« Previous | Contents | Next »
Listen
ROADS (SCOTLAND) ACT 1984; ACQUISITION
OF LAND (AUTHORISATION PROCEDURE)(SCOTLAND) ACT 1947
M74 SPECIAL ROAD (FULLARTON ROAD TO WEST OF KINGSTON
BRIDGE) ORDERS
REPORT OF PUBLIC LOCAL INQUIRY INTO OBJECTIONS
VOLUME 1 : MAIN REPORT
PART 3 : STATUTORY OBJECTIONS
CHAPTER 9 : OBJECTIONS TO THE COMPULSORY PURCHASE
ORDER
Introduction
9.1 The proposed compulsory purchase order embraces
virtually all of the land that would be occupied by the
proposed motorway extension and associated works. A small
part of the route is omitted from the order, notably a
parcel of derelict land to the east of Farmeloan Road and a
small area close to the Fullarton Road junction.
9.2 The land where acquisition is intended comprises
around 200 separate plots, though some form contiguous
clusters within a single ownership. These are most
conveniently seen on a series of 14 maps (reference
2NEA/13/10, dated March 2003), where the land and
servitudes to be acquired are shown in colour on the
topographical base, together with all plot boundaries and
plot numbers.
9.3 Formal statutory objections to the order were lodged
by or on behalf of 42 objectors. Continuing negotiations
between the acquiring authority and these objectors has
resulted in the withdrawal of a number of these objections.
By the close of the inquiry at the beginning of March 2004,
the number of objections not withdrawn was 29, affecting
some 57 plots of land (see document TRA/V/10). Since the
close of the inquiry, and up to the time of completion of
this report, further objectors have withdrawn, reducing the
number of statutory objections to the compulsory purchase
order not withdrawn to 25. Appendix 4 of this report lists
those objectors. The table below lists them on a
geographical basis, moving from west to east (maps 1 to
12), as that is the arrangement that we have adopted to
report on these objections. Maps 13 and 14 are extra maps
showing 4 additional plots that are remote from the
motorway alignment, where the compulsory acquisition of
land or permanent servitudes is proposed.
9.4 For each objector, the table gives the map number
and plot number; the general location of the plots; the
name of the objector; the extent of the land; and (in some
cases) some extra information.
9.5 For each objection, we provide :-
- a short description of the land proposed for
compulsory purchase and the activities that were taking
place on the land at the time of the public local
inquiry;
- a summary of the main arguments put forward against
compulsory purchase;
- a summary of the main points of response on behalf
of the acquiring authority.
In some cases, objections have been grouped together for
reporting because either they relate to the same land, or
are close to nearby land where similar considerations
apply. Findings of fact relating to these objections are
contained in chapter 10 below.
LOCATIONS OF PLOTS WHERE STATUTORY OBJECTIONS
MAINTAINED [at 1 July 2004]
Map number+ plot number | Location | Name of objector | Area ofplot(s) - sq m | Notes |
1/30 | West Street, Kingston | Noble Imports Wholesale | 3,563 | |
1/31 | Paterson Street, Kingston | Albion Chemicals | 7,642 | |
2/40+41 | West Street + Salkeld Street | First Engineering Ltd | 6,837 + servitude 2,017 | |
3/76 | Pollokshaws Road | BRB (Residuary) Ltd | 20,912 | |
3/73 | Pollokshaws Road | Land Securities/Trillium | 3,392 | |
4/80+81 | Cathcart Road/Dixons Blazes | Guthrie Scottish Nominees (No 3) Ltd | 31,815 + servitude1,684 | |
4/94+96 | Lawmoor Place | Allscot Plastics Ltd + David B Dobie | 982 + 2,211 | |
4/100-102 | Clyde river bank | Glasgow Rowing Club | 252 + 636 | |
5/103 | Lawmoor Place | Ingram Brothers (Glasgow) Ltd | 4,603 | |
5/107 | Polmadie Road (west) | BOC Ltd | 39,529 | |
5/110 | Polmadie Road (east) | Scotbeef Ltd | 843 | |
6/119 (part) | Polmadie Avenue | Clearwater DC Ltd | 13,366 | (occupier) |
6/119 (part) +121(part) | Polmadie Avenue | Shanks Chemical Services | as above + 4,983 | (occupier) |
6/119 + 121 | Polmadie Avenue | Mr & Mrs Philip C Smith | as above + 4,983 | (owners) |
6/121 (part) | Polmadie Avenue | Philip C Smith (Commercials) Ltd | as above | (occupier) |
6/123-124, 210-213 | Rosyth Road | H Morris & Co Ltd | 6 contiguous plots totallingapproximately
4.13 ha | |
9/164 | Farmeloan industrial estate | Millside Properties/McConechy's Tyre
Service | 2,360 | |
10/179 | Cambuslang Road | Mr James Boyle | Re-housing objection only; property now
demolished |
10/184-189 +191 +220 | Cambuslang Road | MRC Pension Trust Ltd | 5 plots totalling
17,108; 3 servitudes totalling 422 |
10/178 | Cambuslang Road | Somerville & Morrison Ltd | 4,263 | |
10/221 | Cambuslang Road | Mr B Millen | 20 | |
10/193 | Clydebridge Steel Works | Corus PLC | 9,884 | also plots 11/194-195 |
11/194 + 195 | Clydebridge Steel Works | Corus PLC | 71,616 + servitude 467 also plot 10/193 |
12/198 | Cambuslang Investment Park | Hillview Developments Ltd | 10,472 | |
14/207 | Polmadie Road/Aikenhead Road | H Meanen (Electrical Services) Ltd | 90 | |
Noble Imports Wholesale : Map 1 : Plot
30
Description and background
9.6 This is a 3 storey former industrial building in the
southern part of the street block bounded by Paterson
Street, Scotland Street, and West Street. The site of
Albion Chemicals Ltd (see below) adjoins to the north. The
building was originally built as the Scotland Street Engine
Works, and is listed as being of special architectural or
historic interest, category B (regional importance). There
is a photograph of the building following page 158 of
volume 1 of the EA. The building was described as partly
derelict at the time that the surveys for the Environmental
Assessment were carried out. At the close of the public
local inquiry (March 2004), the building appeared to be
partly occupied as a cash and carry outlet and for car
repairs, and partly vacant/derelict.
Summary of case for Noble Imports Wholesale
9.7 The M74C is unnecessary.
Summary of case for the acquiring authority
9.8 The requirement for the completion of the trunk road
network around Glasgow had been established in both the
planning and transport context. The benefits of the
proposed road are fully set out in the TRA evidence (
see parts 1 and
2 of this report).
Albion Chemicals Ltd : Map 1 : Plot 31
Description and background
9.9 The Albion Chemicals site is situated close to the
south end of the Kingston Bridge, at the western end of the
proposed motorway. This is an area of mixed uses, mainly
industrial, storage, and distribution. The site extends to
about 7,600 square metres, occupying most of the street
block bounded by Paterson Street, Gloucester Street, West
Street, and Scotland Street. The company has operated from
this locality since its foundation in 1841.
9.10 The site is used for the receipt, storage,
blending, re-packaging, and distribution of a wide variety
of chemical products, the majority of which are inherently
hazardous. Incoming material is brought in by large road
tankers and lorries; is stored in a variety of segregated
tanks; blended as necessary in mixing installations; stored
in a variety of product tanks, drums, and cylinders; and
distributed to customers by means of a vehicle fleet based
at the premises consisting of road tankers, lorries and
vans. The site accommodates numerous specialist storage and
processing facilities (approximately 60 bulk storage
tanks), administrative offices, and a works canteen, shower
and toilet facilities. These are accommodated in the open
air, in covered storage, and in a two storey modern office
building. The site plan/overview produced by Albion
Chemicals (document ACL 7) shows these features.
9.11 The specialist and hazardous nature of the
materials that are stored and processed at the site means
that the site is required to have various specialist
operating licences, including registration under COMAH Tier
1.
Summary of case for Albion Chemicals Ltd
9.12 The company took part in the public inquiry,
appearing on 26 January 2004. The main points of argument
raised against the compulsory purchase order are as
follows.
9.13 The company operates from a series of sites
throughout the UK and also in Ireland. The company
consolidated its activities in Scotland during the late
1980s and early 1990s, closing several sites. The Glasgow
site is now the only company site in Scotland, and serves
customers throughout Scotland. The site contains highly
specialised equipment. It supplies more than 500 specialist
chemical products to some 2000 industrial, utility, and
leisure customers, according to customers' specifications
and requirements. Albion Chemicals is currently the largest
chemical distributor in Scotland, with about 30-50% of the
market, and supplying some 1200 tonnes of chemical products
each week. To achieve this, the company requires good
access to and from the motorway and trunk road network to
receive incoming bulk materials (mainly from northern
England) and to distribute products to customers.
9.14 The company emphasises the important role that it
plays in meeting the specialist needs of customers. It can
provide a 24 hour service to customers on a very wide range
of products requiring special handling and delivery. This
aspect is essential, and is not suited to supply from a
distant depot in England. In addition, there are important
efficiency and safety benefits from having a dedicated
fleet of distribution vehicles, rather than subcontracted
arrangements. Albion employs about 50 staff at the site,
plus 10 drivers, who have considerable knowledge and
experience of this specialist activity, and without whom
the company could not operate.
