| Description | PAN 50 Annex D: Controlling the Environmental Effects of Surface Mineral Workings |
|---|
| ISBN | n/a (Web Only) |
|---|
| Official Print Publication Date | |
|---|
| Website Publication Date | February 01, 2000 |
|---|
PAN 50 Annex D: Controlling the Environmental Effects
of Surface Mineral Workings
Annex D: The Control of Blasting at Surface
Mineral Workings
February 2000
Introduction
Background
1. This Annex to PAN 50 Controlling the Environmental
Effects of Surface Mineral Workings provides advice to
planning authorities and the minerals industry on how to
keep the effects of blasting from surface mineral workings
within environmentally acceptable limits. This Annex is
based on the DETR commissioned research by Vibrock Limited
The Environmental Effects of Production Blasting from
Surface Mineral Workings, published by The Stationery
Office 1998 [ISBN 0-11-753412-9] This Annex supersedes the
advice in pages 13 to 15 of PAN 50 Controlling the
Environmental Effects of Surface Mineral Workings.
2. Blasting at quarries and opencast coal sites can have
adverse impacts that extend beyond the site boundary.
Potential environmental impacts of blasting at surface
mineral workings include ground vibration, air
overpressure, noise, dust and flyrock. Where these effects
are perceived at adjacent premises, particularly
residential properties, there can be problems of
reconciling the needs of efficient and economic mineral
extraction with the comfort and well being of the site's
neighbours.
3. Planning authorities should give full weight to the
environmental effects of blasting at surface mineral
workings and the potential disturbance to local
communities. Where a proposal would cause demonstrable and
material harm, permission should not be granted except
where the benefits of the development proposal to the
community would outweigh the potential harm. However, the
planning system can control blasting times, set allowable
levels of ground vibration, control overpressure, ensure
monitoring of vibration levels and control dust and noise.
The Scottish Executive seeks co-operation between operators
and planning authorities so that sensible blasting regimes
can be agreed for individual sites. The reasonable use of
planning controls by planning authorities, in particular
the use of conditions attached to planning permission, is
an important means of ensuring that the effects of blasting
at mineral sites do not pose a threat to the amenity of
communities. Controls should be fair and reasonable, and
should avoid measures that impose costs or constraints on
the operator where there is no real benefit to local
communities.
see NPPG16 Opencast Coal and Related Minerals,
paragraph
4. The advice within this Annex should be used when
considering new applications as well as reviewing and
updating Interim Development Order (IDO) permissions and
other old mineral permissions.
5. The advice within this Annex will also be relevant
when reviewing and updating conditions attached to old
mineral permissions.
Existing Controls
6. Planning authorities have an important role in
controlling the environmental effects of blasting
operations at surface mineral workings, but care should
always be taken to ensure that planning controls do not
conflict or replicate other existing statutory controls. It
is vital that planning authorities are aware of other
existing controls over blasting, so that they can properly
assess proposals and respond to complaints.
7. Blasting operations at surface mineral workings were
controlled by the Quarries (Explosives) Regulations 1988.
These regulations detailed the duties of the site owner,
manager and shotfirer in the conduct of blasting
operations. The health and safety implications of general
quarry operations were controlled by The Quarries
Miscellaneous Health and Safety Provision Regulations 1995.
These regulations provided control over the possibility of
flyrock. Both Regulations have been revoked by The Quarries
Regulations 1999, which came into force on 1 January
2000.
8. Part 3 of the Environmental Protection Act 1990
places a mandatory duty on local authorities to investigate
any complaints of nuisance and then take action where a
nuisance is found, this includes nuisance from noise
emissions and vibration. The relevant British Standard are:
BS 5228 Noise and Vibration Control on Construction and
Open Sites; BS 6472 Guide to Evaluation of Human Exposure
to Vibration in Buildings; BS 7385 Evaluation and
Measurement for Vibration in Buildings.
the need to blast
9. Blasting is not always an essential part of mineral
operations, it is generally only required at rock quarries
and opencast coal workings. However, at these sites the
operators invariably consider blasting as an essential
element of economic mineral extraction. There is usually no
need for blasting at sand and gravel or peat mineral
workings. Blasting may be required as part of the
restoration scheme to create visually acceptable land forms
or provide long term stability of a rock face.
10. Blasting in hard rock quarries is needed to break up
in-situ material which cannot feasibly be removed by
mechanical equipment. The most important factors that
determine whether blasting is necessary are the hardness of
the rock and the type of machinery available for
extraction. In the case of opencast coal sites it is not
the coal itself which may require blasting, but rather the
rock strata or overburden above and in between the coal
seams. The strata often needs to be loosened by the use of
explosives in order that mechanical excavators can remove
the material and thereby gain access to the coal. The need
to blast overburden at opencast coal sites commonly
increases with the depth of the mineral working, since the
deeper layers of overburden contain fewer weaknesses in the
form of joints, particularly in the case of sandstone
layers. If there is uncertainty over whether blasting is
required at an opencast coal site then a precautionary
approach should be taken. It is better for mineral
operators to plan for blasting than not to and find out
that blasting is required once extraction starts.
11. Blasting as a means of rock removal is relatively
expensive. A balance is required between the financial and
environmental costs associated with blasting and the degree
of fragmentation needed for mechanical extraction and/or
crushing operations to be viable. Blasting can also be
disruptive to the continuous operation of a site since
personnel are required to be removed from the immediate
blasting area in order for safe detonation to proceed.
