« Previous | Contents | Next »
Listen
6. Value for Money
6.1. Budgetary issues
87 percent of respondents believed that the use of
PPP had brought forward the timing of
investment. Many commented that, at the time, they would
not have been allocated funding to carry out conventional
procurement. Capital budgets were already allocated to more
pressing projects, in particular to carrying out essential
repairs.
Our understanding is that these responses are an
accurate representation of the reality faced by public
sector managers in local authorities, hospital boards and
within the water and sewerage sectors at that time.
Taking three of the sectors in turn:
- Local authority
16. At the time that the contracts in our Survey
were let, the local authority capital regime in place
involved, in simple terms: (i) the provision of annual
public borrowing consents (together with provision of
rate support grant to cover interest and amortisation
costs) and; (ii) separate funds to enable local
authorities to support
PPP payments on a like for like
basis - e.g. Level Playing Field Support (
LPFS), and the Strategic Waste Fund.
Borrowing consents were allocated to local authority on
a formula basis, whereas the separate funds were
controlled centrally. The impact of this from the local
authorities' perspective was to regard
PPP as additional capital that could
be used from a 'central pot' for projects that were not
prioritised for public borrowing consents.
- Hospitals. The treatment of investment using public
sector capital or
PPP is the same. Both increase the
capital charges faced by the
NHS Board in line with the increase
in the value of its assets. Although capital budgets,
set centrally, have increased dramatically recently, we
understand that there would not have been sufficient
public sector capital available to fund major hospital
PPP contracts (such as The Royal
Infirmary of Edinburgh) at the time they were
procured.
- Water and sewerage sector. In the water and
sewerage sector, the majority of
PPP contracts relate to improvements
in water treatment infrastructure necessary to meet the
requirements of the Urban Waste Water Treatment
Directive. There was not sufficient public capital to
achieve the specified standards by the end of
2000.
32 out of 34 authorities stated that their project was
off the public sector balance sheet.
6.2. Value for money
Figure 18 shows how authorities perceived value
for money at contract letting, and how they perceive it
now. 56 percent of authorities currently believe that the
contract offers good or excellent value for money. Only 1
authority thought that the project offered poor value for
money; in this case bank interest rates had fallen
significantly since financial close, but the project had
not been refinanced to the authority's knowledge.
Figure 18: Authority perceptions of value for
money.

26 projects out of 31 that responded (84 percent) stated
that a Public Sector Comparator (
PSC) had been prepared. The median
saving versus the
PSC was 6 percent; the mean was 13
percent reflecting extremely high savings in a few
projects.
13 projects out of 36 that responded (36 percent) said
that post-financial close evaluation had been carried
out.
In interviews several authorities noted the difficulty
of proving value for money in relation to changes, because
of the lack of competitive pressure. One authority also
commented that insurance costs were significantly higher
for
PPP projects, which had an impact on
value for money compared with conventionally procured
projects.
6.3. Benchmarking
Several interviewees discussed the benchmarking process,
which is now being implemented for the first time in
projects which have been operational for 5 or more years.
Benchmarking relies on independent experts to establish a
comparator price for each service, as opposed to market
testing in which alternative service providers can bid to
replace the incumbent. Interviewees commented that there
had been issues around interpreting the provisions of the
contract and in identifying suitable comparators. One
contractor noted that the private sector was starting to
organise benchmarking clubs.
Interviewees reported that the outcome of benchmarking
exercises to date has been to increase the price paid by
authorities. Labour costs, in particular, have increased
more quickly than many contractors anticipated in their
bids; in the health sector this has been driven by the
NHS Scottish Low Pay Agreement. A
similar outcome would be expected with conventional
short-term outsourcing contracts, where the price would
adjust to the market rate at each re-tendering. However,
some authorities expressed concern that the benchmarking
process could erode value for money by allowing contractors
to make up for any deliberate under-pricing at the bid
stage.
Recommendation: The Scottish Executive
should monitor the process and outcome of benchmarking
exercises in order to inform other projects and future
contracts. It should consider how best to support
authorities in collating benchmarking data, for example by
holding information centrally or by promoting informal
networks.
« Previous | Contents | Next »