9.15 The company has consistently opposed the M74
extension on various occasions as part of the roads
authorisation and planning procedures, including objecting
to the Glasgow City Plan. It argues that the adverse effect
on the company, employment, and the Scottish economy is
such that an alternative route for the motorway should be
found.
9.16 The company notes that the structure plan for
Glasgow and the Clyde Valley, as well as supporting the
principle of the completion of the M74, seeks to promote
the local economy, particularly through the expansion of
existing firms.
9.17 The local plan, which is intended to apply the
strategic guidance contained in the structure plan,
contains no exact route for the M74 extension. However the
plan recognises that existing industrial areas are the
focus for continuing economic activity, where proposals for
improvement and modernisation will be supported. The Albion
Chemicals site lies within such an area.
9.18 The company submits that it would have great
difficulty in replicating the site, together with the
specialist facilities, permissions, and operating licences,
at another location, and this would be a lengthy process,
probably taking about 18 months to 2 years. A new facility
would be likely to be twice the area of the current site,
to meet current operating requirements, and would probably
cost between £8 and £12 million. It would probably be
located on the east side of Glasgow, convenient for
deliveries from England and distribution to customers in
both Glasgow and elsewhere in Scotland.
9.19 Some discussions about relocation have taken place,
but nothing has come of them. To achieve a satisfactory and
timeous move, it would be necessary to identify and secure
a suitable site; have assistance in obtaining the necessary
consents; have advance compensation to finance the new
development; and construct and commission the new
development. There would be only a tight window of
opportunity between knowing that the move was necessary
(due to confirmation of the compulsory purchase order) and
having to vacate the present site for motorway construction
to start. Entry to the site might be required by late 2005,
but (in the event that the order is confirmed) this should
be delayed to allow continuity of the business until a new
facility is ready for use. The company should be given
priority status, and professional and financial assistance
to achieve a fast track move.
9.20 A new facility would require finance to be raised
from banks, which if unsuccessful would force the closure
of the Glasgow site. Scotland represents an important
element (approximately 15%) of the company's chemical
distribution business, and includes some large customers
who have contracts for Albion to supply destinations all
over the UK from their network of depots. The company
estimates that the closure of the Scottish depot would mean
the loss of about £16 million worth of business. The
absence of a Scottish depot could thus have a serious
effect on the company as a whole. In addition, it would
result in a loss of specialised jobs, and the reduced
competition in the Scottish market for special chemicals
could reduce overall competitiveness in the Scottish
economy. Distribution from northern England would be less
efficient, and would increase the amount of hazardous
chemicals on that route.
Summary of case for the acquiring authority
9.21 In response to these arguments, it was stated for
the acquiring authority that disturbance compensation would
be payable by the TRA on the basis of the statutory code
for this purpose. The Valuation Office Agency had been
employed by the TRA to consider each case on its individual
merits. Compensation was not a valid ground for objection
to the proposals.
9.22 The requirement for the completion of the trunk
road network around Glasgow had been established in both
the planning and transport context. The benefits of the
proposed road are fully set out in the TRA evidence (see
parts 1 and 2 of this report). The local plan Proposals Map
shows the new motorway passing across the Albion Chemicals
site.
9.23 The TRA has carried out investigations to determine
the preferred line of the new motorway, including a robust
assessment of various options. The factors that constrain
alignment options in this area include :
- The need to achieve satisfactory connections to the
M8, with acceptable vertical and horizontal
geometry
- The existing SPT subway stations at Shields Road
and West Street
- The crossings of the Paisley and City Union rail
lines
- The provision of on and off ramps for the M74
- Listed buildings in the area
- The surface street network in the
Kingston/Tradeston area.
If the route was to be changed, these factors would
present considerable problems.
9.24 Consideration was given to extending the Port
Eglinton viaduct to the west to allow Albion Chemicals to
remain in operation below the viaduct. However this was
found to be unacceptable due to the potentially hazardous
nature of the business.
9.25 For these reasons, the TRA is satisfied that the
optimum alignment has been selected and the minimum land
requirement identified, and that the land included in the
CPO is required.
9.26 Subject to the authorisation of the various orders,
the projected timetable for the motorway project is :
- August 2004 : Draft tender documents
- Autumn 2004 : Ministers' decision on Orders
- November 2004 : Design and build tenders
invited
- May 2005 : tenders considered
- August 2005 : decision on contract : design and
mobilisation period follows
- Late 2005/early 2006 : start of works
Some advance works might take place during the second
half of 2005, mainly at the eastern end of the scheme.
9.27 A major structure was to be built in the vicinity
of the Albion land, so that the TRA wished to have clear
access for the contractor as soon as possible. Any delay
would have cost implications. The window of opportunity to
relocate the business was now less than 2 years, and was
becoming critical. The TRA therefore wishes to acquire the
Albion Chemicals site by voluntary agreement as soon as
possible, to allow work on the relocation of the business
to start as soon as possible. The TRA is prepared to take
that risk in advance of the outcome of the authorisation
process. However, in the event that the relocation had not
occurred by the time that the site was required for the
contractors, the TRA would be prepared to countenance the
cessation of the business without an alternative Scottish
location.
9.28 Special arrangements were in hand to provide
assistance with the relocation of displaced businesses. A
business relocation team had been formed within the two
councils, with funds and professional expertise to identify
options and carry out feasibility studies. Where council
owned land could be used, priority could be given to
established firms.
9.29 The TRA accepted that the potential loss of some 50
jobs at the site was a matter for the public interest, as
was the contribution of the company in supplying chemicals
to numerous business customers in all parts of Scotland.
Overall costs were also a matter of public interest, and
relocating the business would be likely to be cheaper than
extinguishing the business at this site. The TRA considered
that the completion of the M74 motorway was a much more
important matter than the disturbance or possible loss of
these jobs. The proposed motorway would affect a total of
about 186 businesses with around 2500 employees, but was
expected to achieve major benefits in terms of the economic
return on the investment, benefits on local streets, and
economic and regeneration benefits amounting to
15,000-20,000 jobs. There was thus a compelling major
public interest in the scheme proceeding, which outweighed
the hardship that would be caused to the objector.
First Engineering Limited : Map 2 : Plots 40
& 41
Description and background
9.30 Plot 40, extending to 6,837m
2, is a triangular area of land on the north
east side of West Street, Glasgow, situated in an elevated
position between two elevated railway lines. At the time of
the inquiry, it appeared to be vacant and neglected but,
because of its position, it was difficult to gain a clear
view. The plot is on the line of the elevated section of
the M74C between the Kingston Bridge and Eglinton Street.
Plot 41 relates to a servitude right of pedestrian and
vehicular access over 2,017m
2 of land at 34 Salkeld Street, Glasgow for
constructing and maintaining the elevated structure.
Summary of case for First Engineering Limited
9.31 The objection is based on the importance of plot 40
to the ongoing operations of the objector. The plot, which
is leased from Network Rail, is currently the subject of
negotiations with a view to the objector buying out the
landlord. The plot is the objector's principal stores
facility for the whole of Scotland and services the
infrastructure maintenance contracts with Network Rail.
Sleepers, signalling equipment, large cabling reels and
stores for the train protection warning system are among
the items stored there and it is vital that there is no
diminution in the size of the facility, which while clamped
out of use, is nonetheless a rail connected facility. The
objector requires to retain the capability of rail use of
the site for stabling and maintaining track machines. The
servitude right to be acquired under plot 41 will
detrimentally impact on the safety and security of the
objector's operations in the area. Insufficient technical
information has been made available to allow a thorough
assessment of the likely impact of the M74C on the
objector's operations.
Summary of case for the acquiring authority
9.32 In response to the objection, it is stated for the
TRA that the need for the M74C has been established, in
order to complete the trunk road network across Glasgow.
The proposed motorway would provide a new high quality
strategic link through Glasgow, and would offer an
alternative to the M8, which is often heavily congested.
There are ongoing discussions with the objector in an
effort to reach agreement.
9.33 In this regard, there may be surplus land available
to the objector, following the construction of the M74C,
from those parts of plot 40 not affected by bridge
supports.
9.34 Network Rail has confirmed that plot 40 is not
connected to the rail network. While a significant portion
of the plot was earlier earmarked as a future station under
the Crossrail project promoted by SPT, current plans
provide for the construction of the new station under the
M74C at this location.
BRB (Residuary) Limited : Map 3 : Plot
76
Description and background
9.35 This plot, extending to 20,912m
2, forms part of a much larger, broadly
triangular area of land between the WCML on the south west,
Pollokshaws Road on the north west, and Cathcart Road on
the north east. The plot is level and vacant and the line
of the M74C passes directly across it on an embankment.
Summary of case for BRB (Residuary) Limited
9.36 The objection is based on the following grounds:
-
- Plot 76 is part of a larger land holding, the
balance of which will be effectively severed by the
M74C. There is no access provided under the embankment
to be constructed to allow access to the balance of the
land holding.
- Network Rail has a right of access across the plot
for maintenance of the WCML.
- Negotiations regarding the redevelopment of the
balance of the land holding between the objector and
GCC are well advanced and it would be premature to
determine the exact line of the M74C before these
negotiations are satisfactorily concluded.
