« Previous | Contents | Next »
Listen
ROADS (SCOTLAND) ACT 1984; ACQUISITION
OF LAND (AUTHORISATION PROCEDURE)(SCOTLAND) ACT 1947
M74 SPECIAL ROAD (FULLARTON ROAD TO WEST OF KINGSTON
BRIDGE) ORDERS
REPORT OF PUBLIC LOCAL INQUIRY INTO OBJECTIONS
VOLUME 1 : MAIN REPORT
PART 4 : REPORTER'S FINDINGS AND
CONCLUSIONS
CHAPTER 10 : FINDINGS OF FACT
I make the following findings of fact :
Chapter 1 : Description of scheme and
procedural history
A1 | The description of the proposed motorway
scheme and the setting into which it would be
placed are as described in paragraphs 1.1 - 1.7
above, which are incorporated herein. |
A2 | The history of the project is as described
in paragraphs 1.8 - 1.14 above, which are
incorporated herein. |
A3 | The partnership agreement in respect of the
M74C is as described in paragraph 1.15 above,
which is incorporated herein. |
A4 | The legislative framework underpinning the
Orders is as described in paragraphs 1.16 -
1.19 above, which are incorporated herein. |
A5 | The public consultation undertaken in
respect of the M74C is as described in
paragraph 1.20 above, which is incorporated
herein. |
Chapter 2 : Current policy context
| B1 | The description and summary of
current policy, and associated reasoning, set out
in chapter 2 above is incorporated here. |
B2 | There is a policy commitment to complete the
M74 motorway on the part of the Scottish
Executive; Glasgow City, South Lanarkshire, and
Renfrewshire Councils; and in the statutory
development plan (see below), in order to
complete a perceived gap in the strategic road
network, and to alleviate congestion on the M8,
and in particular on the Kingston Bridge. |
B3 | There is policy support for the proposed
motorway on the part of various economic
development agencies, and to maximise the local
benefits of the new road. |
B4 | There is also widespread policy support for
improvements to public transport, including a
high level commitment by the Scottish Executive
that by the year 2006, 70% of transport
expenditure should be for public transport; and
to improve social, economic, and environmental
conditions for local communities. |
B5 | There is widespread policy support for
sustainable development and sustainable
solutions to problems, including transport and
traffic. |
B6 | There are numerous proposals for new
economic development which would be expected to
benefit from improved accessibility due to the
new road. |
B7 | There is widespread policy support for
promoting social inclusion, and to assist
disadvantaged communities, including those
without the use of cars. |
B8 | There are policies to reduce the amount of
travel in road vehicles (to return to 2001
levels by 2021); to reduce the use of trunk
roads for short local journeys; and to make
better use of road space through
management. |
B9 | There are policies to give higher priority
to walking and cycling. |
B10 | The statutory development plan for the M74
Completion corridor comprises the
Glasgow and the Clyde Valley Joint
Structure Plan (approved 2002), the
Glasgow City Local Plan (adopted 2003)
, and the
Cambuslang/Rutherglen Local Plan
(adopted 2002). Thus there is up to date
structure and local plan coverage for the
area. |
B11 | All 3 plans give explicit support to the M74
Completion project, and the proposed route is
safeguarded in the two local plan Proposals
Maps. The current proposed route for the new
motorway generally conforms to the safeguarded
routes, except for the northward deviation to
avoid the Polmadie rail maintenance
facility |
B12 | All 3 plans promote the improvement of the
local economy and the regeneration and re-use
of brownfield vacant and derelict land. The M74
completion scheme is expected to make an
important contribution to meeting these
objectives. |
B13 | All 3 plans recognise the importance of
completing the strategic road network, to
improve accessibility, ease congestion on the
M8, and improve local conditions. |
Chapter 3 : Transport : strategic issues and
mode share
C1 | The Scottish Executive, as initiator of
these Orders, has demonstrated its wish that
the M74 Completion be constructed. |
Transport spending and mode share
| C2 | The estimated cost of the M74
Completion project at the time of the public local
inquiry was £375-500 million, plus £4.9 million for
additional works to the existing motorways where
the M74/M8/M77 converge. |
| C3 | The cost of the project would be
increased due to loan charges that may be incurred
on the local authority components of the scheme,
and would be considerably higher (in the order of
£800 million) if a PPP is used. However this would
spread the expenditure over a much longer
period. |
C4 | On the basis of the projected transport
infrastructure spending plans presented to the
inquiry, spending on public transport projects
in the west of Scotland during the period
2004-2008 would represent about 35% of the
total, compared with 65% on road projects. This
would be at variance with the intention that
public transport spending (in Scotland as a
whole) should account for 70% of the total by
the end of 2006. Given the large proportion of
spending that would occur in the west of
Scotland, it would be unrealistic to expect the
70% target to be achieved by a much higher
proportion of public transport spending in the
rest of the country. |
C5 | The position would be worsened if there is a
contractual commitment to the expenditure on
the M74 Completion, but public transport
spending is hindered by spending reductions or
delays in delivering projects. |
C6 | Given the probable global limit on transport
spending in Scotland, this reversed balance of
expenditure between roads and public transport,
or increased cost of the M74 if it becomes a
PPP project with charges spread over a longer
period, would be likely to reduce the scale and
effectiveness of the delivery of attractive
public transport improvements, contrary to
stated intentions. |
C7 | No full multi-modal study of options for the
M74 corridor has been carried out because the
M74 Completion project was accepted as a
commitment that had reached an advanced stage
of planning and was considered to be fully
justified on traffic, road safety, and economic
grounds. |
C8 | The draft Scottish Transport Appraisal
Guidance (STAG : document TRA/C/16) states
(page 4-3, paragraph 4.2.9, third bullet point)
that "Simply retro-fitting existing proposals
or those with a planning history, to objectives
may be tempting but is clearly not the way to
proceed". |
C9 | The M74 Completion project is an existing
proposal with a long planning history. Planning
permission was issued for the new road in 1995,
and was subsequently renewed. The current
scheme generally follows the same alignment,
except at Polmadie. |
C10 | Given the fundamental changes in transport
policies that have emerged since 1995,
especially in respect of the strategies for
public transport and new road building, it is
desirable that the implications of the project
for public transport and other transport
objectives should be considered. The current
inquiry has allowed that to take place. |
C11 | It is a Government commitment to strive to
reduce traffic levels in Scotland, so that they
are brought back to 2001 levels (in terms of
vehicle/kilometres) by the year 2021. |
C12 | According to the traffic predictions
presented to the inquiry, the M74 Completion
project would be likely to result in 1.5-2.5%
additional vehicle trips in the Glasgow area,
and it is estimated that there would be
approximately 5% additional vehicle kilometres
due to these additional vehicle trips. |
C13 | Although traffic levels within Glasgow
appear to be stable, vehicle flows across the
city boundary cordon are increasing at around
2.3%, due largely to flows on the
motorways. |
C14 | Facilitating greater use of the motorway
network for vehicle trips by increasing
motorway capacity would be likely to continue
and perhaps increase this trend. This would be
at variance with the policy objective to reduce
overall traffic levels, and would require even
greater efforts to reduce non motorway vehicle
trips to offset this growth if the overall
target is to be achieved. |
C15 | There are no plans to introduce road user
charging in Glasgow, but the City Council keeps
the matter under review. Such a scheme could
have the potential reduce traffic flows into
the city, including traffic leaving the M74 off
ramps, and the other radial routes that it
would relieve. |
C16 | The introduction of tolls for the use of
motorways and trunk roads would require new
primary legislation. |
Traffic congestion
C17 | The existing road network in the vicinity of
Glasgow city centre suffers from severe traffic
congestion during peak periods, notably on the
M8 west of the city centre (junctions 18-19);
on the M8 westbound approach to the Townhead
junction during the morning peak; on the M77
northbound approach to the M8 during the
morning peak; on major radial routes such as
Edinburgh Road, Tollcross Road, Duke Street,
Rutherglen Road, Glasgow Road, and Cambuslang
Road; and on the surface streets leading to
motorway access points. Congestion can last up
to 2-3 hours, and extend for 4-7 kilometres,
even without an incident. |
C18 | The M74C would reduce the loss of time due
to traffic congestion, and road accidents,
within a context of increasing traffic
flows. |
C19 | Traffic predictions for 2010 and 2020, based
on assumed traffic growth, indicate increased
use of the trunk road network for long distance
commuter trips, leading to a generally more
congested network, even with the extra capacity
of the M74C, with much of the road network in
the M74C corridor operating close to capacity
for long periods of the day. |
C20 | The CSTCS (document TRA/A/16 and JAG/7)
recommends various measures to "lock in" the
benefit of road improvements, notably
congestion charging, high occupancy lanes,
trunk road tolls and ramp metering, but
recognises that some of these measures are very
unlikely to be publicly and politically
acceptable. |
C21 | Evidence from continental cities indicates
that effective integrated public transport with
attractive fares can result in much higher
levels of rail usage than Scotland, even where
car ownership levels are higher. |
Benefits on surface streets
C22 | The M74 would reduce traffic levels on
various surface streets (see chapter 4),
notably Rutherglen Main Street, Cambuslang
Road, Dalmarnock Road, and Calder street. These
reductions would be in the order of 9-24%. This
would make these streets more pleasant and
safer for other users and adjacent occupiers,
and would allow more space to be devoted to
pedestrians, cyclists, local deliveries, and
bus lanes. Improvements of this kind are
already taking place, but there would be likely
to be continuing and worsening traffic
