| Description | Planning Advice Note PAN 33 DEVELOPMENT OF CONTAMINATED LAND |
|---|
| ISBN | (Web Only) |
|---|
| Official Print Publication Date | |
|---|
| Website Publication Date | October 20, 2000 |
|---|
Planning Advice Note PAN 33
Revised 2000 October 2000
DEVELOPMENT OF CONTAMINATED
LAND
introduction
Land can be contaminated by a variety of
substances that pose immediate or long-term risks
to human health and the environment. Such
contaminants may escape from the site to cause air,
land, surface water or groundwater pollution, and
in some cases may even damage buildings and
underground services, or contaminate the food
chain.
As part of the Government's commitment to
sustainable development, the legacy of
contamination has to be dealt with, and additional
contamination prevented. Improvements in scientific
understanding of the potential harm caused by
contaminants, allied to the determination to re-use
previously developed land wherever possible, have
served to highlight the importance of tackling
contaminated land.
The planning system has a key part to play in
addressing the problem of historical contamination.
In pursuing policies to re-use and redevelop sites,
developers and planning authorities need to be
aware of contamination issues, and the role of the
planning system in dealing with them (see
paragraphs 24-49).
A new contaminated land regime, implementing the
provisions of Part IIA of the Environmental
Protection Act 1990 (as inserted by section 57 of
the Environment Act 1995), came into force on 14
July 2000. Planning authorities should be aware of
the provisions of the new regime (see paragraphs
50-56), and ensure that their policies, procedures
and decisions are consistent with it.
- The objectives of this PAN are therefore to provide
advice on :
- the implications of the new contaminated land
regime for the planning system;
- the development of contaminated land;
- the approach to contaminated land in development
plans;
- the determination of planning applications when the
site is or may be contaminated; and
- where further information and advice can be
found.
- This PAN replaces the previous PAN 33 on
the development of contaminated land, issued in
1988, which is now cancelled.
what is contaminated land?
Nature of Contamination
Land may be contaminated by a wide variety of
substances and materials in the form of solids,
liquids or gases. Contaminants may be spread across
a site, or concentrated in pockets; readily
identifiable, or hard to detect. They may be mixed
with top-soil, with inert waste materials, or
buried beneath clean material.
A problem arises when the concentration and
environmental availability of a contaminant on site
is not compatible with its existing or proposed
use, or when it escapes into water, air or onto
another site. The scale of the problem will vary
according to the contaminant and the use of
affected land. In order to have a deleterious
effect, there needs to be a pathway enabling the
contaminant to reach a receptor at a concentration
capable of causing harm (see box below).
Sources, Pathways and Receptors
- Source - a contaminant or potential
pollutant ( on site or capable of migrating onto
site.
- Pathway - the environmental route
(direct or indirect) by which contaminants reach
receptors i.e. the link between the source and the
receptor.
- Receptor - target which could be
damaged if contamination is present at a level
sufficient to cause harm.
- Contaminated land can represent a potential risk to
human health or the environment through :
- the direct uptake of contaminants into the food
chain or ecosystems;
- direct ingestion or inhalation of, or contact with,
contaminants;
- contamination of water resources;
- fire and explosion of combustible contaminants;
and
- attack on building materials and services by
corrosive contaminants.
Defining Contaminated Land
'Contamination' can be, and is, interpreted in
many different ways and as a result a number of
definitions exist. The definition of "contaminated
land" in Part IIA of the 1990 Act is set out at
paragraph 51. For the purposes of this document
when this definition of contaminated land is used
it will be referred to as "Part IIA contaminated
land".
It is important to recognise, however that the
Part IIA definition reflects the intended role of
the contaminated land regime, i.e. to enable the
identification and remediation of land from which
contamination currently represents an unacceptable
risk to human health or the wider environment. Part
IIA contaminated land does not necessarily include
all land where contaminants are present.
With regard to the planning regime, a site
containing contaminants may not be likely to cause
significant harm in its current use, but if a
different use were proposed, then the potential for
significant harm may be enhanced. Moreover, the
mere presence (or suspected presence) of
contaminants may prove an impediment to the
successful development of a site. Planning
authorities should have regard to the potential
blighting effects in these cases. Finally, the
presence or level of contamination may simply be
unknown, but this should not be taken to mean that
potential contamination should be disregarded. The
possibility of contamination on a site proposed for
development should trigger a response which takes
into account the potential risk. Planning
authorities, therefore, need to consider
'contaminated land' in its broadest sense.
- Contaminated sites, for planning purposes, may be
regarded as any site where the presence or suspected
presence of contaminants is an obstacle to development,
regardless as to whether development is proposed.
Distribution and Scale of the Problem
In considering the re-use of land, the
possibility that it may be contaminated cannot be
ignored. Chemicals are extensively used in
industrial, domestic and agricultural applications.
They may be introduced to land during their
manufacture, use or disposal, and may also be
deposited from the atmosphere, accidental spills,
migration, leaks and illegal disposal. There are
also natural sources of contamination, whereby
concentrations of certain substances in the soil
are elevated, and may pose a threat to people or
the environment e.g. methane may build up from the
breakdown of organic material.
In Scotland contamination is most frequently
associated with past industrial activity,
inadequate waste disposal and some agricultural
activities. Some materials, once commonly used
without any safeguards, are now known to be
contaminants e.g. asbestos. It is likely to be an
issue where land has been used for gasworks, oil
refineries, metal processing, landfill, chemical
manufacturing, heavy engineering facilities, wood
preserving yards, and petrol stations. The range of
contaminants found at such sites is diverse. Of
particular concern are: toxic or phytotoxic metals
such as lead and cadmium; inorganic compounds such
as sulphates, sulphides and cyanides; organic
compounds such as phenols, polycyclic aromatic
hydrocarbons and solvents; flammable and toxic
gases; pesticides; and asbestos.
Neither the list of uses, nor the list of
substances, is exhaustive.
Contamination may be found in any location, but
is most common around the urban areas that
developed during the industrial revolution. There
is no definitive list of all the potentially
contaminated sites in Scotland, but the Scottish
Vacant and Derelict Land Survey (SVDLS) provides
information on the number of sites where land is
vacant, or derelict as a result of its former use.
