« Previous | Contents | Next »
Listen
3. Procurement
3.1. Procurement timescales
The mean time taken to procure
PPP projects was 28 months, which is
generally perceived to be slower than non-
PPP procurement.
The mean time taken to procure the
PPP projects included in the survey
(i.e. the time from issue of the
OJEU notice to financial close) was 28
months. Most authorities thought that
PPP procurement was slower than
alternative methods. Most contractors also perceived
PPP procurement to be slower, although
20 percent of contractors believed that there was no
difference from conventional procurement. The differing
responses from authorities and contractors may reflect the
fact that authorities commit a considerable amount of time
to developing
PPP projects in the period after issuing
the
OJEU notice, but before detailed bids
are invited from contractors.
Figure 3: Are
PPP projects procured more quickly
or more slowly than non-
PPP projects?

The length of time taken to develop a project from the
initial strategic planning stage through to the agreement
of a contract with the private sector affects the speed
with which new public services are delivered, and the
short-term costs accruing to both the public and private
sectors.
One of the main benefits of
PPP has been the discipline imposed on
the public sector to specify its requirements clearly and
up-front. Detailed design work carried out during the
procurement phase of
PPP projects often would have been
included in the construction phase of conventionally
procured projects. Although a short procurement process is
desirable, bringing design work forward at the expense of
increasing the procurement period is not necessarily a bad
thing.
The involvement of lenders in
PPP contracts generally results in more
due diligence being carried out during the procurement
phase than is the case for conventional procurement, and
this increases the time taken. Similarly, longer contract
lengths for
PPP projects (typically 20 to 30 years)
mean that both public and private sectors invest more time
up-front to ensure that the contract meets their
requirements and allocates risks appropriately.
3.2. Procurement costs
The procurement process is expensive, and
represents a greater burden for smaller projects.
The median cost incurred by authorities for external
advisers was £750,000. Contractors reported much higher
median costs of £2,800,000 (although only six contractors
provided information).
The average cost of authorities' advisers as a
percentage of capital cost was 3 percent, and the range was
1 percent to 9 percent. Higher percentages generally
related to the smaller projects, reflecting the fact that
costs do not vary much with project size. In interviews
contractors commented that it was difficult to justify bid
costs for projects with capital value below £40 to 50
million. In the schools sector, bundling projects has
successfully reduced authority costs as a percentage of
capital investment; average authority costs in this sector
were 2 percent of capital costs.
Where bundling projects is possible, this can reduce the
relative size of the authorities' costs. It would be worth
considering whether more bundling of projects is possible,
in particular in the health sector, if further small
capital value projects are proposed.
Contractor costs are ultimately passed on to the public
sector. Competitive pressure should drive these costs down,
within the constraints of the bid requirements. Costs might
be reduced further through the use of exemplar designs or
standard contracts, by postponing due diligence
requirements until later in the bidding process and, as
discussed above, by bundling projects. These options must
be weighed against their impact on value for money.
3.3. Competition
PPP contracts typically last for thirty
years, with relatively limited opportunities after contract
signature to test or re-tender the total price paid by the
authority over the life of the contract (
see Section 6.3 on
benchmarking). It is therefore vital for the authority
to satisfy itself that it has achieved the best possible
value for money at the point it lets the contract. We
looked first at the number of bidders for each project,
which provides a good indication of the authority's success
in creating effective competition (Section 3.3.1). We also
looked at price movements in the period after the authority
had chosen its preferred bidder (Section 3.3.2). During the
preferred bidder stage, although the authority generally
has the right to re-introduce the second placed bidder, it
rarely exercises that right. Competitive tension is greatly
reduced, and it is important to ensure that price movements
are closely monitored.
3.3.1. Number of bidders
Authorities ran effective competitions for the
projects surveyed. Although the level of competition
has reduced over time, it is still sufficient to
deliver value for money.
On average nine pre-qualification submissions were
received per project, indicating strong competition. The
minimum number of bids received was two, and this only
occurred in one case. Pre-qualification for the projects in
this survey, all of which are now operational, took place
between 1995 and 2000
9. There is no evidence of a downward trend in the
number of bids per project received during that period.
Fewer pre-qualification submissions were received in the
health sector than in other sectors, possibly reflecting
the relatively low capital values of many of the
projects.
When considering the current situation, authorities and
contractors alike said that they believed that the number
of pre-qualification bids had fallen in recent years (see
Figure 4 below). Authorities had some concerns
that this meant that there was now limited competition and
three respondents thought that competition was insufficient
to obtain value for money. Contractors noted that the
reduced number of bidders was partly due to the scale of
recent projects, with smaller contractors unable to compete
and the field reduced to the serious contenders.
Figure 4: Do you believe that there is currently a
healthy level of competition for
PPP contracts in your sector?

