« Previous | Contents | Next »
Listen
Natural Flood Storage and Extreme Flood
Events Final Report
6 CASE STUDY 2 - SOUTH ESK (ANGUS)
6.1 Background
The South Esk catchment area draining through Brechin is
approximately 500km
2 in size. The catchment is almost entirely
rural, with steep topography limiting the amount of
floodplain area. There are very few reservoirs that
regulate the river flow. Only 0.6% of the catchment area is
built-up. The dominant land covers are moorland (about
44%), arable/horticulture (about 22%) which is mostly
located very close to Brechin and rough grass (about
15%).
Brechin suffered serious flooding in 2002. Since then
Angus Council has been undertaking a detailed appraisal of
flood alleviation options, including engineered flood
storage, a flood relief channel, and demountable/hard flood
defences. The engineered storage options investigated were
an on-line reservoir just upstream of Brechin (at a cost in
excess of £8 million) and two storage areas further
upstream - one at Gella Bridge on Prosen Water about 27km
upstream of Brechin and one at Gella Bridge on the South
Esk about 35km upstream of Brechin (also at a cost in
excess of £8 million).
The modelling work on the South Esk (HR Wallingford,
2004) concluded that the use of on-line or off-line storage
upstream of Gella Bridge and Prosen Bridge to reduce flood
levels at Brechin was not a practicable flood mitigation
measure. Two of the reasons given for this were that
significant flood events could be generated by a large
rainfall event over the lower part of the catchment (i.e.,
downstream of Prosen Bridge and Gella Bridge), and due to
the low level nature of the existing embankments on the
main drainage network then most of the floodplain was
already being utilised during extreme flood events.
6.2 Modelling
The first step in the modelling of the South Esk was to
estimate peak flow magnitudes for flooding of the
downstream risk location (Table 6-1).
Table 6-1: South Esk - Flood
flows and return periods
Location | Peak flow (m
3s
-1) | Return period (years) | Notes |
|---|
Brechin | 308 355 | 100 200 | Flows derived from Brechin flood study |
For the South Esk, the recent Brechin flood study
considered storage options to reduce a 200 year event to
the current 100 year downstream flow. We have therefore
modelled these two events only.
An outline of the routing model available for the South
Esk catchment is shown in Figure 6-1. The model is a
Muskingum routing model. Routing parameters were derived
from data given in a report to Angus District Council by HR
Wallingford Ltd., who built a less extensive routing model
as part of a study for the Council (HR Wallingford, 2004).
The routing model was calibrated such that the peak flows
agreed (at least to a close approximation) with the values
given in Table 6-1 for the corresponding return period.
Figure 6-1: South Esk
routing model schematic

The downstream hydrographs for the larger events were
then compared with the peak flow for the 'threshold' event,
and the volume that would have to be stored was calculated
(Table 6-2). These figures can be considered as minimum
required volumes of flood storage (strictly speaking
assumed to exist immediately upstream of the risk
location).
Table 6-2: South Esk -
Storage volumes derived from hydrograph
analysis
| Return period of event
(yrs) |
|---|
Location | Incident event | Target peak flow (or
volume) | Volume (million m
3) |
|---|
Brechin | 100 | 5 (flow) | 3.8 |
The routing model and JFLOW flood inundation model were
run to create flood outlines for the specified return
periods. The area of inundation was calculated and plotted
as a function of distance upstream from the risk location.
We have then calculated the differences between the areas
of the larger (200 year) and smaller (100 year) events to
represent the 'natural' area in which water could be held
back to mitigate the larger event. These results are shown
in Figure 6-2. The steep section of the graph at 5-15km
upstream of the flood risk location may offer good
potential to hold water back during the larger event within
the 'natural' flood extent.
Figure 6-2: South Esk -
Distance-area curves for natural flood extents