congestion on the general traffic road space if
the M74C does not proceed. |
Objectors' alternatives
| C23 | The objectors have put forward
some alternatives to provide improved transport
facilities in place of the M74 Completion, as set
out in paragraphs 3.23-3.24 above. Taken together,
they do not offer a clearly feasible and more
effective approach. Rather they offer a menu of
possibilities that would each require more detailed
investigation to determine the balance of costs and
benefits, and the selection of an appropriate set
of complementary proposals. However there is some
potential for a more focussed approach to tackling
specific problems such as traffic relief on
Rutherglen Main Street; avoiding delays to freight
traffic and buses; and improving public transport
services for the general public, especially those
without access to cars. |
C24 | It is evident that constructing sections of
the new road below ground level would involve
much more expensive engineering work and, in
some places, more disturbance of contaminated
land; but would reduce the impacts of visual
intrusion, noise, and severance. |
Chapter 4 : Traffic implications
| D1 | The description of the methodology
of the traffic prediction studies and results, as
described in paragraphs 4.1-4.19 is incorporated
here. The
Paramics traffic modelling package has
been demonstrated to give effective results through
numerous successful projects that have been carried
through to completion. |
D2 | The work on the CSTCS M74 Corridor, although
more strategic and less focussed on the effects
of the M74C, provides a useful overview of the
wider context of the probable traffic effects.
The description of the findings and conclusions
of the corridor study contained in paragraphs
2.23-2.32 above are incorporated here. |
D3 | The introduction of the M74C scheme would be
likely to ease severe existing peak hour
congestion on the section of the M8 to the west
of Baillieston and to the west of the M80, and
to a lesser extent on the Kingston Bridge. |
D4 | It is not suggested that peak hour
congestion on the city centre section of the M8
(between junctions 15 and 19) would be
eliminated. No traffic predictions are
available for this section, but there are only
2 through lanes in each direction, and queuing
would remain here (and in various other
locations) according to the predictions
contained in CSTCS. |
D5 | The reductions in journey times across and
through Glasgow (in the order of 5-10 minutes
at peak times) would be of benefit to drivers
and businesses. |
D6 | The introduction of the M74C scheme would be
likely to ease severe existing peak hour
congestion on the braided eastbound lanes on
the southwest approach to the Kingston
Bridge. |
D7 | The provision of two motorways serving the
east side of Glasgow would allow traffic to be
diverted between them (by means of the driver
information system) in the event of severe
temporary congestion caused by roadworks,
accident, or vehicle breakdown. |
D8 | These reductions in traffic congestion would
contribute to the Scottish Executive's vision
for 2021 that road traffic on all parts of the
network will be flowing smoothly without
congestion. However congestion would not be
eliminated, and the position would deteriorate
if traffic levels are not curbed, or continuing
traffic growth is not matched by corresponding
increases in capacity. |
D9 | The completion scheme itself would generate
a 1.5-2.5% increase in vehicle trips in the
Glasgow area, leading to an increase of about
5% in vehicle kilometres. |
D10 | The transfer of westbound trips from the
M80/M8 to the M73/M74 would be likely to lead
to congestion on the westbound approach to the
M74C from the east at the Fullarton junction
from the year of opening, becoming
progressively worse due to general traffic
growth. |
D11 | In theory, this queue could be as long as
1800m (about one mile) spread across all 3
lanes. However in practice it would probably be
less, as drivers would seek to avoid it by
changing route (including reverting to the
local street network), changing time, changing
destination, or changing their mode of
travel. |
D12 | Congestion on the eastbound approach to the
M74C from the west would be largely restrained
to the local roads approaching this part of the
motorway system. |
D13 | Due to capacity limitations on the eastern
approach and in the vicinity of the western
approach, the M74C itself would have adequate
capacity to carry the traffic flows that are
predicted to reach it. |
D14 | The section of the M8 between the M74/M8 and
M8/M77 interchanges would require additional
running lanes, to be provided by converting
sections of the hard shoulders. |
D15 | Although some emergency lay-bys may be
provided as a substitute for the hard
shoulders, it is likely that the absence of
hard shoulders would exacerbate congestion
occurring in this location due to accidents,
vehicle breakdowns, and roadworks. |
D16 | Traffic flows would increase on various
streets serving the motorway junctions,
although this would be offset to some extent by
reductions in existing through traffic that has
transferred to the motorway at other locations.
The roads affected by these increases would be
Cambuslang Road (in part), Polmadie Road, and
Aikenhead Road. (For predicted figures, see
paragraph 4.11 above. The environmental
implications of these increases are described
and discussed in other chapters that
follow.) |
D17 | Various streets in the Dumbreck and Kingston
areas would also experience traffic increases.
Those at Kingston are partly due to traffic
using the surface streets to pass between the
M74 and the Kingston Bridge and other Clyde
bridges because of the absence of direct
connections between the M74 and the Kingston
Bridge. About 20-27% of traffic at the western
end of the Completion scheme is predicted to
leave or join the motorway at the Kingston
ramps. |
D18 | Traffic flows would be expected to decrease
on various main roads parallel to the new
motorway route that currently carry heavy
commuter and other traffic, due to the transfer
of trips to the new road. The roads that would
benefit most from these reductions are expected
to be Dalmarnock Road, Cambuslang Road (in
part), Main Street Rutherglen, and Calder
Street (for predicted figures, see paragraph
4.18 above). |
D19 | Where traffic is reduced on main roads, it
would allow more space to be devoted to bus
lanes, cycle lanes, pedestrians, and safer road
crossing facilities, to the benefit of local
residents and other road users. Some of these
improvements are intended with or without the
M74C scheme. |
D20 | There would also be road safety and
environmental benefits where there are traffic
reductions, in terms of noise and air emission
reductions. |
D21 | The completion scheme would be likely to
lead to approximately 760-975 fewer road
accidents across the network during the 20 year
period following the opening of the road. |
D22 | If the M74C is not built, the congestion on
the M80, M8, and M77 is likely to become worse
than if the completion scheme is built, due to
continuing traffic growth, but the congestion
on the westbound approach to the M74 Fullarton
junction would be less, as traffic would remain
on the M80/M8 routes towards the city
centre. |
D23 | Congestion and environmental intrusion on
the streets benefiting from reduced traffic if
the completion scheme is built would also
become worse if it is not built, as existing
traffic would be retained, and levels would
increase due to traffic growth. |
D24 | As some of these surface routes already
carry bus lanes, or are intended to have them
irrespective of whether the M74 Completion is
built, traffic congestion would be exacerbated
if the completion scheme is not built, as
general traffic would be confined to a reduced
road area. The probable driver responses to
this increasing congestion would be a
combination of re-routing (possibly along local
rat runs); re-timing; and possibly modal shift
to the improved public transport services. |
D25 | The absence of direct motorway links between
the M74C and the Kingston Bridge means that
traffic wishing to pass between the city
centre/west end and the M74C would have to use
surface streets. This would lead to longer
journeys and more adverse environmental effects
(airborne emissions, noise). |
D26 | The provision of direct motorway links
between the M74 and the Kingston Bridge, as
advocated by Mr George Baillie, would involve
extra construction costs (in the order of
£10-£20 million) and probably some extra land
acquisition. No traffic analysis has been made
available to the inquiry, but it is evident
that direct connections would increase traffic
levels on the Kingston Bridge (compared with
not having direct connections) with a
corresponding reduction of traffic using the
surface network to cross the Clyde on the other
bridges. The direct connections would also be
likely to attract more traffic with origins or
destinations north of the river to use the M74C
in preference to other routes, and probably to
greater use of the M74C for commuter trips. |
Chapter 5 : Physical, environmental, and
community impact
Land take and property demolition
E1 | The general alignment of the new motorway,
land uses along the route, and the land use
context of the wider motorway corridor are
described in paragraphs 1.1-1.7. Much greater
detail is given in the Environmental Statement,
notably technical annexes B, E, and H (Land Use
and Property, Ecology and Nature Conservation,
and Cultural Heritage). The properties directly
affected are as listed at paragraph 5.21
above. |
Green areas, wildlife habitats, and water
quality
E2 | The new motorway would result in a net
reduction of about 9ha of natural and
semi-natural habitats along the route. |
E3 | Existing watercourses crossing the motorway
route are mainly already in culverts, and these
culverts would be extended to pass under the
motorway. |
E4 | Surface run-off from the motorway would pass
to SUDS retention ponds, before discharge to
the River Clyde. |
E5 | Surface run-off from the motorway would be
expected to increase the volume of a 1 in 10
year flood event on the River Clyde by
approximately 1%. |
Community severance
E6 | The new motorway would pass close to
residential communities at Rutherglen, Farme
Cross, north Toryglen, and Govanhill, and
through a mixed use area at Eglinton Street
where there are residential uses. |
E7 | The new motorway would add to community
severance on the section between Cambuslang
Road and Polmadie Road, despite proximity to
the west coast main rail line, as it would
increase the width of the corridor occupied by
transport uses to 200-300m, and due to the
visual obstruction of the motorway embankments,
and community concerns about passing under the
motorway bridges on foot and by bicycle.
