« Previous | Contents | Next »
Listen
CHAPTER 4: HOW TO ENSURE YOU COMPLY WITH THE NEW
REGULATIONS
As noted in the previous chapters, all waste
incineration installations must be subject to a permit by
the compliance dates set out in Chapter 3. The permit must
include conditions that give effect to the technical
requirements set out in Chapter 5 by that date.
In order to ensure that these requirements are
fulfilled, the Regulations set out a process that requires
operators of waste incineration installations to make an
application for a permit or a variation to their existing
authorisation. This chapter sets out when and how operators
of waste incineration installations should make such an
application.
SEPA has been directed by the Scottish
Executive to include conditions in some existing permits
and authorisations requiring operators to make an
application in line with the dates set out in the
regulations. You may have received a variation notice from
SEPA to add such a condition to your
current authorisation or permit.
The date when an application must be made to
SEPA depends on whether the plant is new
or existing for the purposes of the Regulations. For
existing installations, it also depends on how the plant is
regulated at present.
4.1 New waste incineration
installations
Plants that do not meet the definition of 'existing
waste incineration installation' (see paragraph 3.3) needed
to comply with the requirements of the Regulations from 1
April 2003 (when the Regulations came into force).
Operators of new waste incineration installations put into
operation on or after 1 April 2003 must hold a
PPC permit that meets the requirements
of the regulations before putting the plant into
operation.
However, the Regulations applied to new plant from 28
December 2002. The Regulations provided transitional
arrangements for new installations that were put into
operation after 28 December 2002 but before 1 April 2003.
In these cases the operator of the installation was
required to apply for a variation to their permit by 30
September 2003. This allowed a period of six months after
the Regulations came into force. If an application was made
within this transitional time period then the operator was
permitted to carry on operating the installation in
compliance with the existing permit until the varied permit
superseded it.
4.2 Existing waste incineration
installations
The date when operators of existing waste incineration
installations should apply for a
PPC permit depends on the type of plant
and how it is permitted at present. The three main
scenarios are set out below.
Scenario 1: Existing waste incineration
installations that fall within Schedule 1, Part 1,
Section 5.1, Part A paragraphs (a), (b), (c), (d) and
(e) of the Regulations
Operators of plants falling within these parts of
Section 5.1 are required to make a
PPC application during the following
period (but see also section 4.8):
- 1 January to 31 March 2005.
This represents an adjustment of the original
PPC transitional timetable in order to
ensure that all plants are subject to a permit by 28
December 2005.
Operators of plants falling within these parts of
Section 5.1 will need to include the additional information
set out in Section 4.5 of this guidance when they make
their application for a
PPC permit. Where a permit is granted by
SEPA, it will include conditions giving
effect to the technical requirements set out in Chapter
5.
Operators of plants falling under paragraphs (f) and (g)
of Part A of Section 5.1 are not waste incineration
installations within the meaning of the Regulations.
Operators of such plants are required to make an
application for a
PPC permit in line with the original
PPC transitional timetable of 1 June to
31 August 2005. Applications for permits for these
installations do not need to include the information set
out in Section 4.5.
Scenario 2: Existing waste incineration
installations which presently have an authorisation
under
EPA (except for one mentioned in
Section 5.1 of Part 1 of Schedule 1 to the
PPC Regulations)
and whose relevant period to apply for a
PPC permit is not until
after 31 March 2005
Not all co-incineration plants fall under Section 5.1 of
Part 1 of Schedule 1 to the
PPC Regulations. A number will currently
be regulated under
EPA and will transfer to
PPC as part of a Part A installation
under
other sections of Part 1 of Schedule 1.
Existing waste incineration installations regulated
under
EPA which are not required to apply for
a
PPC permit until after 31 March 2005
have the following options for complying with the
requirements of the Regulations (but see also section
4.8):
- Applying for a variation of their
EPA authorisation between 1 January
and 31 March 2005 to include additional conditions that
comply with the Regulations, followed by an application
for a
PPC permit in line with the
timetable set out in the
PPC Regulations relevant to the
installation; or
- Applying for a
PPC permit that is fully compliant
with the Regulations between 1 January and 31 March
2005.
