« Previous | Contents | Next »
Listen
4. Design and Construction
4.1. Design
4.1.1. Design quality
Authorities are generally happy with design quality
.
73 percent of authorities who responded rated the design
of their project as good or very good (see
Figure 9 ). There was only one project, in the
water sector, where the authority rated the design as poor;
this was due to technical performance failures and
difficulties in operating and maintaining the plant as
designed. In this case payments were deferred until the
issues resulting from the poor design had been resolved;
the public sector might not have had the same protection
under conventional procurement .
Figure 9: Authority perception of design quality,
at evaluation and now.

There has been little change in authorities' positive
opinions about the quality of design between bid evaluation
and the operational phase. This might reflect the fact that
many authorities were closely involved in scrutinising the
designs and commenting on them at the bidding stage.
Indeed, it is worth noting that the responses to this
question from both authorities and contractors are likely
to be biased, and a wider survey including users and
professional architecture and design bodies might have
given different results.
In interviews, some contractors commented that design
briefs were becoming increasingly prescriptive. But this
should be set against the increasing experience of
authorities in commissioning new buildings and the impact
of standardising design on reducing bidding and procurement
costs. Contractors have the opportunity to submit variant
bids if they believe that an alternative design solution
will offer better value for money.
It was not possible to judge what the impact of
PPP procurement as opposed to
conventional procurement had been on project design.
User feedback
User feedback is generally positive, but more user
surveys could be carried o
20 projects reported that they had evidence of feedback
from users. Feedback mechanisms included formal surveys,
comments from user groups, anecdotal feedback from
employees and users, and complaints procedures. In some
cases, positive feedback was inferred from a lack of
complaints. The majority of feedback about design was
positive.
Recommendation: Authorities should ensure
that formal feedback systems, for example user surveys, are
in place.
4.1.2. Building performance compared with non-
PPP projects
PPP projects are perceived to
perform the same as, or slightly better than, non-
PPP projects with respect to
aesthetics, functionality and environment.
Figure 10 shows authorities' views on the relative
performance of
PPP projects. Most authorities did not
perceive a difference in aesthetics, functionality or
environmental performance between
PPP and non-
PPP projects, although some believed
that
PPPs perform better.
Figure 10: Comparison of
PPP and non-
PPP projects with respect to
aesthetics, functionality and environment

Where authorities believed that
PPP had delivered a better solution,
they ascribed this to the impact of life-cycle maintenance
and hand-back requirements on the design approach, the
impact of transferred utilities risk on energy efficient
design, and the output-based specification allowing greater
scope for imaginative and individual aesthetic design.
Where authorities did not perceive a difference, they
commented that building standards and the environmental and
functional specification provided to the contractor would
be the same whatever the procurement method, and that they
would have expected to have had the same input into the
design whether
PPP had been used or not.
4.1.3. Design tools
Formal design evaluation tools were not used.
Only one project reported that the Quality Indicators in
the Design of Schools (
QIDS) tool had been used for evaluation,
the remainder of projects had used expert panels to
evaluate the design but had not used generic design tools.
The majority of projects surveyed were evaluated before
formal evaluation tools were developed. Several authorities
commented that the involvement of users, for example
clinicians in hospital projects, had helped to develop the
functionality of designs and to improve user satisfaction
once the asset was operational.
4.1.4. Innovation
There is evidence that
PPP stimulated innovation, although
contractors are more positive than authorities about
the impact.
Contractors were more positive than authorities about
the innovation demonstrated in the projects surveyed: 39
percent of contractors believed that they had shown
considerable innovation, only 25 percent of authorities
agreed. 31 percent of authorities thought that there was no
evidence of contractor innovation. In part this reflects
the authorities' considerable involvement in the
development of designs, and their view that they should
share the credit for some innovations claimed by
contractors.
Innovations noted included energy efficient designs
driven by the transferred risk around energy performance
and, in the schools and further education sectors, flexible
layouts, and innovative location of and access to community
facilities. Also in the schools sector, one contractor
delivered a new building in place of the refurbished
building proposed by the authority, while remaining within
the affordability budget.