The SVDLS is an important source of information on
potential contaminated land, but it is not
definitive - the position on contamination was
unknown for 43% of the vacant and derelict land in
the 1999 survey (Scottish Executive Statistical
Bulletin, 1999, paragraph 4.1). Of the remainder,
78% of the derelict land was known, or suspected,
to be contaminated. (NB the definition of
contaminated land in the SVDLS is not the Part IIA
definition as set out at paragraph 51). It should
be recognised, of course, that contamination is not
confined to sites which are vacant or derelict.
- In summary, there is no single source of
information available that lists the distribution
and scale of contaminated land in
Scotland.
Scottish Executive approach to contaminated
land
The "Suitable For Use" Approach
The Scottish Executive considers the "suitable
for use" approach as the most appropriate to deal
with our historic legacy of contaminated land, in a
way that takes account of environmental, social and
economic objectives. It is also consistent with
Scottish Executive policy on sustainable
development. This approach focuses on the risks
caused by land contamination, and recognises that
the risks presented by any given level of
contamination will vary greatly according to the
use of the land and a wide range of other factors,
such as the underlying geology of the site. Risks
therefore need to be assessed on a site-by-site
basis (see paragraphs 21-23).
- The "suitable for use" approach consists of three
elements :
i) ensuring that land is suitable for its
current use - in other words, identifying land
where contamination is causing unacceptable risks to
human health and the environment, on the basis of the
current use and circumstances of the land, and
returning it to a condition where such risks no longer
arise ("remediating" the land);
this is the role of the Scottish Environment
Protection Agency (SEPA) in the case of "special sites
1" and local authorities in the case of any other
type of site;
ii) ensuring that land is made suitable for any
new use, as planning permission is given for that new
use - in other words, assessing the potential
risks from contamination, on the basis of the proposed
future use and circumstances, before permission is
given for the development and, where necessary, to
avoid unacceptable risks to human health and the
environment, remediating the land before the new use
commences;
this is the role of the town and country
planning and building control regimes; and
iii) limiting requirements for remediation to
the work necessary to prevent unacceptable risks to
human health or the environment in relation to the
current use or future use of the land for which
planning permission is being sought - in other
words, recognising that the risks from contaminated
land can be satisfactorily assessed only in the context
of specific uses of the land (whether current or
proposed), and that any attempt to guess what might be
needed at some time in the future for other uses, is
likely to result either in premature work (thereby
risking distorting social, economic and environmental
priorities) or in unnecessary work (thereby wasting
resources).
- Within this 'suitable for use' framework, it is
important to recognise both that the use of any
particular area of land may cover several different
activities, and that some potential risks arising from
contamination (particularly impacts on water and the
wider environment) may arise independently of the use
of the land. For example the current use of a site may
be irrelevant if harm is being caused off-site e.g. the
pollution of a nearby watercourse. In practical terms,
the current use of any land should be taken to be any
use which :
(a) is currently being made of the land, or is
likely to be made of it; and
(b) is consistent with any existing planning
permission, or is otherwise lawful under town and
country planning legislation.
Site Specific Risk Assessment
The site specific risk assessment approach
requires a view to be taken of the risks posed by a
specific site, given the particular source(s),
pathway(s) and receptor(s), and the extent of
remedial treatment required to ensure that human
health and the environment are no longer at
risk.
The statutory regime applies where it is
necessary to deal with unacceptable risks which
arise as a result of current uses of land.
Remediation should require that land is returned to
a quality where it is fit for its
existing use. Where development is
proposed on contaminated land, the planning system
is the appropriate mechanism for tackling
remediation, either as a part of the planning
application, or by conditions. Each site has to be
considered on its own merits, and within its own
environmental setting, a concept familiar to
planners. The planning authority should ensure that
the land is made suitable for the
proposed use.
- It is inherent in the site specific approach, that
a site is only considered to be contaminated, and
requiring remedial treatment, if there is a risk of any
harm posed by the site. Any remedial treatment is then
designed to address the actual, or potential, risk
posed. Therefore, the developer must build-up a picture
of the source(s), pathway(s) and receptor(s) that are
relevant to the particular site, consider the risks
that are relevant and design an appropriate remedial
solution. This process of Risk Assessment is summarised
in Annex 1. Implicit within this site specific approach
is that generic concentrations in soil of contaminants
above which a site is considered contaminated
(sometimes called "trigger levels"), are not relevant
to site specific risk assessments and should not be
used.
the role of the planning system
Contamination may threaten public safety, the
natural and built environment, and act as a barrier
to economic activity. As described at paragraph 19,
a key role of the planning system with regard to
contaminated land, is to ensure that land is made
suitable for any new use, as planning permission is
given for that new use. Therefore, whether
confirmed or suspected, contamination is a material
planning consideration. It should be considered as
one of the factors in the preparation of
development plans, as well as in the determination
of planning applications.
The best way of minimising any associated risks
is to ensure that potentially contaminated sites
are identified at an early stage. The necessary
investigations can then be carried out to enable
cost-effective solutions to be devised and thus
reduce the need for urgent and expensive emergency
action later.
- The prospect of enhanced land values is often an
incentive to the remediation of a contaminated site.
Development may be proposed as a means of increasing
the value of a contaminated site, thus covering the
cost of remediation. This is a perfectly acceptable
approach to tackling contaminated land and is
consistent with Scottish Executive policy with regard
to sustainable development. In these circumstances, if
the proposed development is satisfactory in other
respects, then the planning authority is responsible
for ensuring that remediation leaves the land in a
condition suitable for the proposed use.
Development Plans
In preparing development plans, planning
authorities are expected to encourage and promote
the re-use of brownfield land, including
contaminated sites. Development plans provide an
opportunity for authorities to set out their
priorities for the reclamation and re-use of
contaminated land, and to inform developers of the
availability of sites, and the potential
constraints attached to them.
Effective policy making should be based on
adequate and accurate information. Any survey
preparatory to drawing up development plans should
identify, as far as possible, the physical and
chemical constraints on land within the plan area.
The requirement under Part IIA for local
authorities to identify contaminated land in their
area should furnish a more complete information
base on sites than has hitherto been the case, even
where the land is found not to be Part IIA
contaminated land.
Local plans should set out site specific
proposals for land use in their area so that
opportunities for development and redevelopment are
readily identifiable to landowners, prospective
developers and the local community. The allocation
of a site for a particular use however, does not in
itself approve the suitability of a site for that
purpose. Only investigation by the developer or
applicant can confirm this.
Planning authorities should not be deterred from
allocating contaminated land for development on the
grounds that a high level of remediation would be
required for the new use, e.g. housing. Where there
are high remediation costs they may be more easily
borne by a new high value use, though other
planning considerations will also be relevant in
allocating sites and determining applications.