- Purchase of the plot would materially affect the
objector's ability to implement an extant planning
permission for retail, leisure, and industrial
development of the land holding.
Summary of case for the acquiring authority
9.37 In response to the objection, it is stated for the
TRA that the need for the M74C has been established, in
order to complete the trunk road network across Glasgow.
The proposed motorway would provide a new high quality
strategic link through Glasgow, and would offer an
alternative to the M8, which is often heavily congested.
The issue of severance is not a competent objection as
statutory provisions deal with such issues. In any event,
there are ongoing discussions with both the objector and
Network Rail on possible access arrangements.
Land Securities Trillium : Map 3 : Plot
73
Description and background
9.38 Plot 73, extending to 3,392m
2, is part of the office block known as and
forming 159/181 Pollokshaws Road, Glasgow. It lies to the
south east of Pollokshaws Road and is on the line of an
elevated section of the M74C.
Summary of case for Land Securities Trillium
9.39 The objection is that the tenant - the Department
of Work and Pensions - will require to relocate its entire
operation in postal district G41, the community it
currently serves. It is unlikely that it will be able to
acquire a suitable site or building with planning
permission in the area in the open market and accordingly
may have to displace a higher value use to meet locational
and space requirements. The plot represents about one half
of the building, all of which is occupied by the tenant as
a single entity operation. Relocation would require a
similar operation. The objection would be withdrawn if the
TRA gave an undertaking that compensation would be based
under Rule 5 - equivalent re-instatement - and that the
whole building would be acquired.
Summary of case for the acquiring authority
9.40 In response to the objection, it is stated for the
TRA that the need for the M74C has been established, in
order to complete the trunk road network across Glasgow.
The proposed motorway would provide a new high quality
strategic link through Glasgow, and would offer an
alternative to the M8, which is often heavily congested.
There are ongoing discussions with the objector in an
effort to reach agreement. Disturbance compensation is not
a competent ground of objection and will be paid in terms
of statute. Again, there are statutory provisions to deal
with severance compensation when only part of a property is
to be acquired. This is not a competent ground of objection
and compensation will be paid if circumstances warrant.
Guthrie Scottish Nominees (No.3) Limited : Map
4 : Plots 80 & 81
Description and background
9.41 Plot 80, extending to 31,815m
2, is a long rectangular area of land on the
north east side of the WCML, running south eastwards from
Cathcart Road to properties in Lawmoor Place and Lawmoor
Avenue in the Dixon Blazes Industrial Estate. It is
understood that the plot was formerly railway land, being a
large part of the former Gushetfaulds junction. The land is
level and undeveloped and is on the line of the M74C where
it runs in a cutting between Cathcart Road and the
industrial estate. Plot 81 relates to a servitude right of
access for laying down and maintaining drainage apparatus
over a 1,684m
2 narrow strip of land connecting plot 80 at
right angles to Lawmoor Street on the north east. This plot
is also level and undeveloped.
Summary of case for the objector
9.42 The objection is that the M74C can be undertaken
without the need for these two plots.
Summary of case for the acquiring authority
9.43 In response to the objection, it is stated for the
TRA that the need for the M74C has been established, in
order to complete the trunk road network across Glasgow.
The proposed motorway would provide a new high quality
strategic link through Glasgow, and would offer an
alternative to the M8, which is often heavily congested.
There are ongoing discussions with the objector in an
effort to reach agreement.
Allscot Plastics Limited : Map 4 : Plots 94
& 96
Description and background
9.44 Plot 94, extending to 982m
2, accommodates office premises known as and
forming 6 Lawmoor Place, Glasgow. The objector is tenant of
part of the premises. Plot 96, extending to 2,211m
2 and which lies immediately across Lawmoor
Place from plot 94, belongs to the objector and is the
manufacturing facility for the objector's plastics
business. Both are on the line of the M74C.
Summary of case for Allscot Plastics Limited
9.45 The objection is based on the damaging impact the
M74C will have on the objector's business, one that has
operated for 16 years. Relocation and the attendant
upheaval may result in loss of customer base, while the use
of hazardous materials might also make the task of finding
suitable premises more difficult.
Summary of case for the acquiring authority
9.46 In response to the objection, it is stated for the
TRA that the need for the M74C has been established, in
order to complete the trunk road network across Glasgow.
The proposed motorway would provide a new high quality
strategic link through Glasgow, and would offer an
alternative to the M8, which is often heavily congested.
Compensation would be payable in terms of statute.
David B Dobie (Accountants) : Map 4 : Plot
94
Description and background
9.47 This plot, extending to 982m
2, accommodates office premises known as and
forming 6 Lawmoor Place, Glasgow. The objector is tenant of
part of the premises. The plot is on the line of the
M74C.
Summary of case for David B Dobie
(Accountants)
9.48 The objections are to all 3 orders and are that the
M74C will have a detrimental impact on the objector's
business, particularly through the loss of business and
upheaval which would result from relocation brought about
by the impact of the M74C on the existing access.
Summary of case for the acquiring authority
9.49 In response to the objection, it is stated for the
TRA that the need for the M74C has been established, in
order to complete the trunk road network across Glasgow.
The proposed motorway would provide a new high quality
strategic link through Glasgow, and would offer an
alternative to the M8, which is often heavily congested.
There are ongoing discussions with the objector in an
effort to reach agreement.
Glasgow Rowing Club : Map 4 : Plots
100-102
Description and background
9.50 Plots 100 and 101, extending to 636m
2 and 547m
2 respectively, belong to GCC and are leased to
the objector. Plot 102 relates to a servitude over 72m
2 of the bed of the River Clyde to the north
east of Caledonia Road for laying down and maintaining
drainage apparatus in connection with the M74C.
Summary of case for Glasgow Rowing Club
9.51 Plot 100 is situated in front of the roller shutter
doors of the boathouse and is needed to allow access to
both the river for boats and for removing boats from the
boathouse to other locations for competitions. Boats are up
to 20m long and plot 102 is the site of the steps that lead
to the only access to the river. Planning permission has
been granted for the extension of these steps and work
should be completed in the next few months. Without access
to plots 100-102, the club cannot function and would seek
severance compensation.
Summary of case for the acquiring authority
9.52 On behalf of the TRA, it is submitted that issues
of compensation are not competent grounds of objection to a
CPO. Compensation will be paid according to circumstances
and the statutory provisions relating to disturbance and
severance. There are ongoing discussions with the objector
with a view to reaching agreement.
The Polmadie realignment : maps 5 and
6
9.53 At Polmadie Road, the new M74 motorway would have
an intermediate 4 way diamond junction. At this point, the
WCML passes beneath Polmadie Road, and there are extensive
railway facilities on the north side of the railway,
immediately to the east of the road bridge. Objectors in
this area comprise : Ingram Brothers (Glasgow) Ltd (Plot
103); BOC Ltd (plot 107); Scotbeef Ltd (Plot 110); Mr &
Mrs Philip C Smith and Philip C Smith (Commercials) Ltd
(plots 119+121); Clearwater DC Ltd (part of plot 119);
Shanks Chemical Services (part of plot 119 +121); and H
Morris & Co Ltd (plots 123-124, 210-213).
9.54 This group of objections relate to a series of
industrial sites which form the greater part of a strip of
land about 100-150m wide and about 1100m long to the north
of the WCML and the adjacent train maintenance facilities.
The latter land was previously occupied by the original
Polmadie engine sheds, but has been redeveloped to form a
much more modern facility, comprising 5 electrified tracks
leading into a maintenance building some 400m in length.
The route of the M74 extension approved in 1995, and
renewed in 2001, would have passed through the railway
land, avoiding most of the objectors' sites, and affecting
only the southern third of the BOC site.
9.55 The route of the current motorway proposal has been
modified to deflect the route to the north to avoid the
railway maintenance site. It now passes through the centre
of the BOC site, leaving remaining portions to north and
south, and through most or all of the land held by the
other objectors.
9.56 For each of these objectors, it is part of their
case that the motorway route should revert to the original
alignment that would avoid their properties. The TRA has
provided evidence as to why the new northern alignment
should be preferred. The evidence relating to this issue is
reported below, bringing together the relevant submissions
from the TRA and from all of the affected objectors. This
is followed by separate sections for each objector, where
their site specific submissions and the corresponding TRA
response are reported.
9.57 The main arguments presented by the objectors as to
why the southern alignment through the railway land should
be preferred are as follows :
- The currently proposed northern alignment would
sever a number of long established businesses.
- The original southern alignment would avoid or
reduce the loss of their properties, and the
consequential disruption of the various businesses.
(Detailed arguments for individual businesses are
reported below.)
- The realignment has come about due to
representations from rail interests.
- The route of the motorway should remain on the 1995
approved route, which is straight, offering better
alignment and gradients, and would be cheaper to
construct and safer to operate, as it is adjacent to a
motorway junction.
- The 1995 alignment would allow the motorway to pass
under, not over Polmadie Road, minimising environmental
and visual impact. (see also Logan Street Tenants and
Residents Association objection, reported at paragraph
5.13 above.)
- Insufficient justification has been given to
support the northward diversion, which would be in
conflict with the objective of minimising the effects
on properties.
