| Description | Summary of initial research report on the performance of Public Private Partnerships in Scotland. |
|---|
| ISBN | (Web Only) |
|---|
| Official Print Publication Date | |
|---|
| Website Publication Date | May 13, 2005 |
|---|
Listen
ISBN
0 7559 1097 4 (Web only publication)
This document is also available in
pdf format (164k)
Research Aims
This report summarises the results of a research project
commissioned by the Scottish Executive to:
- Provide an initial assessment of the relative costs
and benefits of Public Private Partnership (
PPP) procurement in comparison to
conventional procurement, and of the underlying causes
of good and bad performance;
- Assess the potential merits of centrally collecting
additional performance monitoring information and other
data in order to inform future
PPP performance evaluations, and
provide recommendations on what data should be
collected.
Methodology
We sent questionnaires to the authority and private
sector contractor responsible for each operational
PPP in Scotland. Figure 1 shows how
capital spend on the 64 live
PPP schemes breaks down by sector. We
also interviewed a sample of public and private sector
contract managers. It is worth noting the inherent
limitations of an interview-based methodology, where those
interviewed have a vested interest in the projects.
Figure 1: Capital value of operational
PPP projects by sector

As the Scottish Executive recognised at the outset, our
study covered a wide range of topics, across many sectors
and can therefore only provide an initial assessment of
PPP performance. Furthermore, our
findings are based on Scotland's earliest
PPPs and many of the lessons learnt from
these projects have already been applied to more recent
PPPs. Nevertheless, we believe that our
research has identified some interesting areas for further
research.
Main Findings
Below we summarise responses to the key questions asked
by the Scottish Executive.
Cost
A Public Sector Comparator (
PSC) was prepared for 84 percent of
projects and in all these cases the proposed
PPP showed a saving versus the
PSC. But to make a full assessment of
the extent to which
PPP procurement delivers overall cost
savings in comparison to conventional procurement we
recommend that a number of
PPP and conventional procurements in the
same sector are compared over a significant length of
time.
Competition
We found a generally healthy level of competition for
the
PPP projects surveyed. The level of
competition appears to have reduced in recent years. This
is an area that the Scottish Executive should continue to
monitor to ensure that the most economically advantageous
price is achieved.
Procurement and Construction
Performance
The
PPP procurement process is expensive and
represents a greater burden for smaller projects. The mean
time taken to procure the
PPP projects surveyed was 28 months,
which was generally perceived to be slower than non-
PPP procurement. We note, though, that
the increased costs and timescales associated with
procurement should be weighed against their impact on
overall timing and value for money. It is also worth noting
that 'bundling' of smaller projects can help to spread
procurement costs across several discrete projects.
The proportion of projects delivered on time showed a
significant improvement over historical experience. There
was also greater price certainty during construction in the
PPP projects surveyed than has been the
case historically using conventional procurement.
Nevertheless, on more than half of projects, the price
changed at the preferred bidder stage because of a change
to the design or service specification.
Design
Our survey found that authorities were happy with design
quality.
PPP projects were perceived to perform
the same as, or slightly better than, non-
PPP projects with respect to aesthetics,
functionality and environment.
These perceptions reflect, in part, the fact that many
authorities played an active role in the design
process.
Innovation
There was evidence from the survey and interviews that
PPP stimulated innovation, although
authorities were less positive about the role played by the
PPP contractors than the contractors
themselves. As with design, we believe that the
authorities' views reflected their level of involvement in
design decisions.
Operational Performance
We found no evidence that
PPP operators delivered a better or
worse standard of service than the public sector.
Authorities commented that service standards were
determined by the standards specified in the contract and
the budget available.
Most authorities thought that the standard of service
met or exceeded expectations. Availability performance was
rated highly, which might reflect the strong financial
incentive on contractors to meet availability targets.
Cleaning and minor repairs were cited as the soft
facilities management (
FM) services where performance was least
satisfactory. Hard
FM services rated relatively poorly.