There may however be situations where the
anticipated benefits of remediation are significant
enough for them to take priority over other policy
objectives and a high value end use is essential to
make remediation viable.
- General advice on the preparation of Structure
Plans and Local Plans in Scotland has been given in
previous Planning Advice Notes (PAN 37
Structure Planning, and PAN 49
Local Planning).
Development Control
It is a long established principle that
"planning powers should not normally be used to
secure objectives which can be achieved under other
legislation" (NPPG1 -
The Planning System, paragraph 49). PAN 51
Planning and Environmental Protection,
provides advice on good practice and information on
the role of the planning system in controlling
pollution and its relation to environmental
protection regimes.
However where development is to take place on
contaminated land, a key element of the 'suitable
for use' approach is to ensure that land is made
suitable for the proposed new use (or other uses
allowed under the Use Classes Order); this is the
responsibility of the planning authority. Planning
authorities should therefore require that
applications include suitable remediation measures.
If they do not, then there are grounds for refusal.
Where applications are approved, conditions should
be put in place to ensure that land is remediated
before the commencement of any new use.
Even before an application is made, informal
discussions between the developer, planning
authority and any other interested party should be
beneficial in identifying the likely state of
contamination and the most appropriate means of
remediation. There are clear benefits in bringing
in expert advice, including that from other council
departments, at this early stage. If the planning
authority has reason to believe that the land might
be contaminated, then this should be brought to the
attention of the developer immediately and the
implications explained. Furthermore, if there are
severe obstacles to the proposed development, other
than the question of contamination, these should be
brought to the developers attention at an early
stage, so that the developer can make a judgement
as to whether to carry out what might be an
expensive site assessment for a development which
has little prospect of approval.
Early examination of site characteristics,
either through the first stage of the remediation
process (see paragraph 59), or desk studies, is
crucial. If initial investigations indicate
significant levels of contaminants, it is
appropriate to require site specific risk
assessment to be applied to land that is proposed
for development i.e. a new use. It is the
responsibility of the developer to undertake an
adequate risk assessment of a site, and to propose
measures to ensure that these risks are
appropriately addressed. For a mixed use
development, the restoration plan should consider
the most sensitive receptor for each land use.
A planning officer will need to consider, with
specialist advice if necessary, whether the
developer has adequately identified the sources of
contamination and put forward a restoration scheme
suitable for the proposed use that will ensure that
all the receptors are adequately protected from
contamination. If the information provided by the
applicant is insufficient to enable the authority
to determine the application, the applicant may
need to be asked to provide further information by
means of a direction under Article 13 of the Town
& Country Planning (General Development
Procedure) (Scotland) Order 1992.
- Applications need not, however, be delayed pending
an investigation by the developer unless there is good
reason to suppose that the land is actually
contaminated. Moreover, where there is potentially only
slight contamination, planning permission may be
granted on condition that development will not be
permitted to start until a site investigation and
assessment has been carried out and that the
development itself will incorporate measures shown in
the assessment to be necessary. Section I.2 of the
addendum (issued in April 1999) to Circular 4/1998,
The Use of Conditions in Planning Permissions
sets out model planning conditions relating to
contaminated land (see box below). If an issue cannot
be resolved by imposing a planning condition, it may be
possible to do so by concluding an agreement under
section 75 of the Town & Country Planning Act
1997.
Extract from Model Planning Conditions, the
addendum to circular 4/1998, The Use of Conditions
in Planning Permissions
"Development shall not begin until a scheme to deal
with contamination on the site has been submitted to
and approved in writing by the planning authority. The
scheme shall contain details of proposals to deal with
contamination to include:
i. the nature, extent and types(s) of contamination
on the site.
ii. measures to treat/remove contamination to ensure
the site is fit for the use proposed.
iii. measures to deal with contamination during
construction works.
iv. condition of the site on completion of
decontamination measures.
Before any [
specify e.g.
residential/commercial/business/retail] unit is
occupied the measures to decontaminate the shall be
fully implemented as approved by the planning
authority." In addition, in appropriate circumstances,
a condition covering monitoring measures may be
included.
Section1.2, Page 15
Ultimately however, if the restoration plan is
inadequate and the applicant is unwilling or unable
to amend it, a refusal may be the only option. On
planning appeals relating to contaminated land, it
is important that the principle parties provide
adequate information at the outset concerning the
contamination that has been found; details of the
risk assessment undertaken to consider the
implications of those contaminants in that
location; the proposed restoration programme; and
the planning conditions considered appropriate to
deal with these issues. For those appeals
proceeding by way of public inquiry, this
information should be provided no later than the
submission of the statement of case.
The assessment of the significance of
contamination and of the associated risks requires
careful professional judgement. It is therefore
recommended that planners should obtain advice from
experts in other local authority departments, such
as environmental health, waste disposal, land
reclamation, building control, surveying and
engineering (see paragraphs 46 - 48). In some
circumstances, these departments may indicate that
other organisations should be consulted with regard
to matters for which they have regulatory
responsibility. For example, the Health and Safety
Executive may be consulted on worker exposure and
SEPA on matters such as water pollution and waste
disposal issues. When such consultations take place
it should be made clear by the planning authority
that contamination is the reason for the
consultation. In some circumstances it may be
necessary to use specialist consultants.
Planning officers should recognise that, with
regard to Part IIA contaminated land, remediation
notices may only require that sites be restored to
a standard suitable for the existing use.
Additional clean up measures will frequently be
required in relation to a proposed new use. It is
more effective and efficient to undertake a single
restoration operation, rather than for the owner to
first restore the site to a certain standard, and
then second, for a developer to separately restores
the site to a higher level, suitable for the
development proposed. In these circumstances,
planning officers should, wherever possible, seek
to encourage owners and potential developers to
co-operate and share the cost burden by agreeing a
single restoration strategy to provide a site
adequate for the new use (see paragraphs
70-75).
The planning authority must consider whether a
developer's restoration plan is adequate to avoid
unacceptable risks to human health and the wider
environment from the contamination on the site,
both during the restoration period and for the
final end use.
The end use of the site is a crucial
consideration when determining whether a
restoration plan is adequate. In general,
business and industrial development is likely to
require less remediation than, for example,
low-rise housing with private gardens, but each
site and proposal should be considered on its
merits. The choice of future use and the layout of
uses on the site, can be most effective in reducing
the need for treatment action, provided that
pollution of surface water or groundwater is not an
issue.