Substantial severance is predicted for
pedestrians and cyclists passing through the 3
motorway junctions, and slight/moderate
severance at other places where community
routes would pass below motorway bridges and
viaducts. |
Listed buildings, scheduled monuments, and
archaeological interest
E8 | The motorway would require the demolition of
4 listed buildings, all category B, as
described in paragraph 5.33 above. Other listed
buildings would be retained in close proximity
to the route, as described in paragraph 5.34
above. |
E9 | The overall adverse effects on cultural
heritage sites predicted to result from the
construction of the motorway are as described
in paragraphs 5.35-5.39 above: 3 severe
adverse; 9 major adverse; 49 moderate adverse;
and others minor. |
Visual impact
E10 | The new motorway is predicted to have a
major visual impact on the landscape and
townscape through which it would pass. |
E11 | Although the design philosophy has been to
keep the road as low as possible, some 5500m of
the route (approximately 70% of the total)
would be elevated on embankments, bridges, and
viaducts. |
E12 | Adverse visual impacts predicted for the
opening year are as summarised in paragraph
5.53 above : 11 slight; 13 moderate; and 8
substantial. These would reduce to 10 slight, 5
moderate, and 4 substantial 15 years after
opening, due to landscape planting becoming
effective. |
E13 | The new motorway embankment would be located
about 100m from the residential terraces of the
Farme Cross Conservation Area, with the nearest
point of the motorway carriageway at a distance
of about 130m. |
E14 | The carriageway or slip roads of the new
motorway would be within about 100-150m of
residential areas on the north side of
Rutherglen between Cambuslang Road and Glasgow
Road, a distance of approximately 1500m. This
area is occupied by two storey houses to the
east, and predominantly 4 storey flats in the
centre and west. The facades facing the
motorway route in the vicinity of Rutherglen
town centre are mainly renovated traditional
sandstone tenements. |
E15 | The motorway viaduct passing over Rutherglen
Station would introduce a major engineering
structure above the station platform, cutting
out daylight and bringing traffic noise,
although it would provide shelter from rain and
perhaps a degree of interest for those awaiting
trains. |
Noise
| E16 | Predicted noise impacts from the
new motorway are as summarised in paragraph 5.68
above. These take account of proposed mitigation
measures (mainly noise barriers) which are expected
to reduce noise levels by up to 14 dB. If these
mitigation measures prove to be less effective than
predicted, resulting noise impacts at the receptors
would be correspondingly worse. |
E17 | Adverse noise impacts are predicted to be
moderate at 4 locations, totalling some 180
dwellings; and major at two locations,
totalling some 200 dwellings. |
E18 | The predicted traffic reductions on
Rutherglen Main Street (13-22%) would not
result in a perceptible reduction in traffic
noise, as they are expected to be below 3 dB,
the lower limit of perceptibility. |
E19 | The River Clyde walkway and cycleway near
Auchenshuggle woodland has not been treated as
a receptor in the noise assessment, so no
quantitative figures are available. However
this semi-rural area remote from main roads is
likely to have low or moderate ambient noise
levels, so that the noise of motorway traffic
crossing the new elevated bridge over the river
would be likely to be a very noticeable
intrusion. |
The Oatlands project
Note : Although the Bett Homes objection has
been withdrawn, the objection from the Logan Street
Tenants and Residents Association remains, relating to
the potential visual and noise impact of the elevated
motorway on the Oatlands redevelopment area.
E20 | The Oatlands project is an important
regeneration scheme intended to provide
improved residential conditions in this
area. |
E21 | At Oatlands/Polmadie, the elevated motorway
would be expected to have a slight to moderate
adverse visual impact in the year of opening,
reducing to slight adverse/slight beneficial
after 15 years. |
E22 | In assessing the noise impacts of the
motorway in the Oatlands area, it is
appropriate to take account of the re-aligned
Rutherglen Road in the environmental
assessment, as it is an essential and integral
element of the Oatlands redevelopment that
would affect the local environment, even if the
M74 Completion is not built. |
E23 | The realigned Rutherglen Road would be an
important source of noise affecting the new
dwellings along the southern perimeter of the
new development. |
E24 | The motorway is predicted to add to ambient
traffic noise in the Oatlands area, to the
extent described in paragraphs 5.76-5.79
above. |
E25 | Although not strictly necessary for noise
mitigation purposes, the addition of a noise
barrier along the north side of the motorway in
the Oatlands section, including the motorway
bridge over Polmadie Road, and possibly
including the slip roads on the north side of
the Polmadie Road motorway junction, would have
a beneficial effect on residents of the new
houses, by reducing ambient levels within the
development and providing subjective relief,
especially in the early years before
intervening planting reaches maturity. |
E26 | The noise assessment for Oatlands carried
out on behalf of the TRA conforms to national
guidance on the assessment of traffic noise
from new roads. However it does not provide any
quantitative assessment of night time noise
levels, as recommended in PAN56. |
E27 | Placing the Polmadie section of the motorway
at ground level, with Polmadie Road crossing
over rather than under the motorway, would
incur extra engineering costs due to the
additional work required to cope with ground
contamination, drainage/flooding, and
underground services. |
Local air pollution
| E28 | Overall levels of air pollution
are expected to fall, thanks to improvements in
engine technology. |
E29 | The new road would be expected to increase
local air pollution levels compared with the
future situation without the new road, with the
highest concentrations being found at the
western end of the route. |
E30 | The net result of these changes would not
exceed the recommended standard of 40µg m-3,
and this is not primarily because of the new
motorway but the influence of the higher
concentrations in the city centre and the M8
traffic. These are not locations where the
public will experience long term exposure. |
Disruption during construction
E31 | There would be disruption of road traffic,
including motorway traffic, where M74
construction activities would require road
closures and diversions. The worst affected
locations are those where construction work
will last for longer periods (up to 6 months)
or affect roads carrying heavy traffic flows
and subject to peak hour congestion. |
E32 | Construction traffic is predicted to require
approximately 213,000 HGV loads, causing
noticeable increases on some routes, and some
loss of amenity where sensitive receptors are
close to routes that would carry increased
flows for long periods, eg Cambuslang Road
where there would be around 131 additional HGV
movements per day for nearly a year. These
figures would be doubled if (as appears to be
the case) the return journeys have been omitted
from the calculations (see paragraph 5.94
above). |
E33 | There would be some night time rail track
possessions to allow major structural work to
take place. |
E34 | The noise assessments for the construction
work are based on worst case scenarios with no
mitigation. Mitigation measures should improve
some of the noise impacts. |
E35 | Where necessary, and unlike the operational
traffic noise assessment, the assessment of
construction noise is based on a more stringent
standard for noise at night. |
E36 | Night working on major bridge and viaduct
structures is likely to be required, for
approximately one night per week over a period
of up to 3 months at each bridge location. |
E37 | Piling and general construction work on
major structures at night is predicted to
result in noise exceedances in the range 21-29
dB. As an increase of 10 dB is regarded as a