There was little evidence of innovation in building
techniques in accommodation projects. By contrast, in the
water sector there was considerable evidence of technical
innovation with the introduction of techniques new to
Scotland (for example "bendy channel" grit removal, Cambi
sludge treatment and tertiary
UV treatment) and of rigorous options
analysis resulting in redesign of the authority's proposed
systems - in some cases combining treatment plants, in
others carrying out more treatment locally.
4.2. Construction timescales
The proportion of projects delivered on time shows
an improvement over historical experience in
traditional procurement but there were more delays than
reported in the
NAO's 2003 study.
In the
NAO's 2003 study, '
PFI: Construction Performance', 76
percent of the projects surveyed were ready to use on time
or early and 92 percent were delivered within 2 months of
the target date, an improvement over historical experience
12. In our survey, of the 40 projects where data for
the construction phase was provided, 28 (70 percent) were
delivered on time or early and a further 3 were delayed by
2 months or less.
Timely construction completion is particularly important
in the schools sector, where the target date is generally
arranged to ensure that the new asset is ready at the start
of a school term. In the case of 7 of the 9 schools
PPP projects that responded to the
survey, all of the assets were available for use on time.
In relation to the 2 projects where there was a delay, one
was due to the authority's change of requirements. In the
case of the other project, half of the schools in the
portfolio had been completed by the required date and the
remainder were completed within three months.
Of the 9 waste water projects included in the survey, 3
were delivered late and another, although delivered on
time, did not initially meet its performance test
requirements. Some of the longest delays (7 and 8 months)
were observed in this sector. In the majority of cases the
facilities were working to some extent during the delay
period.
In all 12 cases where there was a delay in the asset
being available for use (other than where the delay was due
to an authority change of requirements), the authority was
able to delay payment of the whole or part of the unitary
charge and, in a few cases, claim compensation for the
delay. (In the water sector bonuses were paid in 3 cases
for early completion.)
Although, under
PPP, the public sector does not normally
pay for assets until they are ready for use, it is still
important that agreed delivery dates are met, both to fit
in with any plans for transition from previous assets, and
so that the economic benefits of the project are realised
as envisaged in the business case. While the results of our
survey demonstrate an improvement over conventional
procurement, it is disappointing that the proportion of
projects delivered on time in Scotland is lower than
reported in the
NAO's study. Despite this, and although
around a third of projects were late, the contract
incentives to deliver on time do appear to be working, with
the mean delay only 5 months, and the maximum delay 11
months, which compares favourably with overruns in
traditionally procured projects.
It is not clear though that these improvements are
unique to
PPP projects, and it might be possible
to achieve similar results using Design and Build
contracts, if upfront specifications were developed to the
same level as in
PPP projects and an element of the
payment were linked to timely completion. There might also
be greater scope to include liquidated damages for delays,
which are standard in Design and Build contracts, in
PPP projects.
Resolution of minor snagging caused frustration for
authorities.
In interviews, several respondents discussed
frustrations over minor snagging, which had not prevented
the asset being deemed available for use but nevertheless
needed to be resolved. If minor snags had not been resolved
before the
SPV's construction contractor had left
the site, then authorities found that it was difficult and
time-consuming to get them remedied. We understand that
there are contractual remedies, in current contracts at
least, which (i) allow the authority to serve a notice on
the contractor requiring the works to be carried out; and
(ii) after a certain period, if the works are still
outstanding, enable the authority to make payment
deductions and / or carry out the works itself and claim
costs from the contractor. Nevertheless, given the number
of authorities that raised this issue, we think that it
would be useful to review whether the latest contracts
provide appropriate incentives to resolve snagging
issues.
Recommendation: Further research should be
carried out to review whether the contractual remedies
relating to snagging provide appropriate incentives to
contractors to resolve these issues.
4.3. Construction related price
changes
PPP projects delivered increased
price certainty compared to traditional procurement but
there were more price movements than reported in the
NAO's 2003 study.