Hence, it is only when the immediate geological conditions
render alternative extraction techniques either impossible
or uneconomical that blasting is considered.
ground vibration
12. When an explosive detonates within a borehole it
causes the rock in the immediate vicinity to crack or
distort. Outside this immediate vicinity of the blast site
permanent deformation does not occur, instead the rapidly
decaying stress waves from the explosion cause the ground
to exhibit elastic properties whereby the rock particles
are returned to their original position as the stress waves
pass. This causes ground vibration to radiate away from the
blast site, the effect reducing as distance increases.
13. It is always in the operator's interest to reduce
both ground and airborne vibration from blast events to the
minimum possible for any specific blast design because it
is this that substantially increases the efficiency, and
therefore, economy of blasting operations. Despite this,
even the best designed and executed blasts will generate a
certain amount of unwanted energy in the form of ground
vibration waves which will radiate away from the blast
location.
Measurement
14. British Standard 7385: Part 1, 1990 discusses the
measurement of vibration in buildings in general terms with
more specific advice for damage investigation given in BS
7385: Part 2, 1993 and for human perception in BS 6472,
1992.
15. There are four interrelated parameters that may be
used in order to define ground vibration magnitude at any
location. These are:
Particle Displacement - the distance that a particle
moves before returning to its original position, measured
in millimetres (mm).
Particle Velocity - the rate at which particle
displacement changes, measured in millimetres per second
(mms -1).
Particle Acceleration - the rate at which the particle
velocity changes, measured in millimetres per second
squared (mms -2) or in terms of the acceleration due to the
earth's gravity (g).
Frequency - the number of oscillations per second that a
particle undergoes measured in Hertz (Hz).
16. In all standards the preferred parameter of
measurement is peak particle velocity (ppv). The
measurement of particles by vibration waves is usually
measured in 3 mutually perpendicular directions, as
particles will be oscillating in 3 dimensions, these
are:
Longitudinal (sometimes termed radial) - back and forth
particle movement in the same direction that the vibration
wave is travelling.
Vertical - up and down movement perpendicular to the
direction the vibration wave is travelling.
Transverse - left and right particle movement
perpendicular to the direction the vibration wave is
travelling.
Magnification Levels
17. The great majority of vibration recordings from
surface mineral workings are undertaken either in order to
demonstrate compliance with the sites planning conditions
or in response to complaints. When recording vibration
following receipt of complaints most commonly the
complainant is concerned over the likelihood of damage to
their property and therefore, in line with good practice
and the guidance given in the relevant British Standard BS
7385, recordings are undertaken outside of property at
ground surface immediately adjacent to the closest facade
to the blast location.
18. It is vibration within a property which people
experience most often and therefore in order to assess
complaints regarding nuisance it may be necessary to
monitor vibration within a property and at a location where
the complainant considers the effects most noticeable in
line with the BS 6472, 1992. These measurements should be
taken in conjunction with those taken outside in order to
be able to quantify any magnification effects.
Magnification levels from 0.5 to 2.0 are most likely within
low rise residential type structures. The actual
magnification will depend upon many factors, but primarily
the frequency content and to a lesser extent the duration
of the incoming vibration and the natural frequencies of
the building or parts of the building concerned.
19. In terms of damage, potential magnification effects
are well known and are allowed for in the relevant
standards. Guide values are invariably related to
recordings to be undertaken at the base of the buildings or
on the ground immediately outside of the building. This is
the case with BS 7385 which also notes that maximum
vibration will be found at mid-span locations on walls or
floors but that such vibration is usually unrelated to
structural integrity.
Effects of Frequency
20. The frequency content of blast vibration is a
significant factor in determining magnification levels and
both human and structural response to vibration. It is very
largely determined by the geological conditions between the
source and receptor, the distance from the source, and to a
lesser extent, blast design and borehole geometry.
21. The more competent or solid the transmission medium,
then the more the high frequency motions tend to be reduced
or filtered out over shorter distances. Thus, ground motion
frequencies will be relatively high when monitored close to
a blast and/or when solid rock is present. Ground motion
frequencies will be relatively low when monitored at a
greater distance from a blast and/or when the transmission
medium is relatively weak, such as clay or soil.
22. The typical range of ground vibration frequency for
surface mineral workings is from 5 to 40 Hz, with levels
predominantly from 20 to 30Hz in the case of hard rock
quarries and 5 to 15Hz in the case of opencast sites with
less competent transmission media. Hence, magnification of
vibration within a structure is, perhaps, more likely with
opencast blasting.
Human Response
23. Human response to blast induced ground vibration is
a relatively complex phenomenon and is dependent upon a
range of factors of which the actual vibration magnitude is
only one and not necessarily the most important. It is well
recognised that the human body is very sensitive to the
onset of vibration albeit very poor at distinguishing
relative magnitudes. Although sensitivity to vibration
varies significantly between individuals, a person will
generally become aware of blast induced vibration at levels
of around 1.5mms -1 peak particle velocity, and under some
circumstances at levels as low as 0.5mms -1.
24. Once a received vibration is greater than an
individual's perception threshold then it is possible for
concern to be expressed about the blasting. Such concern
normally relates to the vibration's potential for causing
damage to the complainant's property. Concern may be
expressed that damage has already occurred due to the
recent discovery of cracking that may have been present for
some time or have been caused by natural processes. More
often, however, concerns are based on the fear that damage
will be caused at some time in the future as a result of
repeated vibration.