The information which should be included in applications
under either option must be consistent with the
requirements set out in Section 4.5 of this guidance. The
relevant permit or variation will include conditions to
give effect to the technical requirements of Chapter 5.
Note that any co-incineration plant which is newly
brought into
PPC, or which moves from Part B to Part
A as a result of the Regulations, will fall within Section
5.1 and must apply in line with scenario 1 above. The
allowance for plants to comply with the Regulations by way
of making an application for a variation to an
authorisation under
EPA applies only to those
co-incineration plant currently regulated under
EPA for which the installation is not
due to phase into
PPC until after March 2005.
Scenario 3: Operators of:
- existing waste incineration installations which
presently have an authorisation under
EPAand have a relevant period such that they are
subject to a
PPC permit on 31 December 2004;
or
- existing waste incineration installations that
already have a
PPC permit
Existing waste incineration installations that will hold
a
PPC permit on 31 December 2004 are
required by the Regulations to apply for a variation of the
conditions of that permit, between 1 January and 31 March
2005, in order to ensure compliance with the Regulations
(but see also section 4.8).
Plants that fall within this description are as
follows:
- existing waste incineration installations that were
issued with a
PPC permit from commencement of the
activity; or
- existing waste incineration installations which
presently have an authorisation under
EPA and have a relevant period such
that they are subject to a
PPC permit on
31 December 2004.
For operators falling within option b) above, the
Regulations allow for an application to be made, with the
consent of
SEPA, before 1 January 2005. This gives
operators the option of applying for the
PPC permit and having conditions that
are compliant with the Waste Incineration Directive
included at the same time, hence preventing duplication.
SEPA will allow early application in
order to avoid the need for duplication by operators.
Operators whose relevant period is towards the end of
2004, and therefore may not have a permit on 31 December
2004, are strongly advised to consider their application
options to ensure they do not end up needing to submit
duplicate applications.
The information which should be included in applications
under either option must be consistent with the
requirements set out in Section 4.5 of this guidance. The
relevant permit or variation will include conditions to
give effect to the technical requirements of Chapter 5.
4.3 Substantial change
The Regulations expand the definition of 'substantial
change in operation' within the
PPC Regulations in relation to waste
incineration installations. As well as the current
definition any existing incineration or co-incineration
plant that burns hazardous waste for the first time will be
classed as having undergone a substantial change in
operation.
4.4 Provision for existing waste incineration
installations to comply with the Regulations
early.
In addition to scenario 3 above there may be a few cases
where operators wish to comply with the Regulations early,
by combining their application for a permit to comply with
the Regulations with another application that they are
making for operational reasons (e.g. an application for a
variation of a permit). Operators must secure the agreement
of
SEPA before making such an application.
SEPA may then agree to include
conditions that meet the requirements of the regulations
ahead of the time at which they would otherwise need to be
included in the permit.
4.5 Content of applications
The information that must be included in a standard
application under
EPA and
PPC is well defined in the relevant
legislation. The Regulations require additional information
to be included in applications for permits or variations
related to waste incineration installations. Section 4.2
sets out when the additional information must be
provided.
The additional requirements for applications are set out
in paragraph 1B of Part 1 of Schedule 4 to the
PPC Regulations (inserted by the new
Regulations). Part 1 of Schedule 4 (applications for
PPC permits) and Part 1 of Schedule 7
(variation of conditions) have been adjusted to refer to
these requirements. The information to be included in
applications for
EPA variations should be consistent with
these requirements.