- There is no planning permission for the northern
realignment. The Scottish Executive cannot promote a
CPO without first demonstrating a planning
permission.
9.58 The main information presented by the TRA as to why
the current proposal (the northern alignment at Polmadie)
should be preferred is as follows :
- A total of 8 different alignment options at
Polmadie have been examined, including environmental
and engineering assessments. The options are the 1995
scheme and 7 others. All figures relate to the Polmadie
section of the route encompassed by these local
studies.
- For the 1995 scheme, the engineering costs of
relocating the Polmadie railway facilities to the south
of the WCML are derived from a study carried out by the
Babtie Group (document TRA/N/1), and are estimated to
be in the order of £82 million, +/- 30%.
- Following elimination of 3 clearly unsatisfactory
options, the 5 remaining options were examined in terms
of costs and impacts on jobs and businesses.
Information for this purpose was supplied by the
Valuation Office Agency and the two local
authorities.
- Details of the assessments are contained in
document TRA/C/7. This does not explain how the
property acquisition costs and job losses have been
calculated, but indicates (table 6, page 12) that the
original 1995 scheme would be expected to involve
property costs in excess of £100m (including relocation
of the rail facilities), affecting 1630 jobs.
- The 4 other options examined in detail would
involve land costs in the range £24-£33 million, and
would affect between 1550 and 1930 jobs.
- The estimated engineering costs for the 1995 scheme
are approximately £0.6 million less than the current
scheme (excluding the cost of relocating the rail
depot).
- The 1995 scheme is estimated to cost about £74
million more than the Option 1 (the current scheme)
(engineering and land costs combined) while the other
options would cost £2.5-£9 million more than the option
1.
- Option 1 (the current scheme) would be expected to
affect 1838 jobs.
- The environmental assessment of the various options
(document TRA/F/4) covers the physical and community
impacts described in chapter 5 above (property
demolition, visual intrusion, noise, air quality,
effect on wildlife and green spaces, etc).
- The environmental assessment does not cover impact
on jobs or the local economy.
- The assessment concludes that the 1995 alignment is
preferable in noise and air quality terms, but performs
poorly in all other respects (partly because the
railway facilities would probably be relocated to the
south of the WCML, occupying additional open space land
closer to residential properties in north
Toryglen).
- Option 1 has slightly less impact than the other
alternative options, when impacts on people and
property are combined with effects on the natural
environment.
- All aspects of the current proposal for the
Polmadie area would comply with motorway design
standards for gradient and curvature, taking account of
the intended 50mph speed limit that will apply. There
is no basis to argue that the 1995 alignment would be
safer or more efficient than the current proposal.
- The cost of constructing the northern route has
been taken into account in the overall cost
assessments.
- If the 1995 alignment is retained, it would be
essential to replace the railway maintenance facilities
prior to vacating the existing depot. This is now
estimated to take at least 6 years, including allowance
for parliamentary processes.
9.59 On the basis of these various studies, the TRA has
concluded that the 1995 route would be considerably more
expensive than any of the alternative options, due to the
cost of relocating the railway facilities, while also being
more intrusive due to the relocation of the facilities
closer to the north Toryglen residential area on land that
forms open space/woodland habitat. The current proposed
scheme is preferred to the other alternatives because the
environmental assessment has shown that it would have the
best environmental performance; and because it would be
cheaper to build, though it would affect 200 more jobs than
the 1995 route and 100-300 more jobs than options 4a and 6.
For these reasons, the TRA has concluded that the current
option represents the best solution, taking into account
the factors assessed.
9.60 In relation to disturbance compensation, the
underlying principle is to put the affected parties in the
same financial position as if the property had not been
acquired. Although the onus for relocation lies solely with
the affected businesses, the TRA and the two local
authorities have agreed to provide additional voluntary
support to affected businesses. Both councils have set up
teams to provide business relocation assistance in liaison
with Scottish Enterprise (national, Glasgow, and
Lanarkshire), to form a centralised business location team
that will cover the whole corridor of the new motorway. The
team will have a budget of some £900,000 to assist in
feasibility studies, and will provide integrated advice on
all aspects of public sector business support and property
assistance. The team will have access to information on the
availability of alternative sites and premises.
Ingram Brothers (Glasgow) Ltd : Map 5 : Plot
103
Description and background
9.61 This plot extends to about 0.46ha, and is situated
to the east of Lawmoor Place and Lawmoor Avenue, forming
part of the Dixons Blazes Industrial estate. The site
comprises a two storey office building, a large single
storey shed for the production and storage of specialist
ingredients for the baking industry, and a yard with open
air storage.
9.62 The route of the motorway would pass directly over
plot 103, where the carriageway would be at grade, rising
to the east on an embankment, with adjoining slip roads, to
pass over Polmadie Road.
Summary of case for Ingram Brothers (Glasgow)
Ltd
9.63 Ingram Brothers has been established in Glasgow for
more than 100 years. It produces and supplies specialist
ingredients for the bakery industry in all parts of the UK.
The company moved from premises in Kinning Park to the
present site in 1987, since when more than £1.5 million has
been invested there. The company is one of the largest
employers in the area (approximately 40 employees).
9.64 The basis of the objection is that the need for the
M74 extension has not yet been established, and there is
therefore no need to acquire the site; and that even if the
need for the scheme is established, the acquisition of the
premises is not required. An adjustment to the line of the
route could be made which would avoid the need to acquire
the premises without prejudicing the scheme. The company
would be prepared to discuss voluntary acquisition, in
order to avoid uncertainty and to relocate the business to
a suitable site elsewhere in the city.
Summary of case for the acquiring authority
9.65 In response to the objection, it is stated for the
TRA that the need for the M74C scheme has been established,
in order to complete the trunk road network around Glasgow.
The proposed motorway would provide a new high quality
strategic link through Glasgow, and would offer an
alternative to the M8, which is often heavily congested. A
full and detailed design process has been undertaken,
including detailed studies in the Polmadie area, which have
shown that the acquisition of this site is necessary.
BOC Ltd : Map 5: Plot 107
Description and background
9.66 BOC Ltd occupies an extensive site (about 9ha) to
the west of Polmadie Road immediately north of the WCML.
The site is approximately square, extending northwards to
Kilbride Street, and west to the Ingram Brothers site (plot
103). Access is from Polmadie Road, where there is an
office block fronting onto the road. Most of the site is
used for open air storage of oxygen cylinders (full and
empty). There is also covered cylinder storage, facilities
for filling cylinders, administrative offices, and a large
hardstanding for vehicle movements.
9.67 The land that is proposed for compulsory
acquisition (approximately 4ha) forms a corridor some
100-150m wide extending east/west through the centre of the
BOC site, and an access strip that would run alongside the
railway line. The acquisition would take away the main
current operational area, including the office block. Parts
of the site would remain to the north and south of the
motorway. The portion to the south of the new motorway
would form a wedge between the motorway and the railway.
The access strip alongside the railway would give access to
this wedge, and to a building to the west that would remain
between the railway line and the new motorway.
Summary of case for BOC Ltd
9.68 In support of the objection, it is stated that the
company operates a major specialist LPG storage facility at
Polmadie Road. It was established in 1956, and is the
company's sole LPG depot in Scotland. The company is a
major player in the medical, leisure, and industrial gas
sectors in Scotland. Virtually all sectors of industry and
society need to use gases in one form or another, so that
BOC makes a fundamental contribution to Scotland as a
whole, and to the local economy. The Polmadie depot
distributes supplies to a network of 8 smaller BOC sites
throughout Scotland, and to 30 agents, as well as directly
to larger and regular customers. In all, BOC serves about
18,000 customers in Scotland. About 100 staff are employed
at the Polmadie site, in skilled and semi-skilled jobs.
9.69 The original route of the M74C through Polmadie
would have passed through the southern part of the site.
However the revised route severs the site, requiring the
demolition of all the principal office and operational
buildings, as well as taking up a significant proportion of
the external storage area. The company would be unable to
continue operations on the much reduced site, as the
remaining area would be insufficient to accommodate a bulk
LPG storage facility. Even if that were possible,
relocating the facilities on the northern part of the site
would bring them nearer to residential and education sites
to the north of Kilbride Street, requiring a new health and
safety assessment.
9.70 The company concludes that the entire BOC facility
will have to be relocated to an alternative site. No
potential sites of a suitable size and location have been
identified in the greater Glasgow area, and any new site
would have to meet HSE requirements. The company is aware
that the start of motorway construction work is now less
than 2 years away. It needs to evaluate options as a matter
of urgency, as it will take 2 years to find an appropriate
site, secure the necessary consents, and construct, fit
out, and commission the new facility. The company and their
agent have repeatedly sought clarification of the
compensation that would be payable, without which they
cannot fully evaluate the options. The absence of a
satisfactory response on the issue of whether Rule 5
Compensation would apply to BOC in this case is crucial to
the ability of the company to assess options.
9.71 The company recognises the benefits that the M74
extension would bring to individuals and businesses in the
Glasgow area, and does not oppose the principle of the new
road. The primary ground of objection is that the motorway
alignment should revert to the original route through the
railway site.