severe impact, these much higher levels must be
regarded as very severe. |
E38 | Day time working would take place on 5.5
days per week, 11 hours per day. |
E39 | Day time noise is likely to last 4-9 months
at each site, with piling work lasting 1-3
months. Day time exceedances are predicted to
be mainly 1-7 dB, but up to 17 dB at one
location. These would give rise to some
moderate impacts. |
E40 | Vibration from piling may be perceptible up
to 100m from the operations. Though this would
be unlikely to affect the integrity of sound
buildings, there could be risk to older or
unsound buildings, and noticeable vibration
could be a source of concern to property owners
and occupiers. |
E41 | Noise mitigation measures would reduce some
of these impacts, but will in some cases depend
on vigilant adherence to good practice. |
E42 | Construction work would increase the
difficulties for pedestrians and cyclists
passing across the motorway route on existing
streets, and would increase community severance
further than that predicted for the operational
phase (see findings above). |
Summary of local environmental impacts as assessed
in Environmental Statement
| E43 | The accompanying table is a summarised
compilation of the assessments of the impacts of
community severance, visual impact, and noise
(during construction and when the motorway is in
use) contained in the Environmental Statement. |
RESULTS OF ENVIRONMENTAL ASSESSMENT : ADVERSE
IMPACTS AT LOCATIONS ALONG ROUTE
Location | Community Severance | Visual impact | Traffic noise | Noise during construction |
daytime | night time |
Kingston | | | | severe | severe |
Eglinton/Pollokshaws Road | moderate
(at night) | substantial | | moderate/severe | severe |
Oatlands/Polmadie | substantial
| slight/ moderate
(slight by year15) | | moderate | |
north Toryglen |
| moderate
(slight by year15) | | major | |
Rutherglen | moderate
(at night) | substantial | moderate | moderate | severe |
west/central | | | | |
Farme Cross | moderate
(at night) | substantial | | moderate | moderate |
Rutherglen east | substantial | substantial | | moderate | moderate |
River Clyde Crossing | | substantial | | | |
Fullarton | substantial | | | major | |
Chapter 6 : Airborne Emissions
(Note : references in brackets are to pages in Technical
Annex K)
F1 | Air quality standards and guidelines,
current and proposed are as described in
paragraphs 6.4 - 6.6 above, which are
incorporated herein. |
F2 | The principal pollutants and their current
and predicted levels are as described in
paragraphs 6.8 - 6.18 above, which are
incorporated herein. |
F3 | An air quality assessment impact study has
been carried out for the M74C. |
F4 | The methodology for the study is as
described in Chapter 15 of the ES and in
Technical Annex K1 and Appendix K1, all of
which are incorporated herein. |
F5 | The methodology is summarised in paragraphs
6.1-6.3, 6.19-6.23, and paragraphs 6.30- 6.31
above, which are incorporated herein. |
F6 | In assessing the impact of a road scheme,
most emission forecasts use traffic forecasts,
because emissions of pollutants are directly
related to vehicle use. |
F7 | The results of the study are not disputed,
the challenge being limited to interpretation
of the results e.g. percentage increases in
certain pollutants. |
F8 | The results are based on two spatial areas,
namely, a Wider Study Area and a Detailed Study
Area. |
F9 | The two spatial areas are as described in
paragraphs 6.21-6.22 above, which are
incorporated herein. |
F10 | The pollutants of concern are NO2 and PM10.
All other pollutants are within the objectives
and guidelines. (K31) |
F11 | Traffic related pollution decays rapidly
with distance from the road. (K47) Air quality
impact is only effective within 200m of the
motorway. |
F12 | Both spatial areas are based on predicted
changes in traffic flows on road links greater
than 10% brought about by the M74C. (K41/2) |
| F13 | The Wider Study Area relates to properties
within 200m of a road link, the measurement
being from the centre of the road link. (K47)
In this area, the majority of properties are
predicted to experience an improvement or no
change in NO2 concentrations, while a large
number of properties are expected to experience
a reduction in roadside PM10 concentrations as
a result of the M74C.(Table 15.1 ES p.206) More
residential properties are expected to benefit
(46%) than to suffer (25%), while the balance
are unaffected. This arises from the relocation
of traffic from local roads to the strategic
road network. |
F14 | In the Wider Study Area, the M74C is
predicted to give 12% and 0.4% reductions in
the number of properties exceeding NO2 and PM10
objectives respectively in 2010. (table
15.2) |
F15 | In the Detailed Study Area, the greatest
impact on NO2 concentrations are expected to
occur at the eastern end of the M74C, on the
new motorway itself. (ES p.207) Within 100m of
the M74C, slight increases in concentrations of
NO2 and PM10 are predicted. |
F16 | Within 100m of the M74C, there are 119
residential properties, 87 industrial, 15
retail, 5 office, 4 community, and 1
recreational property. (K38) |
F17 | In the Detailed Study Area, total maximum
annual NO2 concentrations at the most affected
receptor i.e. Eglinton Street for 2010 are
estimated at 39.3µg m-3, just under the
assessment criterion of 40µg m-3. Short term
NO2 concentrations are also predicted to fall
below the criterion. (ES p.207) |
F18 | In the Detailed Study Area, maximum
incremental concentrations of PM10 at the most
affected receptor are predicted to be 1.1µg m-3
as an annual average and 3.8µg m-3 as a 24 hour
average, compared with present background
concentrations of 27 and 64.5 µg m-3
respectively.(ES p.207) |
F19 | In the Detailed Study Area, further
modelling at a greater spatial scale indicated
that NO2 concentrations in 2010 would exceed
the 40µg m-3 criterion in the vicinity of the
Kingston Bridge. All other sections of the area
would be below the criterion in that year. Long
term average NO2 concentrations on and within
100m of the M74C and at the west end closest to
the city centre may be just above or below the
criterion, given the uncertainties inherent in
the modelling exercise.(ES p208) Air quality
objectives are likely to be met except at the
Kingston Bridge end of the M74C, where the
effect of the M8 itself, coupled with the high
level of city centre pollution, and not the
M74C, may result in the threshold being
exceeded. (K63) |
F20 | Table 15.3 of the ES (page 208) predicts a
significant decrease in emissions of CO, THC,
NOx, and PM10 from the Base 2001 to Do Minimum
2010. Do Minimum CO2 (2010) shows a marginal
decrease on Base 2001 (-11,600 tonnes/year, =
0.5%) The introduction of the M74C is predicted
to increase emissions of CO2, NOx and PM10,
while emissions of CO and THC show a decrease.
The increase in CO2 emissions attributable to
the motorway is predicted to be 86,600
tonnes/year, or 3.8%. |
F21 | The same table shows that for the year 2020,
the Do Minimum predicted figure is 2,366,800,
an increase of 96,800 tonnes/year above the
Base 2001 figure (4.3%), while the Do Something
2020 figure is 2,501,600, an increase of
134,800 tonnes/year (5.7%) due to the
introduction of the M74C. These figures reflect
the higher traffic levels that are predicted,
and the additional effect resulting from the
introduction of the new motorway. |
F22 | The Scottish Climate Change Programme (2000)
seeks to reduce greenhouse gas emissions in
Scotland to help deliver the UK contribution to
the Kyoto Agreement to reduce 1990 emissions by
12.5% by 2008-2012. (ES page 209) The Do
Minimum prediction for 2010 (see above) would
be lower than the 2001 Base, while the
introduction of the new motorway would result
in the higher levels and percentage increases
noted above, both for 2010 and 2020. |
F23 | Improvements in air quality for the benefit
of all, and those with respiratory problems in
particular, are an important part of government
policy. |
F24 | An overall improvement in air quality within
the AQMA covering the city centre, along with a
decrease in the number of non-compliant
properties in the AQMA, is predicted.
