;
- The requirement for all activities to
be licensed by
SEPA would impose
comparatively higher administrative costs
on operators of those activities that
would:
(a) Only require registration under Option
C; or (b) Be authorised by a
GBR or by registration under
Option B; SEPA would incur costs
associated with the processing of large numbers
of licence applications from operators of
relatively small scale and low risk activities.
This could put pressure on the resources needed
to deal effectively and efficiently with larger
scale and higher risk activities. |
Declaration
'I have read the Regulatory Impact Assessment and I am
satisfied that the benefits justify the costs'.
Signed:

Deputy Minister for Environment and Rural
Development
Date

Contact Point:
Tom Harvie-Clark
ERAD-
ASD
Scottish Executive
Victoria Quay
EDINBURGH EH6 6QQTel: 0131 244 0887
Fax: 0131 244 0446
Email:
tom.harvie-clark@scotland.gsi.gov.uk
« Previous | Contents | Next »