« Previous | Contents | Next »
Listen
ROADS (SCOTLAND) ACT 1984; ACQUISITION
OF LAND (AUTHORISATION PROCEDURE)(SCOTLAND) ACT 1947
M74 SPECIAL ROAD (FULLARTON ROAD TO WEST OF KINGSTON
BRIDGE) ORDERS
REPORT OF PUBLIC LOCAL INQUIRY INTO OBJECTIONS
VOLUME 1 : MAIN REPORT
CHAPTER 7 : GEO-TECHNICAL, MINING &
CONTAMINATED LAND
The Approach
7.1 The TRA evidence was based on a Ground Investigation
(the GI) involving a number of consultants and liaison
throughout with the design team on the planning and design
of both the investigation and the emerging detailed design
and route of the M74C. The details of the GI and the
results are contained in chapter 7 and Technical Annex C of
the ES (TRA/F/1) and Productions TRA/I/1 - TRA/I/4. The GI
is an ongoing process.
7.2 The GI itself was based on desk top studies
reviewing all available information, the study on
contamination and mitigation measures culminating in the
production of an Inception Report (TRA/I/1), indicating the
results of the research and the areas where further site
investigations would be necessary. For the purposes of the
GI, the route was divided into 5 sections, with a further
29 discrete sub-area sites identified as major historical
industrial land use sites, where contamination might be
expected. As regards geology, widespread areas of thick
deposits of alluvial soils and shallow mine workings were
noted, along with some local areas of deep fill deposits.
The exact position and condition of mineshafts required to
be determined. Following these preliminary studies, a
contract for the GI was drawn up and let.
7.3 The main GI, which was undertaken between August and
December 2002, included 304 light cable percussive
boreholes (including 36 rotary cored holes), 250 trial
pits, 58 static cone penetration tests, and 24 window
sample holes. A number of groundwater sampling points and
62 trial trenches were included, along with a considerable
number of
in situ tests.
7.4 Analyses carried out by specialist personnel
assessed the impact of the ground conditions along the
route, including the potential risk of collapse to
mineshafts and mine workings and the impact of such
failures on the surface. Assessments of the settlement
characteristics of the fill and alluvial soils under
varying load conditions of embankments were made, and the
analyses helped to formulate recommendations for the design
and construction of the road.
Geo-technical & Mining Issues
7.5 The general geological findings of the
investigations showed that the proposed route was along a
line largely within the Clyde basin. Fill deposits were
widespread and generally less than 5m thick, except for
deeper wastes in former clay pits, followed by alluvium.
These thick alluvial deposits (mostly over 20m) generally
consisted of clays, silts and sands, often laminated and
inter-bedded and generally grading coarser with depth. The
alluvium was followed in places by glacial till, or
rockhead, at depths ranging generally between 20 - 40m.
Three separate groundwater systems were identified. While
artesian conditions were known to exist in the Cambuslang
area, the investigations found this not to be the case at
the route location in that area.
7.6 Shallow mine workings were identified at several
locations along the route, specifically at Gushetfaulds
(chainage 1,580) to Dixon Blazes (chainage 3,500) and West
Clyde Approach (chainage 6,700) to Fullarton Interchange
(chainage 7,780). The workings were found to include the
stoop and room and longwall methods of mining. Potential
instability was identified at several locations along the
route.
7.7 The fill was found to be mainly of general
composition, except for the locations of back filled clay
pits around the Rutherglen area, where chromium waste was
found, and at the former Clydebridge Steelworks, where
paper pulp waste and some slag material were
encountered.
7.8 The concept design was for the road to be retained
at an elevated level to aid crossings and maintain the
route above contaminated ground. This necessitated the
incorporation of several embankments and viaducts. For
areas where high embankments were indicated, considerations
of settlement under the imposed loading of substantial soil
cover were required.
7.9 Construction techniques considered included
pre-loading and surcharging of the embankment footprint,
the use of lightweight fills, stage construction,
accelerated settlement techniques incorporating soil
drainage, basal reinforcement to the embankments, and
piling. All structures would require piling. Foundation
options for embankments and structures were based on
minimum disturbance to contamination. Piled embankments
were recommended at 5 locations, particularly in the areas
of deep wastes. Elsewhere, basal reinforced embankments
were recommended..