The following summarises the additional information
required as part of the application:
Design & Operation
- Demonstration that the plant is designed equipped
and operated to meet the requirements of the
Regulations taking account of the categories of waste
to be incinerated;
- Plant capacity, categories of waste (according to
the European Waste catalogue) to be treated in the
plant including their quantities, systems for
receiving, storing and handling of waste on site;
- Information on temperatures and residence time
(including measurement and validation methods), waste
feed interlock to stop waste feed when the temperatures
are below the permitted levels, provision of auxiliary
burners including the description of proposed auxiliary
fuel;
- In the case of a request for derogation from the
temperature or residence time requirements,
justification for the proposal and its effect on the
quality and quantity of residues produced and the
emissions into air of
TOC and
CO;
- In the case of abnormal operating condition, how
will the dust emissions be controlled to below 150 mg/m
3;
- Information on the predicted emissions to air and
water and show how the Directive's emission limits will
be complied with at all times (e.g. by showing that
there are enough operating margins between the
predicted emissions and the
ELVs);
- Where an applicant is looking for a time-limited
derogation from NO
x limits (as allowed by the regulations), a
BAT justification for these higher
limits must be provided;
- Applications will need to include details of stack
height calculations, dispersion calculations and the
environmental impact of the emissions from the plant to
demonstrate that human health and the environment will
be protected;
- The applicants for co-incinerator plants will need
to provide the information on the process and their
conventional fuels and emission predictions or measured
emission values; and
- Information on methods and handling of waste waters
on the site shall be provided to particularly show that
storage areas have been designed in a way that will
prevent the unauthorised and accidental releases of any
polluting substances into air, soil, surface water and
ground water.
Heat recovery
- Information of the use of heat generated from the
process - for example through combined heat and power,
generation of process steam or district heating
including proposals for future improvements in heat
utilisation.
Residues
- The quality (total organic carbon content and/or
loss on ignition) and quantity of residues produced,
handling and storage of these residues, proposals for
minimising/recycling and disposal, and information on
the chemical constituents of the residues.
Monitoring
- Applicants will need to provide the details of the
monitoring techniques they will employ to meet the
requirements of the regulations. In particular, they
will need to confirm that they will apply the
CEN standards where available and,
when such standards are not available, they will use
ISO or national or international
standards (subject to the agreement of
SEPA); and
- Details of the monitoring points and the monitoring
equipment to be used, especially the continuous
monitors (
CEMs). In the case of a plant
already in operation, the applicant will need to
confirm that all
CEMs will have been fully
commissioned and operational by the date on which the
regulations apply (e.g. 28 December 2005 for existing
plants). They will also need to show that the
CEMs have been calibrated to
CEN standards by the above
date.
In the event that the application does not contain the
required information,
SEPA may reject the application as not
duly made. If clarification is needed
SEPA may serve notices requiring
additional information to be provided before determining
the application If a duly made application has not been
lodged by the due date,, then continued operation of an
existing plant is not covered by the existing authorisation
and
SEPA may initiate enforcement action for
operating an installation without a permit.
4.6 How to make an application
Applications need to be made on the appropriate
application form and accompanied by the relevant
application fee.
Application forms, level of fees and further advice can
be obtained from:
- The local
SEPA office (see telephone directory
for contact details); or
- SEPA's website at
www.sepa.org.uk
4.7 Time scale for compliance
Existing incineration and co-incineration plants that
are subject to the requirements of the Regulations must be
compliant by 28 December 2005. Operators must submit a duly
made application to
SEPA between 1 January and 31 March
2005. Applicants must recognise that time is needed by
SEPA to determine applications and to
discuss upgrade requirements with applicants, followed by
time for the upgrading to be carried out before 28 December
2005. No upgrade programme is allowed after December 2005.
It is recommended that applicants approach
SEPA allowing plenty of
time.
4.8 Operators planning to stop incineration
before 28 December 2005
It is recognised there may be some operators of existing
waste incineration installations who plan to stop burning
waste before 28 December 2005. They might include, for
example, small waste oil burners in garages and roadstone
coaters. In these cases, it is accepted that operators will
not wish to make an application for a
WID-compliant permit during the
application period 1 January to 31 March 2005. The Scottish
Executive has, therefore, amended the
PPC Regulations to introduce a "presumed
notification" system to address this situation. This
amendment, which came into force on 1 April 2005, was
introduced through the Pollution Prevention and Control
(Scotland) Amendment Regulations 2005 (
SSI 2005 No 101). It provides that
operators of existing waste incineration installations who
do not apply for a
WID-compliant permit or authorisation by
31 March 2005 shall, subject to certain conditions, be
presumed to have made notification to
SEPA of their intention to stop
incinerating waste in that installation before 28 December
2005.
« Previous | Contents | Next »