On this page:

PUBLIC PRIVATE PARTNERSHIPS IN SCOTLAND: EVALUATION OF PERFORMANCE Final Report 2005

« Previous | Contents |

Listen

Footnotes

1. Many projects involve some sort of partnership between the public and private sectors. We restricted this study to projects that involve long-term payments to the private sector in return for the provision of a public service asset. PPP projects of this type are often referred to as Private Finance Initiative ( PFI) projects. PPP projects typically differ from conventionally procured projects in that a single contract is let for the design, construction and operation of an asset and long-term financing is provided by the private sector.
2. In most PPP contracts, a significant proportion of the payment to the contractor is linked to the asset being available for use by the public sector at the contracted standard.
3. In contrast with operational risks, construction risks can be measured more easily in terms of whether the assets were delivered to time and budget.
4. The low response rate may also reflect the possibility that some of the smaller projects are not considered by authorities to be 'true' PPPs.
5. Although note that we believe that it should be possible to procure using 'Design, Build and Operate' structures using public finance and gain some or all of these benefits.
6. With the exception of some special situations, for example complex IT contracts.
7. Design, build, finance and operate ( DBFO) as opposed to design, build and operate ( DBO)
8. PFI: Meeting the investment challenge ( HMT), July 2003
9. 1989 in the case of the Skye Bridge project, which was a PPP style project but preceded the private finance initiative.
10. The public sector may be more exposed if the project will be bond-financed since, unlike in the case of bank debt, the margin on the bond is not pre-fixed.
11. For example, increasing the interest rate from 7 percent to 8 percent would increase each annual repayment on a 25 year annuity by 9 percent. Even after discounting at 6 percent real, the increase in NPV could well be greater than 5 percent.
12. The NAO 2001 'Modernising Construction' report found that some 70 percent of projects were delivered late.
13. The 2001 NAO report 'Modernising Construction' found that the 73 percent of government construction projects ran over budget.
14. It was not clear whether this reflects the fact that contracts do not allow authorities access to information or that authorities are not exercising their rights.
15. Only 2 respondents considered that the service exceeded expectations.
16. Local authorities are responsible for PPPs in the education, local transport and waste sectors.
17. One of the issues noted in carrying out this survey has been the time costs imposed on respondents required to answer detailed procurement and financial close questions on projects that closed many years ago.
18. Benchmarked services here relates to the elements of the contract (e.g. soft FM services) were there is an explicit requirement or allowance for benchmarking of costs.
19. This is likely to involve a significant 'benchmarking exercise' of the kind that utility regulators undertake to understand the efficiency of regulated companies.
20. Taking the initiative: using PFI contracts to renew council schools, Audit Scotland 2002

« Previous | Contents |

Page updated: Thursday, May 5, 2005