However, we understand that this reflects some frustration
on the part of authorities over the resolution of snagging
issues and minor repairs, rather than concerns about
lifecycle maintenance. But real issues were raised about
the interaction between hard and soft
FM providers in
PPP structures.
Flexibility
Our survey results showed that authorities find
PPP contracts less flexible than non-
PPP contracts. Authorities reported that
their experience of making changes has been time consuming
and slow. Where changes have been implemented across a
sector they have been delivered later at
PPP facilities.
In interviews, authorities commented that contractual
change procedures were complex and that as a result they
sought to wrap up multiple changes into a single
negotiation and to make one-off payments rather than
changing the financial model. Some authorities expressed
concerns about the costs of new works, in the absence of
the ability to tender them.
Contractual Relationships
Survey evidence showed that the majority of
relationships between authorities and contractors are good.
In interviews it was clear that both parties recognised the
benefits of developing a long-term partnership. Payment
mechanism deductions are being implemented on the majority
of projects.
Budgetary Issues
Many authorities commented that, at the time their
project was procured,
PPP was the only option given their
capital constraints. This does not necessarily suggest that
the
PPP projects undertaken did not provide
value for money, and our survey found that the majority of
authorities considered
PPP to represent good or excellent value
for money (Figure 2).
Figure 2: Authority perceptions of value for
money.

It is too early to compare maintenance strategies
between
PPP projects and contemporary non-
PPP projects. However, our survey
confirmed the observation that
PPP does ensure that funds for
maintenance of particular assets are effectively
ring-fenced over the life of the contract.
Risk Transfer
Survey respondents believed that risks were, for the
most part, allocated appropriately. More issues (for
example concerns about ambiguities in the contract
drafting) were raised in sectors with significant
interfaces between the
PPP contractor, public sector staff,
users and other contractors.
Recommendations for Further Research
The evidence supports the strong view that
PPP transfers construction risk to the
private sector more effectively than historical procurement
methods and is likely to deliver value for money where
there is strong competition and the projects are large.
This is clearer in certain sectors, for example water, than
in others, such as health. Our survey confirmed that the
well known problem of transaction costs for smaller
projects is also an issue in Scotland.
There is not yet enough evidence to conclude whether
PPP transfers post-asset completion
risks any more effectively than conventional procurement.
This should be a focus for future research. At issue is
whether the potential benefits of
PPP, such as whole life costing, are
sufficient to outweigh its disadvantages, such as lack of
flexibility, and whether there might be variations in the
contracting approach that would increase net public sector
benefits without losing the benefits of transfer of
construction cost risks.
We recommend that the Scottish Executive's central
database is extended to collect additional data on the
procurement and construction phases of both
PPP and non-
PPP projects. This will enable real
comparisons to be made about the relative benefits of
PPP procurement in the areas of
competition, timescales, delivery within budget,
construction flexibility, risk transfer and perceptions of
design quality and innovation.
The Scottish Executive should consider holding some cost
benchmarking data centrally to support contract managers
involved in benchmarking or market testing exercises (e.g.
on the input costs for soft facilities management).
Our judgement is that the most valuable areas for
further work relate to the operational phase of
PPPs. In general though, we do not
recommend that the procurement and construction database is
extended to collect operational data at this stage.
Rather, we recommend that the Scottish Executive
commissions sector specific studies to assess the relative
operational performance of
PPP projects. This further work might
include some or all of the following three elements:
- A periodic audit of all
PFI schemes (say every five years)
along the lines of the current work - but also looking
in detail at a smaller number of projects within a
particular sector.
- Detailed studies into some of the specific
components of
PPP contracts identified in this
Study.
- Sector specific studies that seek to compare
performance across
PPP and non-
PPP contracts. We recommend that the
Scottish Executive might consider carrying out a
further, ongoing evaluation of
PPP and non-
PPP schools, building on the work
carried out by Audit Scotland. If possible, such
studies should include the identification of a small
number of standardised cost and performance indicators
that could be collected over time, and be used in a
full comparative efficiency analysis of the sample
projects.
Caroline Low, Daniel Hulls, Alan Rennison
Cambridge Economic Policy Associates