We have made a simple assumption that the volume of
storage needed at the downstream flood risk location can be
divided by the modelled flooded area to give a notional
average storage depth (Table 6-3). We have calculated the
required average depth using both the total extent of the
200 year flood (i.e. the flood event we have used in this
study as the extent of the 'natural' floodplain), and also
the marginal extent between the 100 year and 200 year
outlines.
Table 6-3: South Esk -
Notional average depth of natural flooding
Event return period reduction (years) | Volume
(million m
3) | Available extent | Available area
(km
2) | Average depth
(m) |
|---|
100 to 5 | 3.8 | Within 200 year extent | 18 | 0.2 |
100 to 5 | 3.8 | Between 100 and 200 year
extent | 12.1 | 0.3 |
Based on these figures and the distribution of
floodplain extent (as a function of distance upstream from
the flood risk location) we have then calculated the
average depth of water that would be required on the
floodplain to achieve the required volume of storage
(Figure 6-3). The graphs show figures calculated using both
the full extent of the 200 year flood as a potential limit
for storage, and also the marginal area between the 100
year and 200 year extents.
Figure 6-3: South Esk -
Distance-depth curves for natural flood
extents

6.3 Environmental assessment
The South Esk catchment contains a number of sites
designated as being of significant conservation and/or
historical importance. A map showing the Sites of Special
Scientific Interest (SSSIs) and Scheduled Ancient Monuments
(SAMs) within the catchment is given in Figure 6-4. No
SSSIs are located within or near to the modelled 200 year
flood outline, which has been used in this project to
define the 'natural' floodplain. However, there are some
SAMs in or very near the floodplain area between
Inverquharity and Tannadice which would require a more
detailed assessment if enhanced natural flood attenuation
was proposed for this area. If a more extreme flood outline
was modelled then further sites may have to be
considered.
The project team were unable to acquire any datasets on
the man-made assets within the South Esk floodplain.
Clearly these would require due consideration, with all the
appropriate consultations, if any scheme to enhance
floodplain attenuation was to be developed further.
Figure 6-4: South Esk -
SSSIs and Scheduled Ancient Monuments

6.4 Agricultural economic assessment
6.4.1 MDSF-based
The estimated total cost of the 100 year and 200 year
events using the MDSF methodology are shown in Table 6-4.
Unlike the White Cart the areal extent of the 200 year
event is markedly larger than that of the 100 year event,
which cause the overall damage costs to be quite
different
The results indicate that the damage to the arable
(non-cereals) and horticulture land caused by the two
extreme floods completely controls the overall economic
cost. This is due to the very high value of this land cover
in comparison to all the other land covers, including
arable (cereals).
Table 6-4: South Esk -
Economic cost of flooding on agricultural land, based
on MDSF
Flood return period | Cost
(£) |
|---|
100 year | 311,350 |
200 year | 1,166,910 |
To provide a concise summary, the results are also
presented as a function of distance upstream in Figure 6-5.
For the South Esk the higher agricultural damage costs,
associated with arable and horticultural land cover classes
exist in the area 5-20km upstream from Brechin. Beyond 20km
the land cover is dominated by grassland systems.
Figure 6-5: South Esk -
Distance-cost curve for the 200 year natural flood
extent

6.4.2. Single flood compensation payment
based
Table 6-5 provides a summary of the overall costs of
permitting the land to be flooded using the single payment
for all land cover classes (excluding land cover classes 1,
2 and 3).
Table 6-5: South Esk -
Annual compensation costs, based on single
payment
Flood return period | Area inundated
km
2 | Cost (@ £300/ha)
(£) |
|---|
100 year | 6 | 174,900 |
200 year | 18 | 527,700 |
The total catchment figures are typically 50% less than
those derived from the MDSF methods, again indicating the
large impact that the high value arable and horticultural
crops have on the MDSF figures. However, these figures
provide some indication of the magnitude of the longer term
total annual compensation payments that might be required
if the full 'natural' floodplain was to be actively managed
for natural flood attenuation.
« Previous | Contents | Next »