In those parts of the country which contain a
significant number of potentially contaminated
sites the planning authority may find it useful to
include a question on contamination on their
standard application form and a note to applicants
on the subject.
- Where planning consent is granted for a site on
which the presence of contamination is known or
suspected, an advisory note may be attached to the
planning permission informing the applicant(s) that the
responsibility for the safe development of the site
rests with the developer. It may also warn the
applicant that the planning authority has determined
the application on the basis of the information
available to it, but this does not mean that the land
is free from contamination.
Environmental Impact Assessment
The Environmental Impact Assessment (Scotland)
Regulations 1999 require that certain projects
(projects in Schedule 1 of the regulations and
projects in Schedule 2 which are likely to have
significant environmental effects) must be the
subject of Environmental Impact Assessment (EIA)
prior to development consent. The presence of
contamination in itself is not sufficient to
trigger the requirement for EIA, although it could
be a factor in establishing if a development is
likely to have significant environmental
effects.
- If EIA is required then the applicant will be
required to submit an environmental statement in
support of the planning application. This statement
must address the potential impacts of the development
on the environment. For EIA development involving
contaminated land, impacts may arise during site
remediation and after construction is complete (where
contaminants remain on site under the protection of a
containment system). If the development is likely to
produce contaminants, either by the project process, or
in its construction, then the environmental statement
should include an assessment of the likely effects. EIA
must also address any measures to be used to eliminate
or reduce the environmental impacts.
Other issues
Internal relationships
Contaminated land issues are likely to impinge
on several local authority functions -
environmental health, estates, engineering,
economic development - as well as planning. A
number of authorities have found it useful to form
dedicated multi-disciplinary working groups to deal
with this cross-cutting issue. Regardless of
whether this approach is adopted, it is important
that other departments with an interest contribute
to pre-application discussions (see paragraph 34),
and are consulted when applications are submitted
(see paragraph 39).
Close co-operation between those parts of an
authority responsible for implementing the
requirements of the Part IIA regime, and those
responsible for Town and Country Planning is
desirable. Historical information from the planning
register can be of assistance in identifying land
likely to be contaminated, and information gleaned
as a result of the duty of local authorities to
inspect their areas, can be used as an input into
development plan preparation.
- The new requirement to identify contaminated land
within an authority's area will provide a prime source
of information in the future. Local authorities will be
required to collect, manage and review a variety of
data sources in relation to a potentially large number
of sites. For authorities who do have a large number of
sites, Geographical Information Systems (GIS)
applications may prove useful in handling the data. One
site may be linked to a number of different reports
including previous site investigations.
Working in Partnership with other
Organisations
- There is much benefit to be gained by forming
alliances with other agencies, particularly members of
the Local Enterprise Company (LEC) network. A major
obstacle to the development of contaminated, or
potentially contaminated, sites is uncertainty as to
the extent and nature of the contamination.
Furthermore, such sites often have other problems e.g.
instability, or fragmented/unknown ownership. Planning
authorities and other agencies can play a positive role
in reducing uncertainty and promoting opportunity.
Scottish Enterprise Lanarkshire has developed a strong
working relationship with North and South Lanarkshire
Councils to tackle the problem of derelict industrial
land. They have targeted individual sites and clusters
of sites to promote development. This has involved
compiling information on sites, including site
investigations, and producing and distributing fact
sheets to potential developers. Putting information
together in such a package assists prospective
developers to ascertain relevant information and
identify what further investigative work is required.
This has proved successful in bringing land that has
lain vacant and derelict for a considerable time into
productive use.
the contaminated land regime
The new contaminated land regime is introduced
by the Environment Act 1995, which inserts a Part
IIA into the Environmental Protection Act 1990. The
main objective of the new Part IIA regime is to
provide an improved system for the identification
and remediation of land where contamination is
causing unacceptable risks to human health or the
wider environment, assessed in the context of the
current use and circumstances of the land. The new
contaminated land regime as described here does not
apply to any radioactive contamination of land.
Part IIA makes provision for the regime to be
applied to such contamination with such
modifications as the Scottish Ministers consider
appropriate. Separate regulations will be brought
into force at a later date.
The definition of "contaminated land" in Part
IIA is as follows :
" 'Contaminated Land' is any land which appears
to the local authority in whose area it is situated
to be in such a condition, by reason of substances
in, on or under the land, that -
(a) significant harm
2 is being caused or there is a significant
possibility of such harm being caused; or
(b) pollution of controlled waters is being, or
is likely to be caused;"
(Environmental Protection Act as amended,
Section 78A(2)).
A Brief Summary of the New Contaminated Land
Regime
- Local authorities will prepare written inspection
strategies to be formally adopted and published within
15 months of the issue of the statutory guidance (i.e.
by 14 October 2001);
- Local authorities will inspect their areas to
identify contaminated land and designate special
sites;
- Enforcing authorities (the local authority, or SEPA
in the case of a "special site") will establish the
appropriate person(s) to bear responsibility for
remediation;
- The regime encourages voluntary remediation,
therefore the enforcing authorities will work with
appropriate persons to ensure remediation occurs;
- Where voluntary remediation is not forthcoming, the
enforcing authority is able to serve a notice to
require remediation;
- Enforcing authorities will maintain a record of all
prescribed regulatory action on a public register;
- Remediation requirements are limited to the work
necessary to prevent unacceptable risks to human health
or the environment in relation to the current use or
the officially permitted future use;
- Responsibility for paying for remediation will,
where feasible, follow the "Polluter Pays" principle.
Persons who caused or knowingly permitted the
substances to be in, on or under the land will be
liable, in the first instance. If none can be found,
responsibility will pass to the current owners or
occupier.
Part IIA of the 1990 Act provides that a
pollutant linkage (source, pathway and receptor -
see box at paragraph 8) is identified in order for
land to be designated as "contaminated land" i.e.
site specific risk assessment is implicit in the
statutory regime. In the statutory context, it is
not possible to state that land is contaminated
simply because certain levels of a contaminant are
present.
Under the regime, the regulatory role for Part
IIA contaminated land is performed by the
"enforcing authorities
3 (see box below). The primary role will fall
to local authorities, but SEPA will also have new
duties and powers, including the regulation of
remediation of 'special sites'.
