« Previous | Contents | Next »
Listen
5. Operational Performance
5.1. Standard of service
Most authorities were happy with the standard of
service, but hard facilities management services rated
relatively poorly.
Figure 13: Standard of service
Service | % rating service
'good' or 'very good' | % who consider service
'meets expectations' or
'exceeds expectations'
15 |
|---|
Availability | 91% | 91% |
|---|
Soft
FM | 73% | 86% |
|---|
Hard
FM | 58% | 70% |
|---|
Almost all authorities were happy with the availability
of the asset. In most
PPP contracts, availability is by far
the most significant factor used in calculating the public
sector's payment to the contractor, and this financial
incentive appears to be working effectively to encourage
good performance in relation to availability. Authorities
were less happy with soft facilities management (
FM) service standards (cleaning,
laundry, catering etc.) and even less happy with hard
facilities management service standards (building repairs
etc.). In general, interviewees noted that performance was
best in those areas where the financial penalties could be
made to bite.
Respondents noted that the quality of soft
FM service is dictated by the terms of
the contract and is not inherently better or worse because
the operator is providing it under a
PPP contract - although in some cases it
is better because the impact of
PPP has been to increase the budget. One
interviewee pointed out that authorities may be very happy
with the standard of service because their main point of
comparison is the service at older, non-
PPP facilities. It is extremely
difficult for authorities to judge whether the service at
PPP facilities is as good as it could be
given the new assets and the service levels set out in the
contract.
Unhappiness with soft
FM provision generally related to lack
of flexibility (
see section 5.5 below). The
other source of unhappiness, raised in several interviews,
was the quality of cleaning, and many authorities cited
cleaning reports as the most important performance
indicator. There were particular issues with cleaning in
some parts of Scotland where contractors had
under-estimated the buoyancy of the local employment market
and had struggled to maintain staff. In some cases
authorities had exercised their right to step in and carry
out one-off cleaning services themselves, passing the costs
on to the contractor. This is a good example of the
contractual remedies working effectively to ensure the
required service to the end users, but is frustrating for
authorities. In some contracts there is the opportunity to
bring cleaning in-house as part of a benchmarking exercise,
but this leads to issues over the interface between hard
FM and soft
FM (for example, using appropriate
cleaning products on the floor so that it sees out its
expected life).
Issues around heating and cooling were also raised by a
number of interviewees. Although contracts include
requirements about allowable temperature ranges, it is
difficult and time consuming for authorities to build up
evidence of a breach. The temperature can differ within one
availability area, and can change rapidly over time - in
most cases the contractor has a period of several hours to
remedy any service failure and so repeated monitoring is
needed to demonstrate that the temperature has not been
corrected.
Unhappiness with hard
FM provision typically related to the
fact that repairs often required input from the
SPV's off-site staff and therefore took
longer. In interviews several authorities commented on the
fact that the
SPV structure caused frustrations when
the on-site
FM contractor needed to refer issues
back to the
SPV for decision or for action by
another consortium member. Repairs which the authority
considered to be minor (and therefore expected to be
resolved by the on-site soft
FM team) were sometimes bundled together
and classed as a major repair, taking longer to be carried
out.
At this relatively early stage in projects' operational
phases, most of the issues about repairs raised in
interviews related to snagging issues left over from the
construction phase rather than to life-cycle maintenance.
(Project managers in the water sector seemed happier with
the transfer of the interface from construction to
operations.) Interviewees noted that it was too early in
the operational period to form judgements on whether life
cycle maintenance was being carried out effectively.
Recommendation: The Scottish Executive
could consider carrying out further research in the area of
hard
FM provision, with the aim of producing
best practice guidelines for authorities and contractors
and informing the terms of future contracts.
5.2. Relationship between authority and
contractor
The 2001
NAO report 'Managing the relationship to
secure a successful partnership in
PFI projects' concluded that
PFI projects need to be approached in a
spirit of partnership, that a successful partnership needs
to be established at the outset and that having staff with
the right skills is critical to good contract
management.
The majority of relationships between authorities
and contractors are good.
Figure 14: Current view of authority contractor
relationship

85 percent of authorities and 92 percent of contractors
said that their relationship was good or very good. There
was very little change between the original and current
views of the relationships between authorities and
contractors, indicating that both parties have made strong
efforts to adopt a spirit of partnership from the
outset.