25. The degree of concern and whether or not it leads to
complaints is governed by many factors. Perhaps the most
obvious is the vibration itself in terms of its magnitude,
duration and frequency. However, the vibration magnitude at
which complaints arise varies greatly from site to site
such that no common complaint threshold exists. This is
considered to be in part a reflection of the fact that
individuals are very poor at distinguishing between
vibrations of differing magnitudes.
26. The susceptibility of individuals to vibration will
vary from person to person depending on factors such as
age, health and, to a large extent, previous exposure. It
is usually the case that adverse comments are less likely
once a neighbour has become accustomed to the perceived
effects of blasting. An explanation of the need to blast
and the significance of the vibration levels being received
by a site's neighbours are paramount as is an understanding
and sympathetic attitude from the operator.
Effect on Structures
27. When defining damage to residential type structures
the following classifications are used:
Cosmetic or threshold damage - the formation of hairline
cracks or the growth of existing cracks in plaster, drywall
surfaces or mortar joints.
Minor damage - the formation of large cracks or
loosening and falling of plaster on drywall surfaces, or
cracks through bricks/concrete blocks.
Major or structural damage - damage to structural
elements of a building.
28. BS 7385 1993 gives guide values with respect to all
3 of these damage classifications for residential
structures in terms of peak particle velocity and
frequency. These values are based on the lowest vibration
levels above which damage has been credibly
demonstrated.
29. In terms of cosmetic damage, at a frequency of 4 Hz
the guide value is 15mms -1 peak particle velocity,
increasing to 20mms -1 at 15 Hz and 50mms -1 at 40 Hz and
above. Minor damage is possible at vibration magnitudes
that are greater than twice those given for the possible
onset of cosmetic damage with major damage to a building
structure possible at values greater than four times the
cosmetic damage values. These values apply even when a
structure experiences repeated vibration events.
30. Although damage or the fear of damage is the major
concern for neighbours of surface mineral workings the
reality is that vibration levels at adjacent residential
properties rarely if ever even approach the levels
necessary for even the most cosmetic of plaster cracking.
Engineered structures such as industrial and heavy
commercial buildings and underground constructions are able
to sustain higher levels of vibration than those applicable
to residential type properties by virtue of their more
robust design.
31. British Standard 7385: Part 1, 1990 and Part 2, 1993
discusses the resistance of structures to blast induced
vibration and specifies guide values to preclude damage to
various buildings types from blast induced ground
vibration.
Prediction
32. Variations in instantaneous charge weights at any
specific site relate closely to variations in vibration
magnitude. It is this parameter that, together with
distance from the blast, that forms the basis of vibration
prediction.
33. The accepted method of prediction is to plot
measured peak particle velocity values against a scaled
distance value for each measurement. The scaled distance
value is taken as the blast/receiver separation distance
divided by the square root of the maximum instantaneous
charge weight of explosive in the shot from which the
measurement was taken.
34. When a number of such values are plotted on
logarithmic axes a straight line relationship is seen to
exist for any particular site. Taking vibration recordings
at increasing separation distances from a blast ensures
that geological effects are covered and if a number of
blasts at any one site are monitored then variation between
blasts can also be quantified.
35. Vibration transmission may not always be the same in
all directions from a blast site. Vibration recordings may
be required therefore, in different directions in order to
quantify any such differences. It is the upper confidence
level, generally taken as 95%, that forms the basis of most
vibration regulations.
Effects of Geology
36. Once the vibration is generated at source it is the
geology of the intervening ground that will largely
determine the manner in which the vibration is transmitted
and hence the predominant characteristics of the vibration
including its magnitude at any given distance. An important
factor in this regard is the propagation velocity which is
an indirect measure of geological properties that affect
the rate of decay of vibration. The more competent and less
weathered the rock mass then the greater is the propagation
velocity in any particular rock type. However, variations
in propagation velocities within one rock type and between
rock types can be significant, hence the importance of site
specific vibration measurements.
air overpressure
37. Air overpressure is energy transmitted from the
blast site within the atmosphere in the form of pressure
waves. As these waves pass a given position, the pressure
of the air rises very rapidly then falls more slowly then
returns to the ambient value after a number of
oscillations. The maximum excess pressure in this wave is
known as the peak air overpressure, generally measured in
decibels linear (dB).
38. The pressure waves consist of energy over a wide
range of frequencies, some of which are audible and hence
may be sensed in the form of noise, but most are at
inaudible frequencies of less than 20 Hz. This relatively
low frequency component can be sensed by people in the form
of a pressure wave known as concussion. The noise and
concussion together is known as air overpressure.
Measurement
39. Measurement of air overpressure levels must always
be undertaken with microphones that have an adequate low
frequency response in order to fully capture the dominant
low frequency components.
40. Practical problems may arise when measuring air
overpressure under windy conditions since wind is itself a
pressure variation that may mask the blast generated
pressure wave.
41. It is also the case that due to the unpredictable
and uncontrollable effects of prevalent atmospheric
conditions, the location at which the maximum air
overpressure is expected cannot be determined with any
degree of accuracy. Hence, demonstration of compliance with
any specific air overpressure limit is not a practical
possibility.
42. The routine measurement of the air overpressure
level together with groundborne vibration is clearly of
great importance in terms of both public relations and a
clearer understanding of any environmental disbenefit of an
operator's blasting practices.