Properties on the M8 northern flank should also
benefit. |
F25 | The assessment study is based on a "high
growth" scenario and no account is taken of any
possible traffic reduction interventions.
Should growth be lower and/or traffic reduction
measures introduced, the impact on air quality
would be less. |
F26 | There appears to be no proven link between
new road construction schemes and the incidence
of asthma. |
Chapter 7 : Geo-technical, mining and c
ontaminated land
| G1 | The Ground Investigation (GI)
represents a comprehensive scientific appraisal of
ground conditions (including hydrogeology, mining
and contamination issues) along the route
corridor. |
G2 | For the GI, the route was divided into 5
sections, with 29 sub-area sites where
contamination was understood to be present, as
described at paragraph 7.2.1 of the ES. |
G3 | The number of boreholes and other tests
carried out in the fieldwork of the main GI are
described at paragraph 7.3 above. |
G4 | The GI indicates no particular difficulties
on geological, hydro-geological, and mining
issues. |
G5 | The contamination studies have been based on
a site by site risk assessment in accordance
with the guidance in paragraphs 21-23 of PAN
33. |
G6 | The challenge to the contamination evidence
did not extend to the technical data but was
limited to practicalities such as health risks,
costs, noise from piling operations, and the
like. |
G7 | The key contamination problems are as
described at paragraphs 7.17 above. |
G8 | The receptors at significant risk are as
described at paragraph 7.18 above. |
G9 | The remedial options are as described at
paragraph 7.20 above. |
G10 | The broad remediation strategy proposed is
to bury the contaminated materials (largely
chromium waste) beneath the embankments and
elevated structures which will carry the road
surface, with a range of other remediation
options (TRA/I/3) for contamination which
cannot be treated by this method. |
G11 | Containment is a long established and
accepted method of remediation and is one of
the methods of site restoration described in
Annex 1 of PAN 33. |
G12 | Paragraphs 18-20 of PAN33 confirm the
"suitable for use" approach as forming part of
national guidance. |
G13 | Paragraph 19(iii) of PAN33 identifies one of
the elements of the "suitable for use" approach
as "limiting requirements for remediation to
the work necessary to prevent unacceptable
risks to human health or the environment in
relation to the current use or future use of
the land …..". |
G14 | The route of the M74C has been selected
using the GI data to optimise the best value
for money option on all issues, including the
treatment of contaminated land. |
G15 | The EMS and the GI studies are of an ongoing
nature, the intention being to reduce the risk
of exposure during the construction and
operational phases of the road. |
G16 | Given the length of the M74C and the
extensive contamination, the estimated costs
for earth works, piling, and stabilisation do
not appear disproportionate. |
G17 | The remediation works do not involve any
exceptional or unique engineering works. |
Chapter 8 : Economic impact and
regeneration
Employment forecasts
H1 | The methodology for the Simmonds Report is
as summarised at paragraphs 8.3-8.6 above. |
H2 | The Reference Case in the Simmonds report
shows an increase in total employment for
Scotland of 298,000 between 2005 and 2030
(Table 6-1 p.15), with Glasgow and the Clyde
Valley making up about half of this total. |
H3 | The Simmonds report predicts an increase of
20,000 jobs in Glasgow and the Clyde Valley by
2030 directly attributable to the additional
competitiveness for some areas conferred by the
M74C. The main beneficiaries would be Glasgow
(+11,000) and Renfrewshire (+4,000), with
smaller benefits for East Renfrewshire and
South Lanarkshire (around 3000 each), North
Lanarkshire (about +1500 jobs) and East
Dunbartonshire (+500). |
H4 | Given the use of a fixed economic forecast
for Scotland as a whole, these would not be new
jobs for Scotland, but transfers of predicted
new jobs from elsewhere in Scotland. These job
transfers would be at the expense of the Forth
(-8000) and Ayrshire (-3000) areas, and North
Scotland (-2000), and within the Glasgow and
the Clyde Valley area, from West Dunbartonshire
(-500) and Inverclyde (-1200). |
H5 | Some of the additional jobs are predicted to
be located in Assisted Areas in Glasgow and
Renfrewshire, and some will be drawn from
existing Assisted Areas elsewhere. |
H6 | As a result of this transfer of jobs, the
Simmonds report predicts an additional 14,000
residents in Glasgow and the Clyde Valley by
2030, contributing to the area economy. |
H7 | The scope of the Ekos report is as
summarised at paragraph 8.17 above. |
H8 | The Ekos report predicts an additional
25,000 jobs (gross) directly attributable to
the M74C over the period up to 2030. This study
is based on area forecasts of employment
demand, and the potential supply capacity of
prospective development sites. Assumptions are
made as to what proportion of the predicted
growth can be attributed to the completion of
the M74, as a key factor leading to the
successful regeneration and redevelopment of
sites. |
H9 | On the demand side, table 4.6 of the Ekos
report indicates an annual growth in jobs of
the order of 10,000 between 1995 and 2002.
Figures show increasing demand in service
sector activities, continuing decline in
manufacturing, and a move towards science and
technology activities. (Ekos report, pages 25 -
27) |
H10 | On the supply side, table 4.2 of the Ekos
report identifies strategic development sites
in the west of Scotland capable of providing
2.3 million m
2 of business space, with a
potential capacity of 95,000 jobs (table 4.4)
over the next 20 years. There appears to be a
lack of information on the extent of
contamination on a number of the sites. |
H11 | The range of employment forecasts reviewed
in the Ekos report at tables 4.7, 4.8, and 4.9
demonstrate the wide differences between
various forecasts of essentially the same or
related matters. |
H12 | Objectors' criticisms of the Simmonds report
include limited consideration of land use and
transport elsewhere than central Scotland;
failure to take account of issues such as
business failures and the costs associated with
pollution and congestion; and over simplistic
assumptions. |
H13 | Objectors criticise the Ekos report as
simply listing land availability and failing to
address issues such as likely uptake, demand
and displacement. |
H14 | Objectors doubt the validity of predicted
jobs growth in both reports and, without
providing alternative figures, suggest that the
M74C might have a negative impact on employment
prospects due to the 2 way road effect, and the
fact that local labour may not be suitable for
the new jobs created. |
H15 | The GCVSP identifies 1,245 ha of marketable
business and industrial land in the plan area,
with past take up rates of 60 ha per annum and
projected rates of 69.5 ha until 2010 and 75 ha
from 2010 to 2020. |
H16 | There is approximately 114 ha of land
available for industrial or business use within
1.5km of the M74C, excluding Cambuslang
Investment Park. |
H17 | Paragraphs 11 and 12 of the SACTRA report
summary (August 1999; document JAG15) state
that : empirical evidence of the linkage
between road improvements and economic growth
is "
weak and disputed"; none of the claimed effects can be
guaranteed; "
any contribution to the sustainable rate of
economic growth of a mature economy, with well
developed transport systems, is likely to be
modest." results of studies of the economic impact of
completed transport projects "
do not offer convincing general evidence of
the size, nature or direction of local economic
impacts"; and that "
Our studies underline the conclusion that
generalisations about the effects of transport
on the economy are subject to strong dependence
on specific local circumstances and
conditions." |
H18 | In the light of these warnings, the
forecasts contained in the Simmonds and Ekos
reports relating to the creation of jobs in the
west of Scotland directly attributable to the
construction of the M74C must be treated with
caution, especially as they cover a long period
and there are internal inconsistencies. |
H19 | Given the express limitations and caveats in
both the Simmonds and Ekos reports, the wide
variations in forecasts, the lack of a robust
causal effect between new transport projects
and economic growth highlighted in the SACTRA
report, a precautionary approach to assessing
the impact of the M74C in terms of economic
development and regeneration is advisable. |
H20 | In the context of all the evidence and
caveats noted above, it would appear that the
most optimistic estimate of additional jobs in
the west of Scotland area directly attributable
to the M74C would be the figure of 25,000 (for
2030) contained in the Ekos report. However the
figure of 20,000 contained in the Simmonds
report would consist largely of transfers of
potential new jobs from other areas of
Scotland. Thus, on the basis of these two
reports, the net additional jobs for Scotland
due to the motorway would be 5,000 at the most.