7.10 Grouting was recommended for sections of the route
underlain by shallow mine workings with a potential for
some collapse and surface subsidence. This would involve
drilling into the mine workings and using the drilled holes
to insert a cement grout for infilling. Several mineshafts
in sections of the route were recommended for grouting and
capping. Approximately 1.7 million cubic metres of fill may
be required for the construction of embankments. Possible
sources of the fill material were suggested.
7.11 As regards costs, earthworks were estimated at £30
million, piling at £13.5 million, and stabilisation works
at £8.3 million. There was nothing abnormal or exceptional
in either the works or costs anticipated, the works being
standard and conventional activities associated with a road
project.
Ground contamination
7.12 The contamination studies, recorded in the
documents described above, followed the guidance in the
DMRB and PAN33 (TRA/I/1).
7.13 Historical maps and photographs indicate extensive
tracts of the proposed route were previously occupied by
heavy industry, including iron and steel, chemical and
paper manufacturing, collieries and clay pits, and
associated railway land, giving the potential for
significant land and groundwater contamination.
7.14 Current ground conditions typically comprise a
universal layer of made ground of varying but substantial
thickness, overlying the alluvial infill of the Clyde
valley. Groundwater is present within each strata type, but
the vertical movement between different strata is limited.
Shallow groundwater flow directions are generally
controlled by topography and the location of the nearest
surface watercourses. The GI included sampling of soils and
groundwater from boreholes and trial pits in over 500
locations, as well as the sampling of surface waters and
soil gases. Monitoring wells were installed at 261
locations to allow continued monitoring of groundwater and
soil gas.
7.15 Relevant contaminated land legislation includes the
Control of Pollution Act 1974, the Environmental Protection
Act 1990, and the Environment Act 1995, including Part 11A
and subsequent regulations, planning legislation, and the
Health and Safety at Work Act 1974. Key future legislative
drivers include the Water Framework Directive and the
Environmental Liabilities Directive. Contamination and
pollution identified along the route do not fall within any
single aspect of the legislative framework. Most of the
contamination is defined as "historical" in that the
primary cause of the contamination happened in the past. A
key feature of the new contaminated land regime and
guidance is that the land should be "suitable for its
current use". Changes of land use trigger controls through
the planning process to ensure that the change of use will
not lead to environmental damage. Where a development is
subject to planning permission, the planning legislation is
primary and the Part 11A secondary. Where land is not
subject to planning controls, the default position is Part
11A. This is the situation for the M74C. Local authorities
are the primary regulators for both planning and the new
contaminated land regime, and liaison with the relevant
local authorities is ongoing. The contaminated nature of
the route means that compliance with the provisions of the
Health and Safety at Work and Control of Pollution Acts
will place significant constraints on construction work
procedures.
7.16 Assessment of contamination within the corridor
conformed to established current best practice, using a
risk based approach on a site by site basis. Data for each
site was gathered from documented information and used to
create a conceptual model covering the entire route. The
risk assessment approach involved identification of
hazards, receptors and pathways (between hazards and
receptors) for each site to determine significant pollution
linkages that may result in measurable impacts on specified
receptors. Possible linkages were identified, enabling
impacts in terms of both likelihood and magnitude to be
predicted. SEPA, the relevant departments of GCC and SLC,
and the design team were consulted throughout.
7.17 Contaminants of concern identified included
chromium waste, paper manufacturing sludge, steelworks
slag, combustion residues, and made ground arising from
general re-grading of previous development. Areas of
chromium waste, chemical waste, and slag tend to exhibit
the highest levels of contamination. Other sources of
contamination include surface spills and fly tipped waste.
Asbestos was reported at the majority of sub-area sites
along the route. Chromium waste was identified on that
section of the route from Dixon Blazes Industrial Estate
through Rutherglen and Cambuslang.
7.18 The receptors at significant risk were identified
as: -
- Local residents and construction workers in the
route corridor.
- Local surface waters and the River Clyde at
site drainage discharge points.
- Road structures constructed in highly
contaminated made ground or groundwater.
- Maintenance personnel excavating retained
highly contaminated made ground or below
groundwater level.
- Shallow groundwater in direct contact with
highly contaminated made ground.
- Surface water courses that intercept highly
contaminated made ground or groundwater.
- New planting.
- Road structures constructed within highly
contaminated made ground or groundwater, especially
active drainage routes.
7.19 The remedial approach to the contamination was one
of integration and iteration, the effects of the
contamination being incorporated into the design process
and resolved to the point where no unacceptable impacts are
anticipated. The strategy adopted involved above ground
construction wherever possible to minimise disturbance of
contaminated materials, identification of regulatory
constraints, adoption of compatible remedial solutions, and
a review of all aspects of road design from a contamination
viewpoint to allow for modifications as appropriate.