Human Response
43. Human reaction to a blast event will be in response
to the resulting effects of both ground and airborne
vibration and in particular the combined effects that these
exhibit within a property when secondary noise effects can
be readily induced by relatively low values of air
overpressure or by groundborne vibration alone.
44. Routine blasting operations regularly generate air
overpressure levels at the closest of adjacent property of
around 120 dB. The pressure equivalent of 120 dB will be
generated by a constant wind velocity of just 5ms -1
(Beaufort force 3, gentle breeze) whilst an air
overpressure of 130 dB is equivalent to a wind velocity of
less than 8ms -1 (Beaufort force 4, moderate breeze). Such
magnitudes will be perceived by individuals although they
are entirely safe.
45. The response of an individual to any such event is
dependent upon the same factors as that of groundborne
vibration with the understanding of the phenomenon through
public relations and the attitude of the operators being of
utmost importance.
Effects of Topography
46. Wavelength differences associated with this
frequency range mean that any effects of topography are
likely to be more pronounced for the audible component of
air overpressure rather than the concussive component. Thus
a topographic feature forming a barrier between the blast
site and the receiver may reduce the blast's audible
component but have relatively little effect upon the
concussive component. Whilst any reduction in the audible
nature of an air overpressure wave is to be welcomed such
energy is relatively low within the overall pressure wave
and, therefore, barriers are seen to have little effect
unless they are substantial. For example, man made features
such as acoustic fences and earth amenity bunds commonly
placed along a site's boundaries would not be expected to
reduce to any significant degree the value of air
overpressure received off site, although they are
beneficial in reducing noise from other sources. More
substantial barriers such as a series of quarry faces can
reduce air overpressure values when blasting at depth.
Effects of Meteorological Conditions
47. Because air overpressure is transmitted through the
atmosphere, meteorological conditions such as wind speed
and direction, temperature, cloud cover and humidity will
all affect the intensity of the air overpressure
experienced at a distance from the blast site.
48. If a blast is detonated in a motionless atmosphere
in which the air temperature is constant, then the air
overpressure intensity will decrease purely as a function
of distance and will, once outside of the immediate
vicinity of the blast, reduce by 6 dB as the distance from
source doubles.
49. Such conditions are very rare and it is more usual
for temperature to vary with altitude in a fairly complex
and changing manner. Winds are also invariably present at
differing velocities and directions at differing altitudes.
The overall result is that the nominal 6 dB reduction may
be greater in some directions from the source and less in
others.
50. Given sufficient meteorological data concerning the
relevant parameters of wind speed and direction and air
temperature, and how these vary with altitude, it is
possible to predict these expected increases or decreases.
In practice, however, the data is obtained from
meteorological stations at some distance from the blast
site and at some time before the blast is to be detonated.
As such, it is therefore doubtful whether the data will be
relevant at the specific site and at the proposed time of
blasting, the situation being further complicated by the
variable Scottish weather.
51. Minimising air overpressure at source, such that,
even under unfavourable weather conditions, all such energy
is within acceptable criteria at distance, remains the best
practicable approach. It is an approach that all surface
mineral sites are obliged to follow under the provisions of
The Quarries Regulations 1999.
Effects of Blast Design
52. There are five principal sources of air overpressure
from blasting at surface mineral workings:
- The use of detonating cord which can produce high
frequency and hence audible energy within the air
overpressure spectrum.
- Stemming release, seen as a spout of material from
the boreholes, gives rise to high frequency air
overpressure.
- Gas venting through an excess of explosives leading
to the escape of high-velocity gases, give rise to high
frequency air overpressure.
- Reflection of stress waves at a free face without
breakage or movement of the rock mass. In this case the
vertical component of the ground-vibration wave gives
rise to a high-frequency source.
- Physical movement of the rock mass, both around the
boreholes and at any other free faces, which gives rise
to both low and high-frequency air overpressure.
53. Detonating cord should be used as sparingly as
possible, and any exposed lengths covered with as much
material as possible. Just a few feet of exposed cord can
lead to significant amounts of audible energy and, hence,
high air overpressure levels. Stemming release can be
controlled by detonation technique, together with an
adequate amount of good stemming material. Drill fines,
while readily available, do not make good stemming
material. The use of angular chippings is better. It should
be noted however that detonation cord and stemming release
have been virtually eliminated with the use of in hole
initiation techniques.
54. Gas venting results from overcharging with respect
to burdens and spacings or, perhaps, a local weakness
within the rock, and is also typified by the occurrence of
fly rock. Its control is essential for economic and safe
blasting, and is considerably aided by accurate drilling
and placement of charges, together with regular face
surveys.
noise
55. Although the majority of energy generated within the
atmosphere from any surface mineral blasting will be of a
sub-audible nature, there will also be a component that is
audible, i.e. at frequencies greater than 20 Hz, and as
such can be heard as noise and measured in terms of
dB(A).
see PAN 50 Annex A: The Control of Noise at Surface
Mineral Workings and PAN 56 Planning and Noise
56. Peak levels from blasting are comparable to the sort
of levels typically generated at properties by passing
cars, etc., only in the case of blasting the noise would
exist for around a second and occur relatively
infrequently. It is because of this very brief duration and
its infrequent occurrence that blast noise is rarely
measured in terms of dB(A) but rather looked at as part of
the air overpressure generated and measured by the more
meaningful parameter of dB.