In our view, provided that the number of
pre-qualification submissions from consortia that
demonstrate the technical, financial and commercial
capacity to complete the project does not fall below two to
three genuinely competing bidders, there remains sufficient
competition to demonstrate value for money. Where there is
evidence of very little competition, at worst a sole
bidder, or two bidders but a suspicion that one has agreed
to drop out late in the game, then a lot more attention
must be given to pre-bid value for money. The greater
self-selection of bidders can benefit authorities as it
reduces evaluation costs incurred reviewing non-credible
submissions.
Lack of co-ordination between projects inhibits
competition.
In interviews, contractors commented on the lack of
co-ordination between projects. Given the resources needed
to bid, they said that they chose carefully which projects
to go for, and then expected to bid aggressively for those
projects. This approach by contractors should ensure that
authorities receive good value for money, although it is
important to ensure that there is no collusion between
contractors over which projects each will bid for (there is
no evidence or suggestion that this has happened to
date).
The Scottish Executive already provides information on
its website about the
PPP project pipeline. But Scottish
PPP projects compete with
PPP projects around Europe, as well as
with other construction work, in particular regeneration
work taking place in Scotland. In addition to capacity
constraints in the construction industry, there may be
constraints on the number of
PPP projects that the
SPV management teams within construction
and maintenance companies can take on. In interviews,
authorities noted that, as the
SPV shareholders' portfolio of projects
grew, they were committing less time to the earliest
projects. It was not clear from our discussions the extent
to which constraints on bidding and construction capacity
were physical constraints, or the result of relatively low
capitalisation and therefore inability of companies to take
on more risk.
Recommendation: The Scottish Executive /
Departments / Local Authorities should continue to monitor
the number of pre-qualification submissions received from
credible consortia for new procurements to satisfy itself
that competitive tension is being achieved.
There is perceived to be less competition for
PPP projects than for non-
PPP projects.
73 per cent of authorities thought that there was less
or much less competition for
PPP projects than for non-
PPP projects (see
Figure 5 below). This is probably partly explained
by the fact that non-
PPP projects tend to be smaller and
therefore there are more contractors who have the capacity
to take them on. But the general perception was shared by a
health board with recent experience of procuring new
large-scale assets under Design and Build contracts rather
than
PPP contracts; they believed that
construction companies were more eager to bid for their
work than for comparable
PPP contracts coming to market at the
same time.
Figure 5: How do you think competition for
PPP contracts currently compares
with competition for non-
PPP contracts?

3.3.2. Price movements between selection of
preferred bidder and financial close
On more than half of projects, the price changed at
the preferred bidder stage because of a change to the
design or service specification.
Based on responses from authorities and contractors, the
price moved on 69 percent of projects (24 projects out of
35 that responded), with a total of 66 individual price
changes reported.
Figure 6 and
Figure 7 below show the reasons for the changes
and who initiated them. In the majority of cases the design
changed and there was also a change to the services
specification. Other reasons for price changes included
correction of errors in the financial model, cost increases
following funder due diligence, cost increases to
compensate for delays in reaching financial close and the
impact of negotiation by the authority.
Figure 6: Changes to the contract price
Reason for price change | Number of price changes |
|---|
Interest rate change | 15 |
|---|
Design specification change | 20 |
|---|
Services specification
change | 18 |
|---|
Other changes | 13 |
|---|
Changes were only initiated by the contractor in 4
cases. Most of the time the authority led the change or it
was jointly agreed.
Figure 7: Who led the change?
Price change led by… | Number of price changes |
|---|
Authority | 14 |
|---|
Contractor | 4 |
|---|
Both Authority and
Contractor | 32 |
|---|
Note that several respondents stated that there was
a price change but did not state who led the
change
The
PPP procurement process aims to limit
movements in the contract price during the period between
selection of a preferred bidder and financial close. This
is to ensure that value for money achieved during the
competitive phase of the project is not eroded. Typically
the interest rate risk during this period is retained by
the public sector since it would not be cost effective to
ask the private sector to take this non-controllable risk,
and the price is adjusted to reflect any changes according
to a pre-agreed mechanism
10. Significant price changes at this stage which are
triggered by a change to the design or to the services
specification need to be minimised, and evaluated carefully
to ensure that value for money is achieved in these
non-competed additions to the original specification.
The scale of price changes appears significant and
should be monitored.
Figure 8 below shows the price movements recorded
at preferred bidder stage as a percentage of contract
NPV. The price increased by more than 5
percent in 11 of the 24 projects where the size of the
change was reported.
Figure 8: Percentage change to the
NPV of the contract

The scale of the price movements at preferred bidder
stage could raise concerns about value for money, since the
only competitive pressure at this stage of procurement is
the relatively weak threat that the second placed bidder
could be re-introduced into the competition (or, perhaps,
the threat of cancellation of the procurement process).
Note, though, that we are not able to identify separately
the percentage change that related to interest rate risk
taken by the authority and it is quite possible that an
increase in interest rates, of say 1 percent, could
increase the
NPV by more than 5 percent
11.
It is certainly better to agree changes at this stage
rather than post financial close. But authorities should
aim to introduce any design or service changes before
inviting best and final offers, and the Scottish Executive
should monitor the scale of changes at preferred bidder
stage. As the use of standard contracts increases, and
authorities' experience in developing designs and service
specifications grows, we would expect to see the size of
price changes made after selection of a preferred bidder
decreasing, other than those relating to changes in the
interest rate.
Recommendation: The Scottish Executive
should continue to monitor the size of and reasons for
price changes that happen during the procurement
period.
« Previous | Contents | Next »