Given the uncertainties of forecasting over
such a long period, the numerous other factors
at work, and the cautionary approach commended
in the SACTRA report, the figure seems likely
to be lower, rather than higher. The figure
then requires to be offset by potential losses
of jobs from existing businesses along the
motorway route who may fail to survive the
relocation process, or deciding to relocate
outwith the west of Scotland or even outwith
Scotland. |
Other economic benefits
H21 | Economic activity rates are low in the M74C
corridor. |
H22 | The perception of better transport links
could enhance the attractiveness of the area to
potential developers, leading to increased
economic activity rates. |
H23 | The M74C is regarded as critical to Scottish
Enterprise funding of projects including the
Clyde Waterfront, Clyde Gateway and the
EERR. |
H24 | The long history of the M74C has sterilised
a considerable area of land, generally former
heavy industrial land, along the route
corridor, a situation made worse by the
possible presence of contamination. |
H25 | Apart from contamination, a further
development constraint in this corridor may be
the lack of infrastructure. |
H26 | The M74C could act as a catalyst for the
regeneration of such land. Alternatively, the
land could be released for development by
abandoning the motorway proposal (removing the
blight) and by providing alternative access
arrangements where required. |
H27 | Industrial land unaffected by ground
conditions along the corridor, at the Clyde
Waterfront along to the airport and beyond, may
well benefit in the early years following
construction, through improved road links,
reliability on the network, and reduced journey
times. |
H28 | In the absence of traffic reduction
measures, benefits to the economy would be
progressively eroded by traffic growth. |
Economic impact and regeneration : transport
aspects
H29 | The M74C would benefit businesses to the
west of Kingston Bridge by providing an
improved transport link, but would increase
congestion at the Erskine Bridge, giving less
benefit to West Dunbartonshire and
Inverclyde. |
H30 | Households increasingly adjust to workplace
change by changing commuting habits rather than
their place of residence. |
H31 | The SIAS traffic modelling indicates that
improvements to the motorway and trunk road
network would facilitate more long distance
commuting. |
H32 | The 2 way road effect described in the
SACTRA report (JAG15) could act as a disbenefit
in that businesses may choose to locate outside
the Glasgow area due to the increased
accessibility to it afforded by the extended
motorway. In addition, jobs created locally may
be taken by long distance inward commuters. |
H33 | While easing a genuine bottleneck on a trunk
route may promote economic growth, the purpose
of the M74C is to complete a major new radial
motorway into Glasgow from the southeast. |
H34 | Car ownership rates in the M74C corridor are
low with the result that the new motorway would
do little to assist those currently excluded
from the mainstream economy due to the lack of
personal transport. |
H35 | The M74C would improve vehicular access to
and from Glasgow Airport from the south east of
Glasgow and from the north east by reducing M8
congestion. |
H36 | The proposed rail access to Glasgow Airport
should provide a more reliable mode of access
to the airport, serving a wide catchment area
through the rail network. |
Effects on businesses displaced by the new
motorway
H37 | The TRA estimated that 189 businesses would
be directly affected along the route of the new
motorway, affecting about 2,800 employees.
However the employment estimate was prepared
without inquiry being made of the businesses
themselves and must be viewed with caution. The
Morris furniture factory alone has some 500
employees. |
H38 | The TRA assumed that all businesses affected
would relocate. No account appears to have been
taken of the possibility of businesses choosing
or being forced to cease trading, or choosing
to relocate outwith the area. |
H39 | There must be doubt as to the prospect of
successful relocation of a number of these
businesses within the TRA timescale for
commencement of construction. It is noted that
the TRA is prepared to enter sites even where
the occupying business has not yet relocated.
(see paragraph 9.27 above) |
H40 | Given the number of businesses affected
along the route, the jobs involved, and the
services that some of them provide to other
components of the Scottish economy, the
disruption, relocation or cessation of trading
would be likely to have a severe impact on the
existing local economy and the individual
employees concerned, and to some extent on the
wider Scottish economy. |
Chapter 9 : Objections to compulsory purchase
order
Note : For several of the objections proceeding on the
basis of written submissions, the grounds of
objection/submissions are short, and the response from the
acquiring authority is a short standard reply. These are of
necessity reflected in short findings for these cases as
recorded below.
General
At the time of concluding the writing of this report,
some 25 objections to the proposed compulsory purchase
order remain not withdrawn, out of an original 42. These
relate to 36 plots out of the approximately 200 separate
plots covered by the order as a whole. There is some
overlap between objectors and plots, and between plots and
objectors. Details of remaining objections are listed in
the table on pages 9-1 and 9-2. Findings follow the same
sequence as chapter 9, following the motorway route from
west to east.
Noble Imports Wholesale : Map 1 : Plot 30
Noble 1 | The submissions for the parties are as
summarised in Chapter 9. |
Noble 2 | It is government policy to complete the M74
from Fullarton to the M8 as part of the
national road network. |
Noble 3 | The proposed line and design details of the
M74C have evolved over a number of years and
following a comprehensive technical appraisal
of options. |
Noble 4 | There was no alternative route before the
inquiry. |
Noble 5 | Plot 30 is on the line selected and required
for the construction of the M74C. |
Noble 6 | If the Special Road Scheme is approved, the
acquisition of the plot is necessary.
Conversely, if the Special Road Scheme is not
approved, acquisition is unnecessary. |
Albion Chemicals Ltd : Map 1 : Plot 31
Albion 1 | The legal submissions summarised in appendix
6 below are a matter for consideration by
Scottish Ministers and their advisers. |
Albion 2 | The description and background information
contained in paragraphs 9.9 - 9.11 above is
incorporated here. |
Albion 3 | The line of the proposed motorway indicated
on the local plan Proposals Map passes across
the Albion Chemicals site. |
Albion 4 | There are severe constraints on the
horizontal and vertical alignment of the new
motorway in this locality. Any deviation
sufficient to avoid the Albion Chemicals site
would be likely to involve severe difficulties,
and to affect other businesses in the
locality. |
Albion 5 | Albion Chemicals Ltd provides specialist
chemicals to numerous business and public
sector customers all over the UK and Ireland,
through a network of regional distribution
depots. |
Albion 6 | The premises at Paterson Street/West Street
are the only company depot in Scotland. It
makes an important contribution to the Scottish
economy by supplying up to 500 different
chemical products to about 2000 customers in
Scotland. It also makes an important
contribution to the Albion Chemicals business
by accounting for about 15% of the company's
chemical distribution activity, and by
providing part of the complete coverage of the
UK, necessary for some contracted supplies to
nationwide business customers. |
Albion 7 | It would not be possible for the company to
provide a competitive comparable level of
service from a depot in northern England, in
terms meeting customers' requirements for the
supply of small quantities of special products
within 24 hours. |
Albion 8 | The withdrawal of Albion Chemicals Ltd from
the Scottish chemicals market would reduce
effectiveness and business competitiveness as
Albion Chemicals has a large share of the
market, and there are only two other suppliers
in Scotland. In addition, about 60 specialist
jobs would be lost. |
Albion 9 | For these reasons, it would be undesirable
for the company to cease operations in
Scotland. |
Albion 10 | There is no specific locational need for the
Albion Chemicals business to be sited at
Paterson Street. The business could operate
successfully from a specialist industrial site
on the east side of Glasgow, provided that it
has close access to a motorway and is
sufficiently close to Kingston to retain most
of the current employees. |
Albion 11 | Any new site for the depot would be likely
to be more extensive than the current site, to
provide for current space and safety
requirements, and to allow more space for
manoeuvring and parking the distribution
vehicle fleet and employees' cars. |
Albion 12 | It would take about two years to set up the
business at an alternative site, largely
because of the need to find and obtain a
suitable site and then to obtain a number of
specialist authorisations. Time would also be
needed to construct and commission the new
facilities. |
Albion 13 | As the TRA hopes to have access to the site
to start motorway construction by around the
end of 2005, the window for this relocation is
already too small. Either the business would
have to be extinguished before alternative
premises are available, or the programme for
the motorway construction would have to be
postponed. |
First Engineering Limited : Map 2 : Plots 40 &
41
First 1 | The submissions for the parties are as
summarised in Chapter 9. |
First 2 | It is government policy to complete the M74
from Fullarton to the M8 as part of the
national road network. |
First 3 | The proposed line and design details of the
M74C have evolved over a number of years and
following a comprehensive technical appraisal
of options. |
First 4 | There was no alternative route before the
inquiry. |
First 5 | Plots 40 and 41 are on the line selected and
are required for the construction of the
M74C. |
First 6 | If the Special Road Scheme is approved, the
acquisition of the plots is necessary.