57. If the use of exposed detonating cord is avoided the
characteristic noise of a blast is no longer a sharp crack
but rather a dull thump. This is partly due to the
detonating sequence and partly due to natural energy
dissipation and reduction. Whilst some of the noise
perceived by a neighbouring resident would be directly from
the blast itself, the lower frequency components of the air
overpressure might well induce secondary rattling of
windows and ornaments within a property which could augment
the overall effect.
58. Thus in terms of noise control or reduction the care
and attention to blast design and subsequent
implementation, including initiation, necessary for the
control of air overpressure is equally applicable to
noise.
dust
59. Dust from blasting activities can arise from two
potential activities, namely the drilling of the boreholes
and from their subsequent detonation.
see PAN 50 Annex B: The Control of Dust at Surface
Mineral Workings
60. Drill rigs have potential for the emission of
significant quantities of dust if the waste air that is
vented to atmosphere is not first filtered. Such dust
suppression techniques are commonplace and hence the
relatively high potential for dust emissions from this
source is rarely if ever realised.
61. Detonation of the explosives results in either
ground heave in the case of opencast coal site blasting or
the formation of a rock pile in the case of typical quarry
blasting. Both involve the generation of dust depending
upon specific ground conditions.
62. Mitigation measures can involve the bagging and
removal from the blast zone of the drill returns. An
adequate quantity and quality of stemming material is also
of importance in order to prevent the explosives' rapidly
expanding gases from ejecting such material from the blast
holes and acting as a source of dust generation. This
latter precaution will also reduce the potential air
overpressure and noise generation associated with a blast
event. In practice, however, these measures can only be
partially effective in reducing overall dust emissions that
originate primarily from within the previously undisturbed
rock mass.
flyrock
63. Flyrock is the unexpected projection of blast debris
beyond the designated danger zone as defined by the person
who prepares the specification. This may involve projection
beyond the site boundary in which case the incident must be
reported to the Health and Safety Executive.
Causes of Flyrock
64. The most common causes of flyrock include:
Insufficient Burden - When there is insufficient burden
or stemming on the column of explosive then the potential
for flyrock exists, as the energy released from the
explosive is likely to be greater than that required to
solely fragment the rock mass in its immediate locality
resulting in excess energy available to project rock debris
beyond the danger zone.
Insufficient Training - The Quarries Regulations 1999
state that it is the operators responsibility to ensure
that those dealing with explosives are trained to a
suitable standard. There is already greater awareness of
the need for proper training and this has been reflected in
a reduction in the number of flyrock incidents.
Inadequate Specification Factors - The Quarries
Regulations 1999 give the factors to be considered when
designing blasts and all should be taken into account.
Hole Deviation - This can be in the form of drilling at
the wrong angle in any direction resulting in either
reduced toe burden or toe charges in consecutive holes
being too close together giving too high a concentration of
explosives at one point.
Incorrect Delay Sequence - Care must be taken to ensure
the correct delay sequence is used. Delay periods must be
chosen such that underburdening of subsequent shot holes
does not occur.
Cavity - It has to be recognised that in certain rock
formations, such as some limestones, cavities may exist and
are a potential problem since if inadvertently filled with
explosive they can give rise to a local concentration of
explosives that is too great with respect to the
surrounding rock mass or burden. This can only be countered
by careful checking of the explosive column length during
loading to ensure the explosive is not filling a cavity.
Cavities provide a greater source of danger when using bulk
loading explosive systems due to the faster loading rate
employed.
Explosives in the Stemming Line - Explosives can be
introduced into the stemming line either deliberately in an
attempt to break hard top bands or accidentally usually as
a result of employing bulk loading methods. In both cases
any excess of energy from the rapidly expanding explosives
gases may result in debris projection.
Unforeseen Geological Weakness - This is the most
difficult to detect and counter and is often the main cause
of flyrock.
Weathered or Loose Rock in the Stemming Line - Extra
care must always be taken when blasting operations take
place in these conditions.
Prevention of Flyrock
65. Flyrock can never be completely eliminated. The
number of incidents however can continue to be reduced by
ensuring blasts are carried out exactly to the
specification. Under The Quarries Regulations 1999 a
written specification must be prepared for each blasting
operation to ensure, so far as is reasonably practicable,
that when blasting occurs it will not give rise to danger.
The specification should take account of all possible
causes of flyrock. Should deviations to the specification
occur then management must be informed and be aware of the
potential hazard. Training of all personnel is essential to
ensure these incidents are minimised. Work carried out to
date on methods to reduce flyrock, such as buffer blasting
and the use of blasting nets, has been limited and
inconclusive. Planning authorities can seek advice from the
Health and Safety Executive if they are concerned at the
risk of flyrock.
Risk Based Approach to Flyrock
66. When considering planning proposals involving
blasting the possibility of flyrock should be taken into
account especially if property or public access is nearby.