Duties And Powers Of Enforcing
Authorities Under Part IIA |
Local Authorities'
Duties: | SEPA Duties: |
- Inspect their areas to identify
contaminated land and designate special
sites;
| - Provide site specific advice to
local authorities on contaminated
land;
|
- Ensure remediation of land
identified as contaminated land;
| - Maintain remediation register of
special sites;
|
- Maintain remediation registers for
contaminated land; and
| - Prepare a national report on the
state of contaminated land; and
|
- Consult SEPA on the pollution of
controlled waters.
| - Require remediation of special
sites.
|
Local Authorities'
Powers: - Recover costs for remediation
undertaken itself.
| SEPA Powers: - Recover costs for remediation
undertaken itself.
|
The standard of remediation required by
enforcing authorities should result in the land
being suitable for use. In other words the aim of
any remediation should be to ensure that the
circumstances of the land are such that, in its
current use, it is no longer Part IIA contaminated
land (as statutorily defined - see paragraph 51).
It may be desirable to achieve a higher level of
remediation, to make the site suitable for a
different use, but that objective would have to be
achieved by means other than a remediation notice,
for example through the planning system.
Part IIA incorporates the site specific risk
assessment approach. This means that there are no
generic UK statutory standards for acceptable
concentrations of contaminants in soil. For a site
to be designated as contaminated land under Part
IIA, there must be at least one source, pathway and
receptor which will result in significant harm to
human health or the environment (see paragraph 51)
or pollution of controlled waters, or there must be
potential for such harm to occur. The risks from
each site must be assessed on their own merits to
determine if harm or pollution are occurring. There
are a variety of technical methodologies to assist
the determination.
More detailed information on the new
'Contaminated Land Regime' may be found in the
statutory guidance in SERAD Circular 1/2000.
remediation of contaminated land
Definition of remediation
- The definition of 'remediation' given in section
78A(7) of Part IIA extends more widely than the common
usage of the term (Environmental Protection Act 1990 as
amended). It includes not only the actions to restore
the "contaminated land", but also the assessment of
:
- the land in question;
- any controlled waters affected by that land;
or
- any land adjoining or adjacent to the land in
question.
- It also includes subsequent inspections to keep the
condition of the land or waters under review. For the
purposes of this section, 'remediation' should be
understood in these terms, unless the context dictates
otherwise.
Remediation process
- The box below sets out the key stages in the
remediation process.
Key Stages In The Remediation Process
Site characterisation (comprising site
investigation and risk assessment)
Formulation of a restoration strategy
Detailed design specification
Implementation and post-works activities
(including monitoring)
Adapted from
How to Approach Contaminated Land, Scottish
Enterprise, 1998
Site characterisation
A site is typically characterised by undertaking
site investigations (desk study, walkover survey
and intrusive investigations) in association with a
risk assessment, to develop a conceptual site
model, whereby the source(s), pathway(s) and
receptor(s) are identified. A multi-disciplinary
approach is especially important for investigations
into contamination.
- There is no firm dividing line where site
investigation ends and risk assessment begins. The
purpose of risk assessment is to establish whether a
site is likely to pose unacceptable risks to human
health or the environment, given its existing or
proposed use. Risk is a combination of the likelihood
of an event occurring and the consequences if it did
occur. The approach adopted by the new regime is for
site specific risk assessment (see paragraphs
21-23).
Formulation of a Restoration Strategy
- A restoration strategy (also known as a remediation
plan, or risk management) should be prepared for
contaminated sites. It should address the management of
the risks identified in the risk assessment, and should
not only include details for restoring the site, but
also the means of verifying the restoration. In order
to do so, the strategy should identify means by which
all the source-pathway-receptor links are broken. The
table below shows a variety of remedial options. For
any one site a number of different means might be
employed, particularly if there is a variety of
contaminants and/or receptors.
Remedial Options |
Means of remediation | Example(s) |
Treatment of
source | - Remove all contaminated material
from the site and dispose of it
elsewhere (dig 'n' dump);
- Treat contaminants on site so that
concentration and/or availability is
reduced.
|
Blocking
pathways | Break pathway through installation of a
physical barrier. |
Isolating
receptors | Design layout so that receptors cannot
make contact with areas of
contamination. |
Standards
- There are no UK statutory standards for acceptable
concentrations of contaminants in soil, as decisions
are made on a site by site basis. If it is decided to
reduce the concentrations of contaminants, it should be
noted that SNIFFER (Scotland and Northern Ireland Forum
for Environmental Research), SEPA, the Environment
Agency and Department of Environment Transport and the
Regions (DETR) have developed methods for establishing
the degree of soil clean-up required to protect water
resources, ecosystems and human health.
Detailed specification
- Once an appropriate restoration strategy has been
identified the next stage is to prepare a specification
to implement the strategy. The detailed design should
include health and safety procedures and environmental
precautions. An implementation plan should be prepared
to specify the works to be undertaken, the provisional
remedial targets to be met, the verification procedure
to be carried out, and any on-going monitoring to
ensure the effectiveness of remedial measures after the
works have been implemented.
Implementation and post-works
activities
At the implementation stage, once the remedial
works have commenced, appropriate records should be
kept on the progress of the works. Progress reports
(including verification sampling) will enable the
implementation to be monitored, and enable the
significance of any variations against the
implementation plan to be assessed. Modifications
to the remedial works may need to be undertaken if
remediation standards are not being met.
Ongoing monitoring might be required as part of
post-treatment management to demonstrate
effectiveness in the long term or as regulation of
waste licensing or planning conditions. What
constitutes completion of the remedial works should
be determined at the outset of the project.
If all contaminants of significance are removed
or destroyed at the end of implementation, and the
site specific remediation standards have been met,
no further action is needed apart from ensuring
comprehensive, appropriate documentation is
prepared and maintained. If, however, contaminants
remain or the end-point of remedial treatment is
uncertain, post-treatment management will be
required.
In some cases, the carrying out of remediation
activities may itself constitute development within
the meaning given at section 26 of the Town and
Country Planning (Scotland) Act 1997, and therefore
require planning permission.
- Further information on the remediation process can
be found at Annex 1.
interaction between the planning and contaminated
land regimes
- Although the planning and contaminated land regimes
are two distinct systems, there is a degree of
interaction between them. There are two main
circumstances in which a planning application and Part
IIA procedures may overlap:
(i) where land is designated as contaminated land
under Part IIA, and subsequently the appropriate person
wishes to develop the land; and
(ii) where development of land means, in its new
use, that land will be designated as contaminated land
under Part IIA.