Of the 37 projects for which data was available, 18 (49
percent) had experienced no price change for any reason
during the construction phase of the project. This
represents an improvement over historical performance
13 with conventional procurement but price certainty
had reduced compared with the 2003
NAO survey '
PFI: Construction Performance' which
found no price change in 70 percent of projects.
Figure 11 and
Figure 12 below show the reasons for the changes
and who initiated them.
Figure 11: Changes to the contract price during
construction
Reason for price change | Number of price changes |
|---|
New facilities | 6 |
|---|
Extensions or enhancements to
facilities | 15 |
|---|
Change in function | 5 |
|---|
Refurbishment work | 1 |
|---|
Design change | 15 |
|---|
Changes were only initiated by the contractor in 2
cases. Most of the time the Authority led the change or it
was jointly agreed.
Figure 12: Who led the change?
Price change led by… | Number of price changes |
|---|
Authority | 13 |
|---|
Contractor | 2 |
|---|
Both Authority and
Contractor | 7 |
|---|
Note that several respondents stated that there was
a price change but did not state who led the
change
PPP aims to give the public sector price
certainty in construction projects. Although the survey
results indicated that there were changes in around half
the projects, interviewees commented that the
PPP contract encouraged minimisation of
changes, and forced better up-front specification. Some
authorities expressed concern that changes were being
pushed out into the operating period, even where it might
have been more efficient to amend the construction
programme. That this is happening was confirmed in
interviews with contractors who stated that, given the
penalties for late completion, they resisted any changes
that would delay the completion date. Although contracts
contain mechanisms that allow the contractor to reclaim the
additional bank interest incurred by late completion (and
hence delayed payments for services) due to an authority
initiated change, contractors are very keen to avoid any
delay to the completion date. Authorities commented that
the formal processes in the contract for agreeing changes
enabled the contractor to slow down change requests.
Interviewees also noted that changes were typically paid
for using one-off payments rather than changes to the
unitary charge because of the complexity of agreeing a
change to the project financial model.
Where authorities had successfully requested changes
during the construction period, they raised some concerns
about their ability to demonstrate value for money, given
the lack of competition for the additional works (
see section 6.2 on value for
money).
Recommendation: Authorities should
continue to focus on developing the up-front specification
to minimise any changes during the construction period,
particularly in the light of concerns about value for
money. However there may be a case for streamlining the
change procedure for relatively minor changes.
4.4. Construction cost risk transfer
Construction cost risk was effectively transferred
to the private sector.
Very few authorities knew the actual construction costs
incurred by contractors; only 3 authorities were aware that
the contractor's actual costs had been higher than
envisaged at financial close. 8 out of the 13 contractors
who were prepared to disclose information about outturn
costs stated that costs had increased. The most common
reasons for construction cost increases were unforeseen
ground conditions, environmental issues, weather, public
interventions and supply difficulties. Note that these
risks were not always transferred under other forms of
procurement.
The
PPP process is designed to transfer
almost all construction cost risk to the private sector and
avoid increases to the construction price after contract
signature. This was perceived to be a weak area for
previous procurement methods. While the survey results
indicate that very little open book accounting is taking
place
14, they provide good evidence that the construction
cost risk transfer envisaged in the contract is
working.
4.5 Impact of
PPP procurement on construction
timescales and budget
PPP provides strong incentives to
deliver the asset on time and to budget.
Respondents were asked for their views on the impact of
PPP on construction timescales and
budget. The most frequently repeated comment was that
PPP projects are more likely to be
completed on time and within budget, because of the
powerful incentive of withholding payments until completion
of the asset.
Several respondents commented that the total time for
procurement and construction was longer for
PPP projects.
Several respondents said that they thought the bid price
for
PPP projects tended to be higher than
for non-
PPP projects, but that this reflected
the risks transferred. Some commented that the total
outturn price of
PPP projects was lower or the same as
non-
PPP projects (taking into account budget
overruns on traditionally procured projects).
It was noted that the pressure to meet the agreed
timetable in
PPP projects led to reduced flexibility
to changes during the construction period.
« Previous | Contents | Next »