However, it is not reasonable to sterilise significant
areas of land on the remote possibility that a flyrock
incident may occur at some time in the future. Risk
assessment and its growing acceptance as a safety
management tool means that flyrock danger zone distances
can be based on acceptable risk levels rather than the
potential consequences of infrequent events. Methods of
working should be designed and agreed at the planning
stage. This should include direction of working, face
height and face angle together with expected borehole
diameters, burdens, spacings, explosive type and initiation
system if possible.
limitations of blasting
67. Virtually all aspects of blast design can affect the
performance and efficiency of a blast and therefore the
resulting vibration levels generated at source. The maximum
instantaneous charge weight of explosive, that is, the
maximum explosive charge detonated at any precise instant
of time, has the greatest effect upon vibration levels for
a given optimum design of blast. However, this parameter
cannot be considered alone because it is connected to most
other aspects of blast design, the relationship being
expressed by the term blast ratio. The blast ratio is a
measure of the amount of work per unit of explosive,
measured for example in tonnes of rock per kilogram of
explosives detonated (tonnes/kg), and is dependent upon
virtually all aspects of a blast's design, for example,
hole diameter and depth, burden, spacing, explosives,
loading density and initiation technique.
68. Generally the optimum blast ratio at any specific
site not only gives rise to optimum fragmentation but also
to the minimum ground borne vibration for the specific
blast under consideration. If less than the optimum amount
of explosive is utilised then an increase in ground
vibration occurs, because the lack of sufficient explosive
energy required in order to efficiently fragment the rock
results in an increase of energy transmitted to the
surrounding ground largely in the form of vibration. Thus
the most useful and practical method of reducing ground
vibration levels in order to meet vibration specifications
is to reduce the maximum instantaneous charge weight of
explosive detonated in any blast event whilst maintaining
the blast ratio through reductions in the other relevant
parameters of blast design such as loading density, burden
and spacing.
69. Typically each hole within a blast is detonated
individually by the use of detonators with inherent delay
periods. Thus the maximum instantaneous charge is usually
the maximum amount of explosive on any one specific delay
detonator in any one blast hole. A reduction in
instantaneous charge weight may be obtained by reducing the
total amount of explosive placed into the boreholes drilled
for the blast, typically from 10 to 30 boreholes depending
on the specific site conditions.
70. Deck loading may be employed whereby a relatively
small amount of the column of explosive within the
boreholes is replaced by inert stemming material in order
to separate the explosive into two discrete decks. If each
of these decks is then initiated with detonators of
differing inherent delays then the maximum instantaneous
charge may be virtually halved. Any number of decks within
a blast hole are possible in theory, being limited only by
the requirements of the given blast ratio and the need for
sufficient stemming between the decks so that the
simultaneous detonation of the separate charges is
prevented. Thus, there are relatively few purely technical
limitations on blasting operations in the sense that
maximum instantaneous charges can be reduced in order to
reduce the resulting ground vibration levels as sensitive
locations are approached. In practice several important
considerations must always be recognised:
- Maximum instantaneous charges are, in the absence
of any restrictions, typically of the order of 20 to 40
kg in opencast coal site blasts and 100 to 200 kg at
quarries. Whilst reductions in instantaneous charges by
factors of 2 to 3 by means of decking and/or reductions
in hole depths and diameters may be practicable on
certain sites, depending upon the initial blast
designs, these reductions are only possible whilst
maintaining the require blast ratio. In practice this
has the effect of significantly increasing the number
of boreholes required in order to dislodge the same
volume of material. This increase will in turn
significantly increase the drilling and detonator
costs.
- Even when using optimum blast designs it is the
case that blasting as a means of rock removal is
relatively expensive at both quarries and coal sites.
Because of this, any increase in blasting costs due to
the factors above readily renders blasting operations
uneconomic, albeit technically feasible.
- The economics of surface mineral working are
largely related to a given rate of material removed by
blasting so any significant decrease in the number of
holes drilled per blast will also tend, in practice, to
increase the number of blasts needed to fragment the
same volume of material. This use of smaller, more
frequent blasts leads to smaller but more frequent
vibration impacts. Whether this results in a perceived
improvement in environmental intrusion will depend upon
whether it is the magnitude of the events or the
frequency of their occurrence that is of most concern
to a potential complainant. In each case the balance
between these factors needs to be assessed by
discussion with interested parties.
- Also of importance is the effect that reductions in
burdens and spacings may have upon the variability and
the safety of blasts.
conditions
71. Conditions and their wording should be a matter for
discussion between the planning authority and site operator
and will depend upon the specific details of each
individual site. These details will include the type of
mineral being worked and the form of blasting operation
required for its economic recovery. Conditions should be in
accordance with SODD Circular 4/1998. In all cases, it will
be necessary to ensure that planning conditions accord with
good and safe practice under the Quarries legislation.
Advice can be sought from the Health and Safety Executive
before conditions to control blasting are imposed.
see NPPG 16 Opencast Coal and related Minerals,
paragraphs 53-60, SODD Circular 34/1996 Annex L and SODD
Circular 4/1998
72. It is recommended practice that conditions should
provide for:
- the unacceptable days and times of blasting
operations
- the allowable level of ground vibration
- a scheme by which air overpressure is
controlled
- a scheme of vibration monitoring so that compliance
with the set limits can be demonstrated.
73. All planning conditions should have due regard to
the requirements of The Quarries Regulations 1999.
Accordingly, specific aspects of blast design, such as the
number of boreholes or the amount of explosives to be used,
should not be included in the blasting conditions. Blast
design criteria must always be the direct responsibility of
the site operator as defined by The Quarry Regulations
1999. Flyrock control and warning systems are also integral
parts of these Regulations and as such are not appropriate
subjects of blasting conditions.