In scenario (i) above, the local authority will
have made the determination that an area of land is
Part IIA contaminated land. At this point,
negotiations between the local authority and the
"appropriate person(s)
4" will commence. It may emerge that the
appropriate person sees inherent advantages in
developing the site, and at the same time providing
the level of remediation required to ensure that
all harm on the site is adequately dealt with.
Development may provide the finance necessary to
fund the remediation, for example. In addition,
some engineering operations carried out for
remediation purposes may require planning
permission.
If remediation of Part IIA contaminated land is
proposed as part of a planning application, then it
is the responsibility of the planning authority to
ensure that the land is suitable for the proposed
use. In this instance, the proposal to develop the
land may represent agreed remediation. The
appropriate person would have to supply sufficient
information to both the enforcing authority under
Part IIA, and to the planning authority, which may
require separate documentation of the proposed
development. Remediation should be enforced through
the planning permission and/or conditions, wherever
possible.
Where a site is Part IIA contaminated land, it
is unlikely to be acceptable for land to remain in
a contaminated state for a long period of time
awaiting development - by definition, the site is
causing significant harm or there is a significant
possibility of such harm being caused (see
paragraph 51). In the absence of a definite
timetable for progress, in a reasonable period of
time, the option is available to the enforcing
authority to take action under Part IIA to deal
with the harm from the current use of the site.
In scenario (ii) above, a development proposal
may be submitted to the planning authority. In its
current use the land is not causing any harm, and
therefore is not Part IIA land. However,
development may :
- introduce new receptors onto a site, for example by
changing the use of the site; or
- expose new pathways by which contaminants can reach
existing receptors.
In either of these instances, development may
result in land being designated as Part IIA
contaminated land. It is in the developer's
interests to ensure that development of the site
will not result in designation as contaminated land
under Part IIA, and thus become prone to a
remediation notice under the contaminated land
regime. As with scenario (i) the planning authority
should ensure that the land is suitable for its
proposed use.
There are also opportunities for sharing
information. Under the new regime, local
authorities are required to prepare a strategy to
identify Part IIA contaminated land in their area.
Historical planning records could prove useful to
an authority carrying out its Part IIA duties and
the subsequent inspection of sites is likely to
yield a more thorough information base for councils
than has hitherto been the case. Even where the
land use planning service is not the responsible
department charged with undertaking this task, the
information has the potential to be used for
planning purposes.
- Both local authorities and SEPA are required to
maintain public registers detailing remediation
activity at statutorily contaminated sites. SEPA also
has a statutory duty to compile a national report on
"contaminated land". In time, these requirements are
likely to provide additional sources of information on
the distribution of contaminated land.
financial assistance
Government Sources
Funding is made available through Scottish
Enterprise, Highlands & Islands Enterprise and
the Local Enterprise Company (LEC) network to
support site redevelopment costs for projects aimed
at particular social and economic regeneration
objectives. Remediation of contaminated land is one
facet of Scottish Enterprise's regeneration
activities. The distribution of funding is
administered through the local enterprise network,
and will vary from LEC to LEC. A higher priority is
likely to be given to remediation schemes where
there is a legacy of substantial industrial
dereliction harming local economic development
prospects.
Following consultation with the Convention of
Scottish Local Authorities, additional resources
have been allocated to help local authorities carry
out their responsibilities under the contaminated
land regime i.e. develop inspection strategies,
carry out site investigations and take forward
enforcement action.
European funding
- European funding for the remediation of
contaminated land has been forthcoming in the past ,
but at the time of writing the scale and precise detail
of future European funding had yet to be finalised.
Nevertheless, planning authorities are advised to
explore the possibility of European funding when
considering remediation schemes.
Recovering Costs
- Where land is statutorily defined as contaminated
land then the provisions of Part IIA allow for the
recovery of the enforcing authorities remediation costs
from the polluter or, if the polluter is unable to be
located, from the owner or occupier of the land.
However, remediation notices can only require that land
is made suitable for its existing use. Where
development is involved it is expected that the
remediation costs would be borne by the developer.
other legislation
- Other legislation, in addition to the planning
system and Part IIA, has an impact on contaminated
land, particularly where the aim is to prevent future
contamination.
Building Control
Where it is proposed to build on a contaminated
site, particular attention should be paid to the
provisions of Part G of the Technical Standards for
compliance with the Building Standards (Scotland)
Regulations 1990, as amended. The intention of Part
G is to ensure that measures are taken to protect
people, and the fabric of a building, from harm
which could be caused by site conditions.
Essentially the site beneath a building and ground
immediately adjoining that site, must have harmful
or dangerous substances removed or made safe.
Thorough investigation is necessary to ensure that
appropriate measures can be taken where there is
evidence of such substances. An appendix to Part G
gives outline guidance on the preparation of a site
where harmful or dangerous substances are suspected
or identified.
Future contamination of land is controlled by
:
Integrated Pollution Control (IPC)
- Part I of the 1990 Act places a requirement on
operators of prescribed industrial processes to
operate within the terms of permits issued by SEPA
to control harmful discharges;
Pollution Prevention and Control (PPC)
- a new regime is due to be introduced
shortly to replace IPC, and to implement the
European Union's Integrated Pollution Prevention
and Control Directive, phased in between 2001 and
2007; that includes the specific requirement that
permits for industrial plants and installations
must include conditions to prevent the pollution of
soil and the requirement for site restoration on
closure;
Waste Management Licensing - Part
II of the 1990 Act places controls over the
handling, treatment and disposal of controlled
wastes;
Groundwater Regulations 1998 -
aimed at preventing certain types of discharges to
groundwater of listed substances via land;
Control of Major Accident Hazard
Regulations (COMAH), - deals with accident
hazards at major industrial installations; and
Health & Safety : legislation
such as Health & Safety at Work Act
1974/Control of Substances Hazardous to Health
Regulations (COSHH) 1988.
conclusion
- Planning authorities have a positive role to play
in tackling the legacy of contaminated land by :
- ensuring that, in most instances, contaminated land
is identified at an early stage in the planning
process;
- developing appropriate development plan policies
for the remediation and redevelopment of contaminated
land; and
- taking contamination issues into account in
determining planning applications and attaching
conditions.
- The Scottish Ministers look to planning authorities
and developers to put into practice the advice given in
this Planning Advice Note, but recognise that the
specific policies and practices to be adopted by
planning authorities are for them to decide given the
particular local circumstances in their areas.
note
Enquiries about the contents of this planning advice
note should be addressed to Graham Jones, Scottish
Executive Development Department, Planning Services, Room
2-H, Victoria Quay, Edinburgh EH6 6QQ (Tel : 0131 244 7550,
e-mail :
graham.jones@scotland.gov.uk).