Summary of case for the acquiring authority
9.72 The TRA states that the alignment of the M74 scheme
in the vicinity of Polmadie has been subject to a thorough
appraisal against a number of criteria. The alignment
selected is the optimum, taking into account all the
factors assessed.
9.73 Disturbance compensation would be paid on the basis
of the Statutory Compensation Code, as assessed by the
Valuation Office Agency. Where only part of a property is
to be acquired, severance compensation would be assessed as
a separate matter. The TRA would wish to explore the
possibility of whether the LPG storage facility could be
retained on the remaining part of the current site.
Scotbeef Ltd : Map 5 : Plot 110
Description and background
9.74 Scotbeef occupies a site of some 0.4ha used for the
production and packaging of meat supplies. The site
comprises a large shed used for production and storage; a 2
storey office block; and a large vehicle yard. The land to
be acquired (843 square metres) is occupied by a single
storey extension of the adjacent two storey office
building.
Summary of case for Scotbeef Ltd
9.75 In support of the objection, it is stated for
Scotbeef Ltd that although the section of land to be
acquired is only part of the premises, the remaining
section would be too small to accommodate the company's
ongoing operations and business. The company has plans for
a major extension of their main production facility on the
site in response to customer demand. If it cannot be
carried out, Scotbeef is at risk of losing business and
existing contracts, with associated job losses. The
proposed CPO thus puts at risk the continued viability of
Scotbeef at this location. In addition, the proximity of
the new road would have a major detrimental effect on the
property.
9.76 Scotbeef Ltd note that the only reason that their
property would be affected by the M74C is because of the
proposed realignment of the Polmadie section of the
motorway (see above).
Summary of case for the acquiring authority
9.77 The TRA has explained why it wishes to build the
motorway along the northern alignment at Polmadie (see
above).
9.78 Disturbance compensation would be paid on the basis
of the Statutory Compensation Code, as assessed by the
Valuation Office Agency. The procedures being followed are
in line with the statutory provisions for a trunk road.
Draft orders for the construction of the new road were
promoted at the same time as the CPO, and were open to
objection. If the orders are confirmed, no further planning
procedures are required.
9.79 With regard to the proximity of the roadworks to
the Scotbeef property, the works would be carried out in
such a manner as to minimise any adverse effects. The
presence of the new road would not have any significant
impact on the Scotbeef operation.
9.80 The cost of construction along the revised route
has been taken into account in the comparison of
options.
9.81 The TRA notes that the acquisition of plot 110 is
required to accommodate a drainage detention pond. If
Scotbeef were to demonstrate that acquisition of this plot
would put the viability of the business at risk, it may be
possible to modify the design to allow the pond to be moved
slightly to the north (Reporters' note : this should be
south) to avoid impinging on the plot.
Mr & Mrs Philip C Smith; Philip C Smith
(Commercials) Ltd : Map 6 : Plots 119+121; Clearwater
DC Ltd : part of plot 119; Shanks Chemical Services :
part of plot 119 + plot 121.
Description and background
9.82 These contiguous plots are located to the north of
the Polmadie railway depot, taking access from Polmadie
Avenue. Philip C Smith (Commercials) Ltd are the owners of
plot 119, while Mr and Mrs Philip C Smith are owners of
plot 121. The total area of the two plots is about 1.8ha,
and total acquisition is proposed. Philip C Smith
(Commercials) Ltd are occupants of part of plot 121 (see
below).
9.83 Different parts of the land are occupied by Philip
C Smith (Commercials) Ltd, Clearwater DC Ltd, Shanks
Chemical Services (trading as Shanks Waste Solutions), and
Jobmaster Cleaning (Polmadie) Ltd (who are tenants but not
an objector).
9.84 A small part of plot 121 is occupied by Philip C
Smith (Commercials) Ltd for open air vehicle storage. At
the time of the formal accompanied site inspection during
the inquiry, these vehicles were mainly elderly and
dilapidated plant hire vehicles, such as drain cleaning and
refuse collection vehicles, forming part of a fleet of such
vehicles available for hire from Philip C Smith
(Commercials) Ltd.
9.85 Most of plot 121 and about one third of plot 119 is
occupied by Shanks Chemical Services for the receipt and
disposal of a variety of chemical waste products. The
facilities include open air and covered storage of chemical
products and wastes; some processing and repackaging
installations; and office premises for the administration
of the business. The central third of plot 119 is occupied
by Clearwater DC Ltd, who receive liquid wastes for
disposal. Some of these are cleaned up and put into a sewer
on the site, while others are despatched elsewhere for
specialist disposal. Finally, the western third of plot 119
is occupied by Jobmaster Cleaning (Polmadie) Ltd. This
comprises a large shed within which commercial vehicle
liquid tankers are cleaned out prior to re-use.
9.86 Apart from the disposal of liquid waste down the
sewer, all materials processed at these sites arrive and
depart by road. At the time of the site inspection, there
appeared to be little functional interaction between the
various businesses, although they are all involved in the
cleaning up and disposal of liquid wastes. But Jobmaster
Cleaning (Polmadie) Ltd could provide vehicle cleaning
services for road tankers and other vehicles that have
visited the other 3 sites.
Summaries of case for the objectors
9.87 The main points put forward in support of these
objections were :
- The acquisition of this land is not necessary to
carry out the scheme which was granted planning
permission in 1995, subsequently renewed in
2000/2001.
- Some of these objectors do not oppose the principle
of the new road, but the alignment should revert to the
1995 route.
- The deviation from the approved line now proposed,
which would pass through the objectors' land, was
adopted by the Scottish Executive and the local
authorities without any proper investigation,
discussion, or consideration, and is now regarded by
them as final. This was a secretive, improper, and
unlawful process.
- The decision was made prior to any consideration of
the activities carried on at the objectors' sites, and
the implications of seeking to relocate them, including
costs.
- There have been no discussions of these matters
between the TRA and these objectors, unlike other
objectors nearby. The TRA has acknowledged that it had
no knowledge of the activities at these sites when the
decision to re-route the motorway was made.
- There had been no TRA check on the valuation roll
to ascertain property interests.
- The Polmadie waste disposal sites, and their
activities, are not mentioned in the Environmental
Statement produced for the TRA, nor in any of the TRA
inquiry documents. These omissions have led to a flawed
conclusion in the ES, which cannot be remedied without
further investigation.
- The assessment of loss of jobs by the TRA is
inaccurate, being based on incomplete information.
- The valuation of the sites for the assessment of
options at Polmadie appears to have been based on
historical costs, which is taken to mean recorded
purchase prices.
- The assessment of the comparative costs of the
options is flawed, being based on incomplete
information.
- The uses at the sites are highly specialised, and
of major national environmental importance. They bring
together several licensed operators on the same site,
almost uniquely suitable for the purpose.
- The sites have Waste Management Licences and a
Discharge Consent from SEPA; and a Trade Effluent
Discharge Consent from WoSWA.
- The site has a direct pipeline to the Greengairs
waste disposal site. (Reporters' note : This could not
be confirmed during the site inspection, and appears to
be incorrect.)
- The specialist installations on the sites have cost
£4-5 million.
- The objectors estimate that the total cost of
relocating or replacing the existing facilities would
be in the order of £28 million, including land
purchase.
- There are only 2 other similar facilities in
Scotland : a small chemical facility in Paisley, and a
facility in Aberdeen dealing solely with oil industry
waste.
- It would not be in the national interest to attempt
to disperse these activities to different sites
elsewhere.
- It would be virtually impossible to find sites that
are as well located, and there would be considerable
difficulty and protest.
- Finding a suitable alternative site is inhibited by
limitations of sewerage capacity in North and South
Lanarkshire, and flooding problems in the east of
Glasgow. The west and south of Glasgow are areas of
dense residential development with limited industrial
opportunities.
- There would be a double negative environmental
impact, due to the closure of the present site and the
impact of the activities in the new location.
- Some international business would be lost.
- There would be a direct impact on some 68 jobs at
the site, having an adverse effect on the local
economy.
- Although the relocation of the rail facility might
delay the motorway project by up to 4-6 years, a
similar delay could result from the need to relocate
the waste disposal facilities, taking account of the
need to find a site; gain all the necessary consents;
and design, build, and commission the new
facilities.
- There should be full, proper, and open
consultation, investigation, discussion, and
consideration of these matters before any decision is
made.
- There are errors in the details of the description
of the extent of the various ownerships and
tenancies.
- The objectors believe that the 1995 route at
Polmadie should be preferred to the current proposal,
when all of the costs, environmental, and economic
implications of the two options are taken into
account.
Summary of case for the acquiring authority
9.88 The main points made by the TRA in response to
these objections are as follows :
- The TRA has explained the reasons why the northern
alignment is now preferred to the 1995 alignment
through the railway land (see paragraphs 9.58-9.59
above).
- Disturbance compensation will be payable on the
basis of the Statutory Compensation Code. The Valuation
Office Agency will consider each case on its
merits.
- Estimates of the total compensation that would be
payable for the proposed scheme and various local
alternative options were provided by the Valuation
Office Agency during 2002.
- As is usual in such cases, to avoid causing
concern, no contact was made with the potential
claimants. Instead, based on standard professional
practice, estimates were based on records held by the
agency and from other sources, but without inspections
of the land and property or information from the
businesses concerned.