Conversely, if the Special Road Scheme is not
approved, acquisition is unnecessary. |
First 7 | Plot 40 is not connected to the rail
network. |
Land Securities Trillium : Map 3 : Plot 73
Trillium 1 | The submissions for the parties are as
summarised in Chapter 9. |
Trillium 2 | It is government policy to complete the M74
from Fullarton to the M8 as part of the
national road network. |
Trillium 3 | The proposed line and design details of the
M74C have evolved over a number of years and
following a comprehensive technical appraisal
of options. |
Trillium 4 | There was no alternative route before the
inquiry. |
Trillium 5 | Plot 73 is on the line selected and required
for the construction of the M74C. |
Trillium 6 | If the Special Road Scheme is approved, the
acquisition of the plot is necessary.
Conversely, if the Special Road Scheme is not
approved, acquisition is unnecessary. |
BRB (Residuary) Limited : Map 3 : Plot 76
BRB 1 | The submissions for the parties are as
summarised in Chapter 9. |
BRB 2 | It is government policy to complete the M74
from Fullarton to the M8 as part of the
national road network. |
BRB 3 | The proposed line and design details of the
M74C have evolved over a number of years and
following a comprehensive technical appraisal
of options. |
BRB 4 | There was no alternative route before the
inquiry. |
BRB 5 | Plot 76 is on the line selected and required
for the construction of the M74C |
BRB 6 | If the Special Road Scheme is approved, the
acquisition of the plot is necessary.
Conversely, if the Special Road Scheme is not
approved, acquisition is unnecessary. |
Guthrie Scottish Nominees (No 3) Limited : Map 4 :
Plots 80 & 81
Guthrie 1 The submissions for the parties are as
summarised in Chapter 9.
Guthrie 2 | It is government policy to complete the M74
from Fullarton to the M8 as part of the
national road network. |
Guthrie 3 | The proposed line and design details of the
M74C have evolved over a number of years and
following a comprehensive technical appraisal
of options. |
Guthrie 4 | There was no alternative route before the
inquiry. |
Guthrie 5 | Plots 80 and 81 are on the line selected and
required for the construction of the M74C. |
Guthrie 6 | If the Special Road Scheme is approved, the
acquisition of the plots is necessary.
Conversely, if the Special Road Scheme is not
approved, acquisition is unnecessary. |
Allscot Plastics Limited : Map 4 : Plots 94 &
96
Allscot 1 | The submissions for the parties are as
summarised in Chapter 9. |
Allscot 2 | It is government policy to complete the M74
from Fullarton to the M8 as part of the
national road network. |
Allscot 3 | The proposed line and design details of the
M74C have evolved over a number of years and
following a comprehensive technical appraisal
of options. |
Allscot 4 | There was no alternative route before the
inquiry. |
Allscot 5 | Plots 94 and 96 are on the line selected and
required for the construction of the M74C. |
Allscot 6 | If the Special Road Scheme is approved, the
acquisition of the plots is necessary.
Conversely, if the Special Road Scheme is not
approved, acquisition is unnecessary. |
David B Dobie (Accountants) : Map 4 : Plot 94
Dobie 1 | The submissions for the parties are as
summarised in Chapter 9. |
Dobie 2 | It is government policy to complete the M74
from Fullarton to the M8 as part of the
national road network. |
Dobie 3 | The proposed line and design details of the
M74C have evolved over a number of years and
following a comprehensive technical appraisal
of options. |
Dobie 4 | There was no alternative route before the
inquiry. |
Dobie 5 | Plot 94 is on the line selected and required
for the construction of the M74C. |
Dobie 6 | If the Special Road Scheme is approved, the
acquisition of the plot is necessary.
Conversely, if the Special Road Scheme is not
approved, acquisition is unnecessary. |
Glasgow Rowing Club : Map 4 : Plots 100-102
GRC 1 | The submissions for the parties are as
summarised in Chapter 9. |
GRC 2 | It is government policy to complete the M74
from Fullarton to the M8 as part of the
national road network. |
GRC 3 | The proposed line and design details of the
M74C have evolved over a number of years and
following a comprehensive technical appraisal
of options. |
GRC 4 | There was no alternative route before the
inquiry. |
GRC 5 | Plots 100-102, while not on the line
selected, are required for the construction of
the M74C as part of essential drainage
infrastructure. |
GRC 6 | If the Special Road Scheme is approved, the
acquisition of the plots is necessary.
Conversely, if the Special Road Scheme is not
approved, acquisition is unnecessary. |
GRC 7 | The rowing club has a specific locational
need to retain their facility on the river
bank, and to have unimpeded access to use the
boatshed for the storage of long boats. |
Polmadie realignment and affected businesses (maps
5 and 6) : Plots 103, 107, 110, 119, 121, 123-124,
210-213
Polmadie 1 | The current proposed route would affect the
following plots where objections to the
compulsory purchase order are maintained, that
were not affected by the scheme approved in
1995 : Ingram Brothers (Glasgow) Ltd (Plot
103); BOC Ltd (plot 107)*; Scotbeef Ltd (Plot
110); Mr & Mrs Philip C Smith and Philip C
Smith (Commercials) Ltd (plots 119+121);
Clearwater DC Ltd (part of plot 119); Shanks
Chemical Services (part of plot 119 +121); and
H Morris & Co Ltd (plots 123-124, 210-213).
(* The BOC site was affected by the 1995
scheme, but the requirement of the current
scheme is much more significant.) |
Polmadie 2 | The description of the locality (paragraph
9.53-9.55) and the various individual sites
(paragraphs 9.61-62, 66-67, 74, 82-86, and
89-90) are incorporated herein. |
Polmadie 3 | The current proposed route would require the
relocation of the activities on these
objectors' plots, in most cases the complete
relocation of the businesses to new sites. |
Polmadie 4 | The number of jobs on the sites affected by
the realignment would be at least 600, out of a
total of some 1800 jobs affected by the current
scheme on sites between the Dixons Blazes
Industrial Estate and Glasgow Road, Rutherglen.