Further copies, together with other PANs, can be obtained
by contacting Lynn Jameson at the same address (Tel : 0131
244 7543, e-mail :
lynn.jameson@scotland.gov.uk).
NPPGs and Circulars are available from Planning Division
(Tel : 0131 244 7067, e-mail :
planningdivision@scotland.gov.uk).
This PAN, along with other planning series documents, is
accessible within the Scottish Executive web site at
www.scotland.gov.uk/planning
Annex 1 : remediation process
Site Characterisation
A.1 A site is typically characterised by undertaking
site investigations (desk study, walkover survey and
intrusive investigations) in association with a risk
assessment, to develop a conceptual site model.
Site Investigation
A.2 Site investigations should always commence with a
desk study, so that consideration can be given to health,
safety and environmental hazards prior to fieldwork
commencing. Information on potential hazards should be
translated into a Health & Safety Plan for the work. A
key indicator of whether a site is potentially contaminated
is the current and/or previous uses (see paragraphs 14-17).
Several sources of information can be used in an initial
investigation to establish the potential for contamination
:
- Planning history;
- Current and historical OS maps;
- Current and historical site plans;
- Photographic information;
- Financial records;
- Information about surrounding sites; and
- Previous investigations.
A.3 The desk study should be followed by a walk-over
study if there are indications that contamination may be
present, and provided that the initial desk study has
indicated that risk to personnel is minimal. A walk-over
study can provide obvious visual signs of pollution such as
oil staining and vegetation stress.
A.4 If the initial investigation gives cause to believe
that there may be a problem with contamination then further
more detailed investigation will be required. Physical site
investigations take a variety of forms including:
- Trial pits;
- Surface samples;
- Boreholes;
- Soil gas and vapour surveys;
- Groundwater monitoring;
- Surface water sampling; and
- Geophysics.
A.5 For an effective site investigation an appropriate
sampling strategy has to be developed. Data quality is
dependent on :
- Completeness - the extent to which the available
information adequately defines the situation being
assessed;
- Relevance - the extent to which the information is
relevant to the situation being assessed;
- Reliability - the extent to which measurements or
observations accurately reflect true or likely site
conditions and the implications of information gaps on
assessment findings; and
- Clarity - the extent to which the available
information presents a clear and unambiguous account of
the situation being assessed.
A.6 For more detailed information on site investigations
please see How to Investigate Contaminated Land, Scottish
Enterprise (1998).
Risk Assessment
A.7 There is no firm dividing line where site
investigation ends and risk assessment begins. The purpose
of risk assessment is to establish whether a site is likely
to pose unacceptable risks to human health or the
environment. Generally it comprises identifying and
assessing potential hazards and then estimating and
evaluating the degree of risk. Risk is a combination of the
likelihood of an event occurring and the consequences if it
did occur.
Purposes of risk assessment
- Systematically determine whether there are any
current or potential unacceptable risks to human health
or other targets;
- Determine the effects of foreseeable events, such
as weather extremes, rising water table, flooding,
increases in neighbouring populations etc., on the
nature and magnitude of the risks;
- Determine the consequences (e.g. potential impacts
on the environment, groundwater resources, human
health) of a change of use, development, redevelopment
or other works on site;
- Identify the critical contaminants and pathways
relevant to the site so that the steps necessary to
reduce risks to 'acceptable' levels both currently and
in the foreseeable future, can be determined;
- Make judgements about the significance and
acceptability of identified risks;
- Help to set objectives and priorities for reducing
risks; and
- Provide a rational and defensible basis for
discussing a proposed course of action with third
parties (e.g. regulators, communities, funders,
insurers etc.).
A.8 Generally risk assessment comprises four main
components :
- Hazard investigation
- identification of contaminant
sources, pathways and receptors, taking into account
the actual or intended use of the site and its
environmental setting. - Hazard assessment
- consideration of the plausibility of pollutant
linkages and determination of the potential for human
health and environmental risks. - Risk estimation
- estimation of the risk that identified
receptors will suffer adverse effects if they come into
contact with contaminants under defined
conditions. - Risk evaluation
- evaluation of the need for risk management
action having regard to the nature and scale of risk
estimates, any uncertainties associated with the
assessment process and, where further action is
required, the objectives and broad costs and benefits
of that action.
A.9 This approach allows a view to be taken of the risks
posed by the site, given the particular source, pathways
and receptors. It also helps to set objectives and
priorities for reducing risks so that a restoration
strategy can be devised.
Site Restoration
A.10 A restoration plan (also known as a remediation
plan, or risk management) should be prepared for
contaminated sites. It should address the management of
risks identified in the risk assessment and should include
details for restoring the site, and also the means of
verifying the restoration. Such a plan is an essential part
of a planning application for contaminated land.
Alternatively, where contamination is only suspected or is
of a minor nature the planning authority may wish to make
restoration a condition of the planning consent (see
paragraph 37).
Methods of Restoration
A.11 Source, pathway and receptor may be considered as
links in a chain. The potential for harm only occurs when
the chain is complete. In order to manage risk the links
must therefore be broken. This might be done by removing or
reducing the source of the pollution by the physical
removal of the offending material or by treatment e.g.
bio-remediation, incineration or soil washing.
Alternatively the pathway may by blocked by, for example, a
physical barrier. The final link may be broken by keeping
receptors away from the source/pathway e.g. preventing the
establishment of sensitive uses on sites which have not
been the subject of remediation. Generally, restoration
proposals will entail one of the following :
Removal of all the contaminated material from the site
and disposing of it elsewhere (dig 'n' dump);
Breaking the pathways through installation of barriers
etc.;
Treatment of contaminants on site such that
concentrations and/or availability of contaminants are
reduced; or
Retaining the contaminants in a particular area of the
site.
A.12 Remediation measures should be evaluated to
identify an appropriate and cost-effective strategy to deal
with those unacceptable actual or potential risks to human
health or the environment which have been identified,
taking into account the actual or intended use of the site.
For any one site a number of different means might be
employed, particularly if there is a variety of
contaminants.
A.13 The following criteria may be used for the analysis
of remedial options:
- Protection and compliance - the ability to provide
the necessary degree of protection for receptors,
achieve specific remedial objectives and comply with
any regulatory requirements.
- Long-term performance and permanence - residual
risk remaining at the site after treatment should be
considered, and post-treatment management controls
should be assessed.