7.20 Final remedial options for the M74C, in general
terms, include selective removal of discrete sources of
contamination; prevention of any direct contact with
contaminated soils by way of placement of engineered
structures across the entire route corridor; restriction of
infiltration of water into contaminated soils beneath the
route;
in situ treatment of contaminated soil and
groundwater where contaminated soils are to be
significantly disturbed by the construction process;
interception of contaminated water by in situ treatment
facilities, where contaminated made ground is present below
normal groundwater levels; engineered protection of
culverted surface waters; specification of appropriate
building materials; and protection of buried services. In
addition, the whole construction and operation of the road
will be subject to an Environmental Management System
(EMS), acting as the primary mechanism for delivering the
required protection of construction and maintenance workers
and the public. Contract conditions will regulate hours of
working on the various activities in both the construction
and operational phases, thereby minimising the impact on
residential amenity.
7.21 Remedial options include well established and
proven techniques. While the approach does not remove
contamination, it does offer positive benefits such as
minimal disturbance of contaminated materials and
compatibility with the road structure and construction
process. Removal can pose greater risks than bunding of
contaminants. Unfortunately, bio-remediation cannot deal
with the concentrated inorganic based contamination that is
prevalent along the route. As regards the retention or
disturbance of chromium waste residues, the affected areas
have been identified and procedures developed to manage
contact with the contaminated materials and prevent
hazardous releases, both during construction and when the
road is operational. In some areas, exposure of
contamination will be necessary to allow adequate treatment
to take place, but most of the road will be built without
disturbing the existing contaminated material.
7.22 The M74C can be constructed in a manner that will
manage the contamination impacts throughout the
construction period, and planned remediation measures will
mitigate long term environmental risk. Without the M74C,
much of the route and adjacent sites are likely to remain
in their present contaminated condition.
The Case for JAM74/FOE
7.23 No counter evidence was led by JAM74/FOE on
geo-technical, mining and contamination issues and there
was no cross-examination of the TRA geo-technical and
mining witness. The contamination evidence, however, was
the subject of extensive cross-examination, particularly in
relation to the extent and nature of the contamination, the
proposal to bury much of the contamination (particularly
chromium waste) under the M74C itself rather than removing
the contamination completely from the areas affected; the
extensive earth and piling works involved and the
associated noise and disturbance; the limitation of the GI
to the route corridor itself, leaving the adjacent
regeneration sites for treatment in due course by potential
developers; and the massive costs involved in remediation
works.
The Case for SAPT
7.24 Again, SAPT led no counter evidence and there was
no cross-examination of the TRA geo-technical and mining
witness. Cross-examination of the contamination witness
focussed on the possibility of a break in the linkage
between a source and a receptor; the statutory
responsibilities of local authorities to deal with
contaminated land; and the suggestion that containment of
contamination as opposed to removal was driven by cost
considerations. The cost of the SAPT alternative proposals
involving tunnels at West Street and under Rutherglen
Station was also raised in the cross-examination of Brian
Swan, who indicated that contamination problems were likely
to be encountered. While no detailed study had been carried
out, costs were likely to be of the order of £100/115
million at West Street and £30/50 million at Rutherglen,
with further costs of £65/80 million on the section between
Farmeloan Road and Glasgow Road.
The Case for Mr T Martin
7.25 The objector is particularly concerned about the
proposal to construct the M74C through areas such as
Southcroft Park at Glasgow Road, Rutherglen, which is known
to be severely contaminated with hexavalent chromium waste,
a known carcinogen causing nasal, skin and lung cancer if
ingested. Previous sites of a similar nature in Rutherglen
have simply been capped over and left undisturbed on advice
from the relevant authorities that the waste was too
dangerous to move and disturb. Old mine workings also lie
beneath Southcroft Park and previous expert reports have
highlighted the dangers of piling and laying foundations on
such unstable materials. The M74C is to be a Design and
Build contract and accordingly the design has not been
finalised. The environmental assessment has proceeded on
the basis of assumptions.
The Case for Terrace Community
Association
7.26 The objection is a general one, highlighting
concerns at the high levels of chromium waste in the
Rutherglen area and the risks to health which construction
of the M74C on the line proposed might bring. The
suggestion of re-routing the road to the north to an
earlier line involving 2 bridges at the Cuningar Loop is
suggested.
« Previous | Contents | Next »