(document TRA/C/7, table 6). |
Polmadie 5 | The number of jobs that would be displaced
along the corresponding section of the 1995
route would be about 1630. (same source
document; rail depot jobs are not
included). |
Polmadie 6 | The relocation of the railway depot would
add about £75 million to land costs, compared
with the current proposal, and broadly similar
amounts compared with other options
considered. |
Polmadie 7 | Relocating the rail depot to the south of
the WCML would bring it close to the Toryglen
residential area, where part of it would occupy
some of the amenity open space situated between
the housing and the existing railway land. |
Polmadie 8 | Replacing the railway depot would be a
complex and lengthy undertaking, possibly
requiring parliamentary powers and a period of
up to 6 years. |
Polmadie 9 | The estimated engineering costs of the 1995
scheme and the current scheme are very similar,
the estimated difference being in the order of
£0.6 million on a total of about £20
million. |
Polmadie 10 | Most of the businesses in this locality
provide specialist supplies and services to a
very wide area, extending well beyond the west
of Scotland and in some cases well beyond
Scotland. They make an important contribution
to the local and wider Scottish economy, both
in providing jobs locally and providing
important services to other businesses. |
Polmadie 11 | Relocating some of the displaced businesses
would be lengthy and complex, due to their size
and complexity (eg Morris Furniture), and the
need to find suitable sites and obtain safety
and pollution authorisations for activities
with specialised requirements (eg BOC Ltd,
Clearwater DC Ltd, and Shanks Chemical
Services). |
Polmadie 12 | The TRA estimates of land costs used in
assessing options have been based on historical
data rather than specific appraisal of the
facilities and activities on each of the
affected sites. |
Polmadie 13 | There is a very wide disparity between the
TRA estimates of land costs (including
compensation), which are in the order of £31
million for the whole section of route between
Dixons Blazes Industrial Estate and Glasgow
Road, Rutherglen, and those of the objectors,
where plots 119 and 121 alone are said to
require a combined expenditure of some £28
million. This suggests that there could be
difficulties in reaching mutually acceptable
compensation settlements. |
Polmadie 14 | The timescale for relocation of the more
complex businesses (probably some 2 years)
would be well over the period of a little more
than a year that would remain after the
decision is expected, before it is hoped that
construction would commence around the end of
2005. |
Polmadie 15 | If the displaced businesses are unable to
relocate before construction commences, due to
the timescale required to find suitable new
sites, gain necessary authorisations, and build
and commission new facilities, or because
compensation and other financial assistance is
insufficient to set up new facilities meeting
modern requirements, these jobs and businesses
services would be lost to the local and
Scottish economy, with devastating effects
locally and serious wider implications. |
Polmadie 16 | A motorway route below Polmadie Road would
be less visually intrusive than the current
proposal which would pass over Polmadie Road on
an elevated embankment and bridge. |
Millside Properties Limited/McConechy's Tyre
Service Limited : Map 9 : Plot 164
Millside 1 | The submissions for the parties are as
summarised in Chapter 9. |
Millside 2 | It is government policy to complete the M74
from Fullarton to the M8 as part of the
national road network. |
Millside 3 | The proposed line and design details of the
M74C have evolved over a number of years and
following a comprehensive technical appraisal
of options. |
Millside 4 | There was no alternative route before the
inquiry. |
Millside 5 | Plot 164 is on the line selected and is
required for the construction of the M74C. |
Millside 6 | If the Special Road Scheme is approved, the
acquisition of the plot is necessary.
Conversely, if the Special Road Scheme is not
approved, acquisition is unnecessary. |
Somerville & Morrison Limited : Map 10 : Plot
178
S&M 1 The submissions for the parties are as
summarised in Chapter 9.
S&M 2 It is government policy to complete the M74
from Fullarton to the M8 as part of the national road
network.
S&M 3 The proposed line and design details of the
M74C have evolved over a number of years and following a
comprehensive technical appraisal of options.
S&M 4 There was no alternative route before the
inquiry.
S&M 5 Plot 178 is on the line selected and is
required for the construction of the M74C.
S&M 6 If the Special Road Scheme is approved, the
acquisition of the plot is necessary. Conversely, if the
Special Road Scheme is not approved, acquisition is
unnecessary.
James Boyle : Map 10 : Plot 179
James Boyle 1 The submissions for the parties are as
summarised in Chapter 9.
James Boyle 2 The objector has now been re-housed and
the building demolished.
James Boyle 3 The objection is not competent.
MRC Pension TrustMap 10 : Plots 184-189, 191, & 220
| MRC 1 | The legal submissions for the
motion for an award of expenses against the TRA are
set out in Appendix 7, along with a recommendations
to hw the matter should be determined. The request
is now a matter for consideration by Scottish
Ministers. |
| MRC 2 | The description of the various
plots to which the objection relates is as set out
in paragraph 9.103 above. |
| MRC 3 | The recent planning history
relating to direct access to the Estate from
Cambuslang Road is as described in paragraph 9.107
above. |
| MRC 4 | The TRA promoted the Orders in March
2003. |
| MRC 5 | The objector commissioned its
traffic expert in October 2003. |
| MRC 6 | Given this sequence of events, the
Environmental Assessment could not embrace an
alternative proposal that did not exist at the
time. |
| MRC 7 | The requirements of PAN58 have not
been breached. |
| MRC 8 | The TRA believed the objection to
be a re-run of the 2002 called in planning
application. |
| MRC 9 | That application was refused. |
MRC 10 | The TRA supplied the objector's traffic
expert with all information requested and
without any undue delay. |
MRC 11 | Option 1A was put forward in February 2004
as part of a revised production MRC01 in the
mistaken belief that the access lane was in
public ownership. The fact that it was in
private ownership only came to the objector's
attention at the inquiry. |
MRC 12 | Option 1A would entail a fresh CPO and
further delay. |
MRC 13 | Option 1A is in direct conflict with a
proposed solution to an objection lodged by the
owner of the access lane. |
MRC 14 | In any event, option, 1A using land in
private ownership, would be contiguous with the
start of the slip road forming the on ramp
southbound to the M74C at the Cambuslang
interchange. |
MRC 15 | This would be contrary to the advice in
paragraph 62 of NPPG17 which states that direct
access to a motorway or a motorway slip road is
not allowed from any private development other
than a motorway service area. |
MRC 16 | Option 1B, mooted for the first time at the
inquiry, must inevitably take any access back
to the slip road. |
MRC 17 | The provision of a private access roadway
immediately adjacent to a motorway slip road
would be both confusing and inherently
dangerous. |
MRC 18 | Road safety considerations are paramount in
this matter. Additional signage close to a busy
interchange would be likely to add to driver
confusion, contrary to advice in the DMRB. |
MRC 19 | The proposed access via Duchess Place,
albeit possibly more expensive and involving
longer travel distances, provides a safer
vehicular access to the Estate. |
MRC 20 | Traffic regulations could be introduced if
necessary to assist the free flow of traffic on
Duchess Place. |
Mr B Millen : Map 10 : Plot 221
Millen 1 | The submissions for the parties are as
summarised in Chapter 9. |
Millen 2 | It is government policy to complete the M74
from Fullarton to the M8 as part of the
national road network. |
Millen 3 | The proposed line and design details of the
M74C have evolved over a number of years and
following a comprehensive technical appraisal
of options. |
Millen 4 | There was no alternative route before the
inquiry. |
Millen 5 | Plot 221 is on the line selected and is
required for the construction of the M74C. |
Millen 6 | If the Special Road Scheme is approved, the
acquisition of the plot is necessary.
Conversely, if the Special Road Scheme is not
approved, acquisition is unnecessary. |
Millen 7 | If the M74C is carried out as intended, the
access in question will immediately abut a
traffic light. Vehicles waiting at the light
when it is red will prevent other vehicles from
leaving or entering the site. |
Corus plc : Maps 10 & 11 : Plots 193-195
Corus 1 | The submissions for the parties are as
summarised in Chapter 9. |
Corus 2 | It is government policy to complete the M74
from Fullarton to the M8 as part of the
national road network. |
Corus 3 | The proposed line and design details of the
M74C have evolved over a number of years and
following a comprehensive technical appraisal
of options. |
Corus 4 | There was no alternative route before the
inquiry. |
Corus 5 | Plots 193-195 are on the line selected and
are required for the construction of the
M74C. |
Corus 6 | If the Special Road Scheme is approved, the
acquisition of the plots is necessary.
Conversely, if the Special Road Scheme is not
approved, acquisition is unnecessary. |
Hillview Developments Limited : Map 12 : Plot
198
Hillview 1 | The submissions for the parties are as
summarised in Chapter 9. |
Hillview 2 | It is government policy to complete the M74
from Fullarton to the M8 as part of the
national road network. |
Hillview 3 | The proposed line and design details of the
M74C have evolved over a number of years and
following a comprehensive technical appraisal
of options. |
Hillview 4 | There was no alternative route before the
inquiry. |
Hillview 5 | Plot 198 is on the line selected and is
required for the construction of the M74C. |
Hillview 6 | If the Special Road Scheme is approved, the
acquisition of the plot is necessary.
Conversely, if the Special Road Scheme is not
approved, acquisition is unnecessary. |
H Meanen (Electrical Services) Ltd : Map 14 : Plot
207
Meanen 1 | The description of the site and operation is
as set out in paragraph 9.131 above. |
Meanen 2 | If acquisition takes place, less off street
parking will be available for the business,
causing some difficulties because of the number
of vehicles operated. |
Meanen 3 | There may be some opportunity for on street
parking. |
« Previous | Contents | Next »