- Technical sufficiency - depending on the nature of
the material treated, the quantities of hazardous
materials on-site, the reversibility of the methods and
the types of residual materials generated.
- Impacts during implementation - on human health,
health and safety of the workforce, and the environment
including air, land and water quality and
ecosystems.
- Practicality - assess the risks and uncertainties
associated with the use of each method in the field and
the effects of any known constraints.
- Cost - including pre-implementation costs,
implementation costs and longer-term operation and/or
maintenance costs.
- Social and community impact and acceptance - any
specific requirements or concerns likely to be
expressed by the local community.
- Institutional acceptance - potential concerns of
owners, investors etc..
- Implementation and verification
A.14 The implementation of the restoration plan begins
when the preferred remedial strategy has been selected and
decisions need to be taken about how it is going to be
applied. "Remedial action", may be of a technical nature
(i.e. involving direct action on the contaminants or their
behaviour) or a non-technical nature (i.e. where action
involves the management of receptor behaviour to
reduce/alter their ability to come into contact with the
contaminants). The main stages in implementation are :
- Management Context: identifying management
objectives for the implementation of risk management
action and ensuring that the technical, planning and
management scope of the preferred remedial strategy is
clear and documented.
- Design and Procurement: confirming that the
remedial works have been designed and specified in
sufficient detail for the strategy to be
implemented.
- Implementation and Verification: ensuring that once
the remedial works have commenced appropriate records
are kept on the progress of the works (including any
variations). Records of verification sampling should be
used to confirm that objectives have been met.
- Ongoing Monitoring and Maintenance: The purposes,
aims and results of ongoing monitoring and maintenance
should be recorded.
Further Reading
A.15 A number of texts explore site remediation in
greater death. As a starting point please refer to How to
Investigate Contaminated Land, and How to Approach
Contaminated Land, both by Scottish Enterprise (1998).
Annex 2 : processing an application for development on
a contaminated site - issues checklist
At pre-application stage or on receipt of the
application
Information on contamination:
Has the site been classified as statutorily
contaminated?
Is the site known or suspected to be contaminated?
Are previous uses likely to have left the site in a
contaminated state?
Does the site require investigation prior to the
determination of the application?
Has the local authority gathered information on the site
in meeting the requirements of Part IIA?
Does the local authority possess any information on the
type and extent of contamination?
Have studies already been undertaken on the site?
Is the developer in possession of relevant information
on contamination?
Has the developer thoroughly investigated the site?
Remediation:
Does the site require some form of remediation for its
current/proposed use?
Has the developer provided a strategy for the
remediation of the site?
If so :
Is the strategy suitable for the proposed use of the
site?
Have a number of remediation techniques been
considered?
Have suitable standards been employed?
Does the remediation plan contain arrangements for
checking compliance with the standards selected?
Does the site require to be monitored on completion of
the works? If so, what arrangements are
proposed/required?
If not :
Is a remediation strategy required before the
application can be determined or can the necessary measures
be applied through conditions?
Post Approval Monitoring
Has the development been carried out in accordance with
the approved plans?
Has the developer complied with any planning
conditions?
Has the site been treated in accordance with the
remediation plan?
If required, have post-works monitoring procedures been
put in place?
Selected Bibliography
British Geological Survey (BGS) (1990) Hydrogeology of
Scotland (and associated Hydrogeology of Scotland map
(1988)).
British Standards Institiute (BSI) (1999), BS5930
Code of Practice for Site Investigations.
CIRIA, Special Publications 101-112 (1995-97),
Remedial Treatment of contaminated land, Volumes I-XII.
Contaminated Land (Scotland) Regulations 2000 (SSI
178/2000), The Stationery Office.
Department of the Environment (DoE) (1994), Guidance
on Preliminary Site Inspection of Contaminated Land (CLR
No.2).
DoE (1994), Documentary Research on Industrial Sites
(CLR. No. 3).
DoE (1994) Sampling Strategies for Contaminated Land
(CLR. No. 3).
DoE (1995/1996), Industry Profiles.
Department of the Environment, Transport and the
Regions (DETR), The Contaminated Land Exposure Assessment
Model (CLEA).
DETR (1997), A Quality Approach to Contaminated Land
Consultancy (1997)
Environmental Protection Act 1990, The Stationery
Office.
Environment Act 1995, The Stationery Office.
Environmental Impact Assessment (Scotland)
Regulations 1999 (SSI 1/1999), The Stationery Office.
Scottish Enterprise (1998), How To Investigate
Contaminated Land. Scottish Enterprise.
Scottish Enterprise (1998), How To Approach
Contaminated Land. Scottish Enterprise.
Scottish Executive Rural Affairs Department (2000),
Circular 1/2000, Environmental Protection Act 1990 : Part
IIA - Contaminated Land.
Scottish Executive (2000), Scottish Vacant and
Derelict Land Survey 1999, Statistical Bulletin Environment
Series ENV/2000/1.
Scottish Office Development Department (SODD) (1994),
NPPG 1 : The Planning System.
SODD (1998), Circular 4/1998, The Use of Conditions
in Planning Permissions.
Scottish Office Development Department (1999)
Addendum to Circular 4/1998, Model Planning Conditions.
SEPA (1999), Methodology to Derive Tolerable Daily
Intakes.
SNIFFER (1999), Communicating Understanding of
Contaminated Land Risks.
SNIFFER (2000), Framework for Deriving Numeric
Targets to Minimise the Adverse Human Health Effects of
Long-term Exposure to Contaminants in Soil.
Technical Standards for Compliance with the Building
Standards (Scotland) Regulations 1990, as amended.
www.detr.gov.uk
www.scotland.gov.uk
Footnotes
If land is "contaminated land" and it falls within a
description in paragraphs (a) to (h) of regulation 2(1) of
The Contaminated Land (Scotland) Regulations 2000, then it
is a "special site" (Environmental Protection Act as
amended, Section 78A(3)).
'Harm' means "harm to the health of living organisms or
other interference with the ecological systems of which
they form part and, in the case of man, includes harm to
his property." (Environmental Protection Act as amended,
Section 78A(4)).
The "enforcing authority" is, in relation to a special
site, SEPA, otherwise it is the local authority in which
the "contaminated land" is situated (Environmental
Protection Act as amended, Section 78A(9)).
The "appropriate person" to bear responsibility for
remediation is defined by section 78F of the Environmental
Protection Act as amended.