Our interviews revealed that while generally, as
reported in the questionnaires, relationships between
authorities and contractors are good, some authorities do
find it frustrating that they need to spend a great deal of
time debating interpretations of the contract requirements
and maintaining the pressure on contractors to comply with
the contract. This was particularly evident in the health
sector, probably reflecting the complexity of the
interfaces between the private sector, public sector and
users in this sector, and the potentially severe
consequences of, for example, a power failure or slippery
floor.
It was notable in interviews that relationships appeared
to be working better where the authority was responsible
for a portfolio of projects and was able to use experience
from other projects to make judgements about how to manage
the contractor. Managing a portfolio of projects also
enables more efficient monitoring, for example a dedicated
monitoring team reporting on the cleanliness of a large
group of schools, is more effective than relying on head
teachers to monitor their own schools, alongside their
other responsibilities.
Interviewees noted that the personalities of the
individuals involved had a big effect on the ability to
develop a successful partnership. They also commented that
staff turnover on both the public and private sector sides
of the contract was relatively high, although not out of
line with wider experience in the sector. Authorities noted
that the culture of the major contractor in the
SPV had an impact on how the
relationship was handled and that it was easier to have a
happy relationship where the contractor was profitable.
The contractual disputes resolution procedure had
been used, and all disputes reported had been resolved
without escalation to the courts.
The disputes resolution procedure had been initiated one
or more times on 8 projects and an external adjudicator
used on 4 projects. Most disputes related to practical
interpretation of contractual provisions. Interviewees
commented that it was difficult to find suitably qualified
adjudicators, given that
PPP contracts are relatively new.
5.3. Performance monitoring
PPP contracts should set out how
performance will be monitored, based on output
measures.
Performance monitoring mechanisms are satisfactory
but improvements could be made to performance
indicators.
61 percent of authorities thought that performance
monitoring mechanisms were working well or better, 36
percent thought that they were satisfactory, and only 3
percent thought that they were poor (see
Figure 15 below). These results are very similar
to the
NAO's findings in its 2001 report
'Managing the Relationship'.
Figure 15: How are project and performance
monitoring mechanisms working?

Only 45 percent of authorities thought that the
performance indicators were wholly appropriate for
measuring contractor performance. 52 percent thought that
they were partially appropriate and 3 percent found that
they were not at all appropriate. Despite this lack of
satisfaction with the performance indicators, there were
only a few projects where new indicators had been
negotiated. This could be due to the lack of contract
flexibility or, equally, to the lack of better
alternatives.
Based on our interviews, it appeared that performance
indicators (
KPIs) worked best in sectors such as
prisons, transport and water where there were clear
KPIs for the whole sector, not just
PPP projects. Arguably, these sectors
also have less complex interfaces between the contractor,
public sector staff and systems and users. Interviewees in
other sectors commented that interpretation of the drafting
of performance indicators was often open to discussion.
This issue of ambiguity was exacerbated by changes of
staff. In some cases interviewees felt that too many
indicators were monitored, not all of which were
useful.
Some authorities reported that it was difficult to
establish the right balance between monitoring and
auditing. Several stated that they had not fully understood
their monitoring requirements at the outset of the
contract. They were concerned that, given the impact of the
payment regime, leaving the contractor to self-monitor
would discourage him from being proactive in identifying
and rectifying faults.
Several authorities commented that they were surprised
at the input required on their part to ensure that the
contractor delivered the contracted level of service.
PPP contracts are typically
self-monitoring, with the authority responsible for
auditing the contractor's records of service failures. One
interviewee commented that, while mistakes in the
self-monitoring invariably had to be put down to human
error, the mistakes were skewed in the contractor's
favour.
Authorities commented that the ultimate threat of
default did work to encourage good performance.
Recommendation: There is a strong case for
establishing, for each sector, a relatively short list of
performance indicators, enabling comparison between
PPP and non-
PPP projects. A framework of
benchmarking actual performance against periodically
restated
KPIs and enhanced authority rights to
re-tender the contract in the event of persistent
shortfalls against
KPIs could considerably improve outcomes
in the longer term.
5.4. Contractual remedies
Payment mechanism deductions are being implemented
on the majority of projects, with some minor
relaxations to promote good working relationships.
Out of 32 projects where information was provided in
response to questions about the use of contractual
remedies, 88 percent had made deductions from the payment
mechanism.
Figure 16 shows the contractual remedies used.
Figure 16: Use of contractual remedies

41 percent of authorities said that there had been
occasions when the contract allowed them to enforce
penalties but they had chosen not to. In most cases
authorities said that they had waived penalties when the
amounts were small and the consequences were not
significant, and they felt that it would promote a good
working relationship with the contractor. This approach was
taken particularly at the start of the operational period,
and on the basis that the contractor accepted that there
had been failures and had put in place action plans to
resolve matters.