- These estimates assumed that as most of the
businesses were manufacturers or wholesalers, that the
vast majority would relocate, and that disturbance
costs would include removal costs, loss or adaptation
of fittings, and temporary loss of profits.
- The underlying principle of compensation is that
affected parties should be in the same financial
position as if the property had not been acquired.
- It is up to the affected parties to use
compensation to locate and move to a suitable
alternative property. In addition, other funds such as
Regional Selective Assistance may be available to
assist with business relocation.
- The environmental impact of relocating displaced
businesses is not assessed at this stage, as this is an
issue for consideration once relocation sites have been
identified.
- SEPA has stated that the agency does not entirely
agree with the assertion that the activities undertaken
at these sites are of national importance. The
fundamental aspect of handling special waste is able to
be carried out at a number of alternative locations.
The agency notes that Clearwater DC Ltd has more
specialised infrastructure on its site, but there are
alternative firms who perform similar activities.
- The TRA acknowledges that there are potential
difficulties in attempting to relocate the waste
disposal activities currently carried on at the
Polmadie sites.
- The TRA and the local authorities and local
enterprise companies are working together to assist in
such relocations, including assistance in obtaining
permissions, consents, and licences. It is recognised
that this is a sensitive issue. However the TRA
considers that the potential difficulties do not
justify any change in the assessment of options, nor a
change in the decision to adopt the current
alignment.
H Morris & Co Ltd : Map 6 : Plots 123-124
and 210-213
Description and background
9.89 This company makes furniture in a factory complex
running parallel to and to the north of the Polmadie
railway depot. Access is from Rosyth Road (from the
northwest), which serves the main entrance, reception, and
administrative offices, as well as most of the production
buildings; and from Southcroft Road (from the east) which
provides a large manoeuvring area for HGV deliveries and
uplifts.
9.90 The 6 plots to be acquired total approximately 4
ha, largely forming a contiguous site which accommodates
virtually all of the production facilities, but excludes
some of the vehicle parking and manoeuvring area at the
Southcroft Road entrance. Plots 124 and 210 are very small
areas detached from this larger site. In addition, the
company occupies additional premises on the west side of
Rosyth Road.
Summary of case for H Morris and Co Ltd
9.91 In support of the objection, it is stated for the
company that it is a leading European furniture
manufacturer, with its manufacturing headquarters at Rosyth
Road. It employs some 500 staff at these premises in a
range of skilled and semi-skilled jobs offering
opportunities to a wide spectrum of the Glasgow population.
The company has a distribution fleet of some 70
vehicles.
9.92 The revised route for the M74C would wholly sever
the premises, requiring the demolition of a significant
portion of the main manufacturing facility, a 480,000
square foot elongated factory directly in the path of the
motorway. Detailed investigations have shown that it would
not be possible to re-route the motorway through the
premises or re-arrange the premises on the reduced site
without wholly unacceptable detriment to the business.
9.93 There is no ready supply of 500,000 square foot
manufacturing units of the type and specification required
for furniture production and distribution at this scale in
the Glasgow area. Following an extensive search, two
alternative sites in the area have been assessed, but the
cumulative costs of a complete relocation to either of the
sites were shown to be excessive and unviable. Thus no
viable options yet exist for relocating the enterprise
within the greater Glasgow area.
9.94 The motorway proposal thus raises a number of
significant economic considerations. It threatens the
headquarters and production facilities of a major
specialist manufacturing business, having a devastating
effect. This outweighs any advantage of the revised
route.
9.95 The company considers that insufficient
justification has been given to support the decision to
divert the motorway route to the north of the railway land
(see paragraphs 9.57-9.59 above).
Summary of case for the acquiring authority
9.96 The TRA has explained the reasons why the northern
alignment is now preferred to the 1995 alignment through
the railway land (see paragraphs 9.58-9.59 above).
Disturbance compensation will be payable on the basis of
the Statutory Compensation Code. The Valuation Office
Agency will consider each case on its merits. Where only
part of a property is included in the compulsory purchase
order, severance compensation may be payable. Again each
case is considered on its merits.
[note : this ends the section on the Polmadie
diversion]
Millside Properties Limited/McConechy's Tyre Service
Limited : Map 9 : Plot 164
Description and background
9.97 This plot, extending to 2,360m
2, is part of Unit 7B, Farmeloan Industrial
Estate, Rutherglen, which lies to the rear of Rutherglen
railway station. It is currently occupied by a large
asbestos shed and car parking. The plot is on the line of
the M74C, forming part of the east embankment of the
elevated structure over the railway station.
Summary of case for the objector
9.98 The objection is that the CPO will result in the
closure of the business and the need for relocation.
Summary of case for the acquiring authority
9.99 In response to the objection, it is stated for the
TRA that the need for the M74C has been established, in
order to complete the trunk road network across Glasgow.
The proposed motorway would provide a new high quality
strategic link through Glasgow, and would offer an
alternative to the M8, which is often heavily
congested.
James Boyle : Map 10 : Plot 179
Description and background
9.100 This plot, extending to 3,286m
2, was the site of the houses known as and
forming 2/4 Gray Street and 134/136 Cambuslang Road,
Rutherglen, owned by SLC and now demolished. It lies close
to the Cambuslang Road interchange and is affected by the
connecting roads to the M74C which crosses Cambuslang Road
at this point by a bridge.
Summary of case for Mr Boyle
9.101 The objection relates to issues of compensation,
re-housing, and related matters.
Summary of case for the acquiring authority
9.102 The issues raised by the objector do not
constitute a competent objection to the CPO.
MRC Pension Trust Limited : Map 10 : Plots
184-189, 191, & 220
Description and background
9.103 The eight plots relate to areas of ground forming
part of the Clyde Industrial Estate, Rutherglen, which are
required to facilitate the construction of the M74C on ramp
south at the Cambuslang Road Interchange and an alternative
access to the estate using Duchess Place and Cunninghame
Road, Rutherglen. Plot 184, extending to 272m
2, is part of an open area of car park, fronting
a private lane. This land is understood to be required for
the formation of a hammerhead adjacent to the private lane.
Plots 185 and 186, extending to 61m
2 and 342m
2 respectively, are contiguous immediately to
the south of plot 184 and relate to servitude rights of
access over the same car park for the construction of a
turning area, for installation and maintenance of drainage
apparatus, and for access in connection with the M74C
construction. Plot 187, extending to 1,312m
2, is part of the same car park and lies
immediately south of plot 186 on the line of the on ramp,
while plot 188, extending to 1,339m
2, is part of the
solum of Cunninghame Road, again on the line of
the on ramp. Plot 189 relates to a servitude right over 19m
2 of land lying to the east of Cunninghame Road
to lay down and maintain drainage apparatus. Plot 191,
extending to 13,960m
2, is part of the former Clydebridge Steel
Works, Rutherglen, to the north east of Cambuslang Road.
Again, it is on the line of the M74C. Plot 220, extending
to 225m
2, is part of the
solum of Cunninghame Road required to link
Cunninghame Road and Duchess Place to Cambuslang Road, some
125m west of the on ramp.
Summary of case for MRC Pension Trust Limited
9.104 The objection is in the following terms: -
" 1. The Order, if confirmed, would result in the loss
to our client of a substantial part of its land holding at
Clyde Industrial Estate, Rutherglen.
2. The Order, if confirmed, would disrupt the
operation of our client's business at Clyde Industrial
Estate aforesaid.
3. Insufficient detail has been provided in the
draft Order and on the Map (as defined in the draft Order)
to enable our client to ascertain the full extent of the
proposals."
9.105 The objector owns the Clyde Industrial Estate
("the Estate") which lies between Cambuslang Road on the
south west and the River Clyde on the north west. Access to
the Estate is gained from Cambuslang Road and Cunninghame
Road. The TRA proposes to stop up Cunninghame Road and to
provide an alternative access via the Cambuslang
Road/Duchess Place junction, some 300m to the west of the
Cambuslang Road /Cunninghame Road junction. The current
access to the M74 from the Estate is 800m south eastwards
along Cambuslang Road, turning left into Bogleshole Road
from where, by using Cambuslang Road, Cambuslang and 3
roundabouts, Fullarton Road junction is approximately 1.6km
distant.
9.106 In amplification of the objection, the Estate
currently houses 3 industrial buildings sub-divided into
units, the anchor tenant being Business Post, a freight
oriented organisation. The Estate also contains 2 vacant
plots. In September 2003, planning permission was granted
for the erection of a distribution warehouse (Class 6),
ancillary offices, and car parking on part of the southern
plot, the prospective occupant of the 1,475m unit being
Business Post and the intention being that access would
continue to be taken from Cambuslang Road via Cunninghame
Road. Business Post and a similar company, Scotmail, occupy
the largest unit on the Estate which has a large yard
between it and Cambuslang Road, a considerable area of
which is to be compulsorily acquired for the M74C.
9.107 Considerable importance is placed by the objector
on the recent history of the Estate and the proposed
motorway, reference being made to the 1995 motorway
proposal for which planning permission was granted for a
scheme which included a virtually identical junction
arrangement at Cambuslang Road as that now being proposed
and the grant to the then owner of the Estate, on appeal
against non-determination in 1997, of outline planning
permission for a direct connection between the Estate and
that junction. A subsequent application to renew this
permission, which SLC was minded to grant, was called in
and dismissed by Scottish Ministers in 2002.