74. Conditions should, wherever possible, state the
desired objectives rather than the methods by which they
can be achieved. One exception to this is in respect of air
overpressure, the off-site magnitudes of which are
difficult to always accurately control or predict due to
atmospheric conditions. Accordingly an alternative approach
is suggested whereby a scheme of control of air
overpressure is detailed by the operator for subsequent
agreement with the planning authority.
75. When formulating conditions the following points
require consideration.
Days and Times of Blasting Operations
76. Whilst specific blasting hours should be a matter
for discussion between the planning authority and operator
they should allow, where possible, for blasting to take
place at regular times within specified periods on Mondays
to Fridays. The need for Saturday morning blasting should
be given separate consideration and blasting would not
normally be allowed on Saturday afternoons, Sundays, Bank
Holidays or National Holidays.
77. In the event of an emergency, any conditions should
be able to be relaxed, in which case the planning authority
should be notified immediately of the details of the
event.
78. A public road adjacent or near to a surface mineral
workings may need to be temporarily closed during blasting
operations, for instance when the public road comes within
the designated danger zone. If this is the case, full
consideration should be given to the impact on traffic
caused by the temporary road closure. The relevant roads
authority should be consulted to determine what traffic
management measures are necessary. Restricting blasting to
set times will allow the public to plan journeys and avoid
any temporary road closures.
see PAN 50 Annex C: The Control of Traffic at Surface
Mineral Workings, paragraph 97-99
79. An example of a condition controlling blasting times
is as follows:
No blasting shall be carried out on the site except
between the following times [1000 and 1200 hours] and [1400
and 1600 hours] on Mondays to Fridays and [1000 and 1200
hours] on Saturdays.
There shall be no blasting or drilling operations on
Sundays, Bank Holidays or National Holidays.
The above condition shall not apply in cases of
emergency when it is considered necessary to carry out
blasting operations in the interests of safety. The
planning authority shall be notified in writing immediately
of the nature and circumstances of any such event.
Allowable Ground Vibration Levels
80. Allowable ground vibration levels should be
specified in terms of peak particle velocity measured in
millimetres per second. The recommended criterion is the
maximum of 3 mutually perpendicular directions. It should
be noted that in order to demonstrate compliance with
BS6472, concerning perception, that additional recordings
may be necessary within a building at a point of
disturbance to an occupant. (see paragraph 97)
81. In determining the precise level of peak particle
velocity it should be recognised that imperceptibility is
not a realistic criterion, but that a limit should always
be chosen to minimise groundborne vibration according to
good practice and safe and efficient blasting operations.
As such, the individual circumstances of a particular site
must be considered. Specified values should be compatible
with current guidance on this matter given within the
relevant British Standards publications, namely, BS 6472,
1992 concerning perception and BS 7385, Part 2: 1993
concerning the likelihood of damage.
82. In determining the specific time period,
consideration should be given to the anticipated frequency
of blast events in order that a representative number can
be assessed. It may also be necessary to consider what time
period would be representative of any site variations in
blast locations and/or design where appropriate.
83. In order to be able to assess compliance with the
95% probability criterion, the number of blasts considered
should ideally be 100 or greater. However, in practice it
would be unreasonable to extend the time period greater
than 12 months before an assessment could be undertaken
even if the number of events is relatively small. Blasting
within opencast coal sites is within specific cuts or
linear areas of a site which progress across the excavation
area relatively quickly compared with the progress of
quarry faces. Hence, a suitable time period for an opencast
coal site may be that time typically taken for any one cut
to be fully worked. A minimum time period of 3 months would
generally be considered as sufficient to be representative
of blasting variations within both opencast coal sites and
quarries.
84. The values chosen should recognise the fact that
blasts in practice must be designed so that the intended
level of 95% confidence is rarely approached or exceeded.
In theory therefore, blasts must be designed for mean or
average vibration values of around half of the 95%
confidence level. In practice, more values will in fact be
generated below this average value.
85. Once the threshold of perception is exceeded, the
likelihood of complaints is largely independent of
vibration magnitude but greatly influenced by the
relationship between an operator and the local
community.
86. Generally, individual blasts should not exceed 12
mms -1. Average levels should not exceed 10 mms -1, and
usually will not be below 6 mms -1 in 95% of all blasts.
These levels conform with the BS 6472, 1992 and BS 7385,
Part 2: 1993.
87. Whilst it is recognised that under exceptional
circumstances it may be appropriate that level are set
beyond the range of between 6 to 10 mms -1 such
circumstances should be carefully examined because levels
greater that this may give rise to a likelihood of damage
at properties. Levels lower than the recommended range may
well, in practice, result in a greater number of blasting
events in order to produce the same extraction rate which
could be environmentally counterproductive.
88. Lower levels may need to be considered in proximity
to hospital operating theatres or precision laboratories
where delicate tasks or the use of sensitive equipment may
coincide with blast times. In determining the permitted
vibration levels detailed consideration should be given to
any such potential blasting constraints. A fully reasoned
justification should be given by a planning authority when
they impose a condition requiring vibration levels outside
the recommended range.
89. Historic Scotland should be consulted when it is
considered that blasting at a surface mineral working may
affect a category A listed building or its setting or the
site of a scheduled monument or its setting. If necessary
vibration levels at historic structures may be set below
the recommended range. A condition could require that
monitoring of a historic structure is agreed to the
satisfaction of the planning authority in consultation with
Historic Scotland. This might include a thorough survey of
the building, recording width, length and breadth of all
defects before commencement of blasting and continued
monitoring of defects during blasting operations, until
such time as monitoring indicates that no damage has
occurred due to blasting.