5.5. Service
flexibility
PPP contracts typically contain a
mechanism for agreeing changes during the operating period.
If the authority wishes to implement a change, it starts by
documenting its request. The contract sets out the
circumstances in which the contractor is obliged to meet
the request, and the process by which he agrees or
disagrees to proceed. Assuming that the contractor has
agreed to proceed, he presents cost estimates, and there
are then further procedures by which the authority accepts
or challenges these estimates until agreement is
reached.
PPP contracts are less flexible than
non-
PPP contracts. Where changes have
been implemented across a sector they have been
delivered later at
PPP facilities.
All contracts in the survey contained provisions to
change the service specification, and these provisions had
been used in 50 percent of contracts. Informal changes had
also been agreed in 28 percent of contracts, for example
changes to opening times or the use of rooms. Interviewees
noted that, where the relationship is good, informal
changes can be made between the operational staff and
periodically swept up into formal variations. All changes
were jointly initiated, or initiated by the authority.
34 percent of authorities considered service levels
under a
PPP contract to be less flexible than
alternative contractual arrangements, for example
short-term contracting out, or where the authority itself
employs staff to carry out the services. 49 percent thought
that the form of contracting made no difference, and only 6
percent considered
PPP contracts to be more flexible. By
contrast, 42 percent of private sector respondents thought
that
PPP contracts were more flexible (see
Figure 17).
Figure 17: How does the flexibility of service
delivery compare with non-
PPP arrangements?

Although contracts set time limits for each step of the
change procedure, the amount of 'to-ing and fro-ing'
between authority and contractor has meant that changes can
be very slow to agree. Several authorities stated that it
had taken one year or longer to agree what they saw as
relatively straightforward changes. The lack of flexibility
in the
PPP sector was particularly apparent
where changes were being implemented across a sector (for
example Patient Line in hospitals, or fresh water drinking
fountains in schools) and were introduced later at
PPP facilities than those operated by
the public sector. Concerns about value for money were a
significant factor in the time taken to agree changes;
authorities often challenged contractors' initial cost
estimates and requested additional information.
Contractors' perceptions that
PPP contracts are more flexible than
non-
PPP arrangements might result from the
fact that there is less need in short-term service
contracts than in long-term
PPP contracts to include complex change
mechanisms.
In interviews both authorities and contractors mentioned
that in order to simplify matters, and avoid making changes
to the project financial model, they often waited until
they could agree a set of changes whose net financial
impact would be zero. Refinancing was also seen as an
opportunity to push through changes.
Recommendation: Further research should be
carried out to look at ways of enhancing flexibility
without losing the benefits of
PPP, focusing on those sectors where
flexibility is a key area (e.g. health).
5.6 Allocation of operational risk
Operational risks are, for the most part,
appropriately allocated.
96 percent of contractors and 85 percent of authorities
thought that risks relating to the ongoing operation of the
asset currently were allocated to the party best able to
manage them. Some of the risk allocations in the earliest
projects had been amended in later projects, for example
vandalism risk was retained by the authority (at least when
the asset was in use), and utilities risk was transferred
to the contractor.
Interviewees commented that appropriate allocation of
risk was most difficult to achieve where there was
significant interaction between contractor, authority and
users. Materials management in hospitals was cited as an
example of a risk that is sometimes transferred to the
contractor but can be difficult for him to manage because
of the need to interact with
NHSIT systems. Allocation of risks relating
to cleanliness can be difficult if more than one contractor
is operating on the same site. This is a particular issue
in Scotland where soft
FM is sometimes carried out in house, or
may be taken in house or let to a different contractor at
fixed points in the contract. The interface between
different contractors can then lead to difficulties in
determining responsibilities if things go wrong.
Interviewees also commented that cost risks arising from
unanticipated behaviour of different users of the asset,
for example greater wear and tear caused by more severely
ill patients in mental health facilities, were not always
clearly allocated in the contract.
The example of Mearns Primary School demonstrates how
the transfer of major risks has worked in practice. When
the roof blew off one wing of the school, the contractor
forfeited a significant amount of its availability payments
and was responsible for the entire cost of repairs.
Although the council was fully protected financially, it
was the council's own staff that responded initially to the
emergency, since the contractor's staff were not based
locally.
« Previous | Contents | Next »