9.108 Notwithstanding the objection lodged to the CPO,
the objector in July 2003 forwarded to the TRA a proposal
entitled "Indicative Grounds for Objection &
Alternative Proposals" (Production MRC 18) and a meeting
took place the following month, although no agreement was
reached. This was confirmed by letter of 9 September 2003
from the TRA (Production MRC 19), the reasons being severe
engineering difficulties and road safety concerns. The
objector's agent, who had been present at the meeting,
understood that the TRA nonetheless gave a commitment at
the meeting to consider a roundabout arrangement.
9.109 The objector supports the principle of the M74C
and a junction at Cambuslang Road. The objection is to the
stopping up of Cunninghame Road and the closure of its
junction with Cambuslang Road. The proposed alternative
access via Duchess Place is tortuous and involves
additional mileage. It involves passing through the
neighbouring Farme Castle Industrial Estate and using roads
that have no parking restrictions and are unsuitable for
the passage of HGVs. A mobile snack bar currently sits in
Duchess Place and is understood to have the benefit of
planning permission. The TRA alternative requires the
acquisition of land, the construction of 230m of an
alternative access road, and considerable additional cost
when compared to a more direct access from Cambuslang
Road.
9.110 The objector provides a comprehensive review of
the development plan to conclude that its proposed access
accords with that plan. It is not accepted that it
technically contravenes policies TRA1 and 8 of the local
plan. Furthermore, the proposed access is supported by
SPP1, SPP2, NPPG17, its Addendum (SPP17), PAN66, and SEL
document "Changing Gear Towards 2010". The TRA has failed
to meet its responsibilities under PAN58 in that it has not
properly assessed the objector's alternative access
proposal.
9.111 In the absence of further information from the
TRA, the objector engaged a traffic consultant in October
2003 to review traffic flow data at the Cambuslang junction
with a view to preparing a proposal providing for the
retention of an access to the Estate from Cambuslang Road.
A request was made to the TRA for the traffic flow
information it had used. The output data for a traffic
prediction model for the design years 2010 and 2020 was
supplied by e-mail towards the end of October 2003. There
was no information however on the Duchess Place/Cambuslang
Road junction. Based on the incomplete information which
was still being worked on to build a computer based TRANSYT
model of the TRA's proposal, the consultant prepared a
preliminary report on the traffic aspects of the junction,
outlining 2 possible options (options 1 and 2) for
retaining access (Production MRC 01 - October 2003). The
consultant then used the TRANSYT model to compare his
alternative proposals with that of the TRA. On 10 December
2003, the TRA, on its own initiative and at its own
expense, had a traffic survey of the junction conducted by
survey contractors Count on Us. The results of the survey
were sent to the objector in early January and copies were
made available to the consultant within a day or two later.
The consultant then required to re-work his model on the
updated information and prepare a fresh report that was
made available in mid February 2004 (Production MRC 01 -
February 2004). This effectively became the traffic
consultant's precognition for the inquiry, the official
precognition of October 2003 having largely been overtaken
by events. At the inquiry, it became apparent that the
objector had been unaware of further traffic survey
information obtained by the TRA for a Road Safety Audit of
its proposal, a pre-requisite in terms of the DMRB before
promoting the Orders.
9.112 The December 2003 actual count data was
extrapolated to the design year 2020 using the national
road traffic high growth forecast, and the results compared
with the side road traffic flows using the earlier data.
The comparison highlighted major differences, with the
earlier data showing 471 vehicles entering Duchess Place in
the morning peak hour and 460 leaving in the evening peak
hour. In contrast, analysis of the actual count data
produced corresponding figures of 246 and 241 vehicles. For
this reason, the TRA proposal was tested against Transyt
model analysis of both sets of data. The objectors
indicative options 1 and 2 of October 2003 were found to be
virtually identical in terms of Transyt network
specification and only one test was carried out to cover
the 2 options. For modelling purposes, the assumption was
made that there would be a pedestrian crossing cycle at
every second traffic signal cycle at the junction. The
signalling system would be phased so that all lights were
red at the one time, eliminating the need for button
controlled crossings. There was little pedestrian traffic
at the junction in any event. No account was taken of the
possible expansion of business on the Estate. The results
indicated that the objector's proposed access would work as
well or marginally better than the TRA proposal, with the
performance index being better in all cases under the
objector's arrangement. On further study of the 2 options,
a variation of option 1 (option 1A) emerged as the better
option because of constructional and operational
difficulties associated with differences in ground level
and the steep gradient needed to access the Estate. The
total volume of traffic using either Duchess Place or the
objector's access remains the same, the only difference
being the access point. No increase in traffic delay should
result from the objector's access, which can be developed
in accordance with the DMRB.
9.113 At the inquiry, it was accepted that option 1A as
set out in Appendix 12 of Production MRC01 (February 2004),
involved the acquisition of a lane and commercial premises
fronting it from a third party who was himself an objector
to the CPO in respect of another plot and that the
commercial premises were the subject of a number of
tenancies. This would require a fresh CPO and entail
further delay. Option 1A was no more tortuous than the TRA
alternative. It was not accepted that the introduction of
the objector's access at an already busy junction would
give rise to safety implications, making it more complex
and confusing for motorists. Appropriate map signage would
warn motorists of the access into the Estate and in all
likelihood there would be a similar arrangement at Duchess
Place with the TRA scheme. It was not accepted that
motorists following traffic entering the objector's access
would assume that the signal from the vehicle in front
showed the intention to use the east bound on ramp, giving
rise to the risk of collision or sharp braking movements.
Again, there was no difference in this respect between the
objector's access and Duchess Place. The objector
maintained that all the options were merely indicative and
that an option 1B, not involving additional land take,
could possibly be achieved. The objector did not accept
that a fully worked up option 1B should have been produced
for the inquiry. The objector's responsibility was simply
to provide an alternative engineering solution, which had
been done. Traffic from the west using the objector's
access (option 1A) would require to travel a safe and
convenient distance down the lane, possibly some 25/40m,
before taking a 90 degree right turn into the objector's
storage yard, proceeding across the yard, and taking
another 90 degree left turn into Cunninghame Road. This
would entail the use of land currently allocated for
industrial use. It was accepted that, while the maximum
additional travel distance under the TRA scheme would be
750m, the average would be in the region of 140m.
Summary of case for the acquiring authority
9.114 On behalf of the TRA, it was submitted that, prior
to the promotion of the CPO and Roads Orders, an outline
design, in sufficient detail to determine the minimum land
requirement for the M74C had been prepared, which
established the need for the land which the TRA seeks to
acquire from the objector. Compensation will be paid in
accordance with statute and the issue of compensation
itself is not a valid ground of objection to the CPO. The
TRA has met with the objector's agent but no evidence has
been produced to show that a direct access to the Estate
from Cambuslang Road is possible. The report on the
called-in application of 2002 (Production TRA/A/15) is of
critical significance. As regards the meeting with the
objector's agent in September 2003, it is strongly denied
that the TRA gave a commitment to consider a roundabout
option. This option had been examined and ruled out before.
Furthermore, the letter of 9 September 2003 from the TRA
(Production MRC18) sets out at some length and in some
detail what was discussed at that meeting and does not
record the commitment claimed. There was no challenge to
the terms of the letter at the time. The objector's
proposal - option 1A - is entirely different to what the
objector had previously proposed. The proposal now is to
take an access via the privately owned lane and no longer
from the slip road, an apparent acceptance of the
impracticality of the original proposal.
9.115 Option 1A as now proposed would require a further
CPO, a new Roads Order and would cause uncertainty and
delay. The owner of the lane and the commercial premises
fronting it (Mr Millen) is himself an objector to the CPO
in respect of plot 221. Negotiations are underway with Mr
Millen in regard to accommodation works, which hopefully
will see the closures of both the lane at its junction with
Cambuslang Road and the pend lane a few metres to the west
of the lane, with alternative access from the rear using
the new road proposed by the TRA to access the Estate. Mr
Millen is understood to favour Option 2 on drawing
474000/Sk135 of Production TRA/C/14, which would be wholly
incompatible with option 1A. The objector's proposed access
would be unlikely to find favour with the various tenants
of Mr Millen's commercial premises. The lane itself is
sub-standard being narrow and having a poor surface, lacks
footpaths, and is unsuitable for HGVs. Option 1A adds
another junction to an already busy and complex junction.
The number of junctions should be minimised to avoid
confusing drivers. This view is supported by the DMRB which
highlights the danger of indecision on the part of drivers.
It is important to ensure correct motorway signage and the
map signage proposed by the objector could simply add to
driver confusion. Map signage at Duchess Place would be
300m away from the Cambuslang interchange. Further
criticisms of option 1A include east bound traffic on
Cambuslang Road not being opposed by traffic lights and
west bound traffic from Rutherglen/Cambuslang seeking to
access the east bound on ramp having to cross over the path
of east bound traffic. The proposed stop lines are not
considered effective. The TRA alternative access
arrangement has been the subject of a road safety audit.
The same cannot be said of the objector's alternative. The
new access proposed by the TRA is shown in Production
TRA/C/14 with traffic lights at the Duchess Place junction
linked to the traffic signals at the M74/Cambuslang Road
junction. The proximity of the Cambuslang Road junction
will greatly enhance accessibility to the Estate. While the
average additional travel distance is of the order of 140m,
delays at junctions could represent more of a problem to
road users. As regards the mobile snack bar in Duchess
Place, information from SLC indicates that there is no
planning permission for this use but that a street trader's
licence exists. While SLC has responsibility for traffic
regulation on adopted streets such as Duchess Place, there
is no reason to believe that SLC, as a project partner,
would not exercise its powers to control parking should a
problem arise.
9.116 As regards the traffic flow data, the TRA supplied
the objector's traffic expert with all the information
requested. The DMRB requires a Road Safety Audit with
traffic flow data and the expert would have been aware of
this requirement.
9.117 The TRA used higher growth figures to create a
worst case scenario in order to prove that the alternative
access arrangement, particularly at the Duchess
Place/Cambuslang Road junction, would work satisfactorily
and to take account of future development of both the
Estate and Farme Cross Estate. The Performance Index
/Saturation Flows in excess of 90% as shown in Appendices 7
and 8 of Production MRC01 (February 2004 version) are not
accepted, based on detailed analysis undertaken by the TRA
over many years. Option 1A has not been tested using the
TRA high growth forecasts.
Somerville & Morrison Limited : Map 10 :
Plot 178
Description and background
9.118 This plot, extending to 4,263m
2, is part of the property known as and forming
130 Cambuslang Road, Rutherglen. It lies to the south west
of Cambuslang Road, adjacent to Rutherglen rail depot and
takes its access directly from Cambuslang Road through land
belonging to the objector but not included in the CPO. The
plot contains a number of dilapidated buildings still in
use as a paper processing business. The office and car park
of the business are outwith the plot.
Summary of case for Somerville & Morrison
Limited
9.119 The objection is that, without adjusting the land
take or agreeing an exchange of land, the objector's
specialist protective paper processing business - the only
one of its kind in Scotland - will be lost. This family
business, established in 1873, has a substantial order
book, particularly in the export market, and has 21
employees.
Summary of case for the acquiring authority
9.120 In response to the objection, it is stated for the
TRA that the need for the M74C has been established, in
order to complete the trunk road network across Glasgow.
The proposed motorway would provide a new high quality
strategic link through Glasgow, and would offer an
alternative to the M8, which is often heavily congested.
There are ongoing discussions with the objector in an
effort to reach agreement.
Mr B Millen : Map 10 : Plot 221
Description and background
9.121 This plot, extending to 20m
2, is an area of land forming the entrance to a
private lane fronting Cambuslang Road, Rutherglen. The lane
serves a number of commercial properties owned by the
objector. The plot lies at the start of the on ramp to the
M74C south at the Cambuslang Road interchange.
Summary of case for Mr B Millen
9.122 The objection is based on the M74C effectively
cutting off the objector's existing accesses from
Cambuslang Road to his properties on the west side of the
private lane he owns and to the pend through other property
belonging to him fronting Cambuslang Road. The proposed
traffic lights at the junction adjacent to his property
will mean that traffic from the east would no longer be
able to turn right into the pend, while traffic from the
west would likely to be hindered by traffic queues at the
lights and the tight space available for turning into the
pend. The objector's premises are currently let to a number
of tenants. Access from the Cambuslang Road frontage to the
premises at the rear will no longer be possible, access
having to be taken from Duchess Place. Additional costs are
anticipated. In the last 18 months, 7 tenants have vacated
these premises due to the derelict and vacant nature of the
surrounding area attributable to the prospect of the M74C.
This has resulted in a significant loss of revenue, a
situation that is likely to continue through the
construction period. The objector is also unclear as to any
obligations he may have in respect of the proposed
hammerhead on the other side of the lane close to its
junction with Cambuslang Road.
9.123 In a supplementary submission to the response from
the TRA, the objector suggests that the TRA has
misunderstood his objection to some extent. His concern is
that traffic moving towards the Cambuslang junction from
the city may back up at the traffic lights, restricting
access to the pend for vehicles approaching from either
direction wishing to enter his land via the pend. A meeting
with the TRA to discuss the objection took place in August
2003, as a result of which the objector was provided with
drawings of 3 possible solutions. Only the second solution,
namely, drawing 474000/Sk135, showing access from his
private lane through a building to be demolished, would be
acceptable to him.
Summary of case for the acquiring authority
9.124 In response to the objection, it is stated for the
TRA that the need for the M74C has been established, in
order to complete the trunk road network across Glasgow.
The proposed motorway would provide a new high quality
strategic link through Glasgow, and would offer an
alternative to the M8, which is often heavily congested.
There are ongoing discussions with the objector in an
effort to reach agreement. Plans of possible solutions have
been supplied to the objector and the TRA is confident that
an acceptable arrangement can be agreed. The TRA does not
intend to purchase any of the adjacent commercial
properties.
Corus plc : Maps 10 and 11 : Plots
193-195
Description and background
9.125 These plots are contiguous and are situated in the
grounds of the Clydebridge Steel Works, Rutherglen, lying
to the north east of Cambuslang Road, Rutherglen and to the
south west of the River Clyde. While the steel works
remains in operation, the surrounding land including the
plots is vacant semi-derelict scrubland. Plot 193 extends
to 9,884m
2, while plot 194 extends to 71,616m
2. Both plots are on the line of the M74C which
would run on an embankment. Plot 195 is a rectangular area
of ground extending to 467m
2 over which a servitude right for drainage to
the River Clyde is sought.
Summary of case for Corus plc
9.126 The objection is based on the extensive amount of
land being acquired and severance of existing operational
and potential development areas, including the main access
and a number of internal roads integral to the operation of
the Clydebridge Works. The operation of the works will be
severely disrupted with a large area to the north of the
M74C being severed. If the M74C goes ahead, it will be
essential to maintain a minimum ground clearance of 3m from
the existing main access at Ballochmill Road up to the
western edge of the works plant at the very least, and the
objector would wish to be advised if the M74C is to come
closer than 40m from the works. A further requirement would
be the retention of a continuous access from Ballochmill
Road for HGVs and other vehicles, including access to the
weighbridge, which may require to be relocated. Again,
continuous access will be required to the land to the north
of the M74C, in particular to the electricity sub-station
and outfall pipe to the Clyde, which too may require to be
relocated.
Summary of case for the acquiring authority
9.127 In response to the objection, it is stated for the
TRA that the need for the M74C has been established, in
order to complete the trunk road network across Glasgow.
The proposed motorway would provide a new high quality
strategic link through Glasgow, and would offer an
alternative to the M8, which is often heavily congested.
There are ongoing discussions with the objector in an
effort to reach agreement.
Hillview Developments Limited : Map 12 : Plot
198
Description and background
9.128 This plot, extending to 10,472m
2, is an area of open land to the north east of
the River Clyde, forming part of the Cambuslang Investment
Park. It lies south west of London Road and to the west of
Fullarton Road. The plot is close to the Fullarton Road
junction and is on the line of the M74C and associated side
roads.
Summary of case for Hillview Developments
Limited
9.129 The objection is that the route of the M74C
dissects the objector's land holding in such a way as to
have a detrimental environmental impact.
Summary of case for the acquiring authority
9.130 In response to the objection, it is stated for the
TRA that the need for the M74C has been established, in
order to complete the trunk road network across Glasgow.
The proposed motorway would provide a new high quality
strategic link through Glasgow, and would offer an
alternative to the M8, which is often heavily
congested.
H Meanen (Electrical Services) Ltd : Map 14 :
Plot 207
9.131 This company occupies premises at the convergence
of Polmadie Road and Aikenhead Road, some 800m to the south
of the motorway route. At present, this junction is blocked
off to give a free flow of traffic along Aikenhead Road.
Under the M74 proposals, the junction would be reconfigured
to open up Polmadie Road as the main route to and from the
motorway junction. Aikenhead Road would then meet Polmadie
Road at a T junction. This rearrangement requires the
acquisition of a small (90 sq m) triangle of land from the
objector. This is currently open land forming part of the
property, not affecting the building itself.
Summary of case for H Meanen (Electrical Services)
Ltd
9.132 In support of the objection, it is stated that the
firm employs 8 people at the site involved in electrical
contracting work throughout west central Scotland. The
business is dependent on the use of 4 vans and two cars,
which are parked, unloaded, and loaded in the stopped up
part of Polmadie Road. Expansion of the firm would require
further vehicles.
9.133 If this section of Polmadie Road is re-opened, it
can no longer be used as it is at present. This would have
a very serious impact on the operation of the business, and
preclude expansion. This also applies to various
neighbouring businesses.
9.134 The TRA has proposed using part of the land owned
by the company and off the new highway for some vehicle
parking. This would provide 3 parking spaces. However this
would be insufficient for the operational needs of the
business. The solution is to have assistance to relocate
the business to a site where adequate parking would be
available.
Summary of case for the acquiring authority
9.135 The TRA has offered to provide a turning head
within the objector's site so that vehicles can turn round
before leaving. There should be no difficulty entering
Polmadie Road as the traffic flow will be regulated by new
traffic lights nearby.
« Previous | Contents | Next »