90. An example outline of a condition limiting ground
vibration follows:
Ground vibration as a result of blasting operations
shall not exceed a peak particle velocity of [6 mm -1] [10
mm -1] in 95% of all blasts measured over any period of [6
months] and no individual blast shall exceed a peak
particle velocity of [12 mm -1] as measured at vibration
sensitive buildings. The measurement to be the maximum of 3
mutually perpendicular directions taken at the ground
surface at any vibration sensitive building.
Limiting the Number of Blasts
91. Occasionally permissions include a limitation as to
the number of blasts permitted on a daily or weekly basis,
typically varying from one or two blasts per day to one or
two blasts per week. With the adoption of suitable site
specific vibration criteria such a condition is
unnecessary.
Vibration Sensitive Buildings
92. Planning authorities and mineral operators should
consider the effects of ground vibration on vibration
sensitive buildings. A vibration sensitive building being
any building occupied by a person or persons either on a
regular or irregular basis as a form of dwelling,
workplace, meeting place, etc (for example, residential
property, school, offices, industrial premises, church,
village hall). Such occupation need not necessarily occur
at the time of the blasting event.
Scheme of Air Overpressure Control
93. A scheme which details the intended methods to be
employed in minimising air overpressure from blasting
operations is recommended in preference to limit values, as
previously advised in PAN 50 page 15. This is because of
the nature of this phenomenon and because conditions that
are intended to control its effects need to be both precise
and enforceable. Such a scheme would need to be detailed by
the operator and agreed with the planning authority.
94. Although air overpressure can be controlled to a
great extent at source by careful attention to blast design
and implementation, once detonation occurs the prevailing
atmospheric conditions play a significant role in
determining air overpressure values at distance from the
blast site.
95. A scheme of air overpressure control should
address:
- the adequate confinement of all explosive charges
through sufficient quantity and quality of stemming
material;
- the adequate confinement of all charges by means of
an accurate face survey and subsequent judicious
placement of explosive charges;
- the precautions to be taken in areas known to
exhibit weaknesses in the ground;
- the detonation techniques preferred, including the
practicality of prohibiting the use of surface lines of
detonating cord;
- the practicality of prohibiting the use of
secondary blasting; and
- the procedure to be followed in the event of a
misfire.
96. An example of a condition requiring that a scheme of
air overpressure control is submitted for approval of the
planning authority is as follow:
Prior to the commencement of blasting operations details
of the methods employed to minimise air overpressure from
blasting operations shall be submitted to the planning
authority for written approval. All blasting operations
shall take place only in accordance with the scheme as
approved or with such subsequent amendments as may receive
the written approval of the planning authority .
Scheme of Vibration Monitoring
97. The precise requirements of any scheme for the
monitoring of blast induced vibration should be a matter of
discussion between the planning authority and operator.
Requirements will be site dependent and must take into
account local conditions. Any such scheme should
consider:
- The location and number of monitoring points
Usually the closest vibration sensitive building to
current blasting operations would be the preferred
monitoring location. Where blasting takes place in more
than one area within a site then more than one monitoring
location may be necessary. It may also be appropriate to
monitor at other vibration sensitive locations that are not
the closest to the blast site.
In some situations access to a vibration sensitive
building may not be practicable. In this case,
consideration should be given to the selection of a
location away from the building in a general line with the
area to be blasted and at which monitoring could be
regularly undertaken. Such locations may be at or just
within the site boundary.
- The type of equipment to be used and the parameters
to be measured.
The measurement of vibration should be undertaken using
specialist monitors designed for the purpose of blast
vibration monitoring. Such instrumentation, termed
seismographs, should be capable of recording both ground
and airborne vibration. Ground vibration should be recorded
in terms of peak particle velocity in millimetres per
second and in 3 mutually perpendicular directions. Airborne
vibration should be measured in terms of decibels (dB) or
on a linear scale in terms of pounds per square inch
(p.s.i.).
- How often the measurements are required to be
taken.
It would generally be the case that all blasts are
monitored in order to be able to demonstrate compliance
with a vibration limit. In a situation where measured
vibration levels are relatively low when compared with the
site limit it may be appropriate that only a representative
sample of blasts are monitored over a given time period. In
all cases the scheme should precisely define what is
required.
- The method by which such data are made available to
the planning authority.
The results of monitoring should be freely available to
the planning authority. Typically the results would be kept
at the site and made available for inspection by the
planning authority at all reasonable times with copies
being supplied to the planning authority upon request.
- The method by which such data are used in order to
ensure that the site vibration limit is not exceeded
and to mitigate any environmental effects of
blasting.
Procedures may be specified if recorded values exceed an
agreed level. Typically these procedures would involve
notification of the planning authority of the event
together with an assessment of its implication with respect
to future blasting activity and the site's vibration
limit.
98. An example outline of a condition requiring that a
scheme of vibration monitoring is submitted to the planning
authority for approval is as follows:
Prior to the commencement of any blasting operations a
scheme for the monitoring of blasting including the
location of monitoring points and equipment to be used
shall be submitted to the planning authority for written
approval. All blasting operations shall take place only in
accordance with the scheme as approved or with such
subsequent amendments as may receive the written approval
of the planning authority.
complaints procedures
99. The role of the planning authority and environmental
health officer can be paramount in influencing the level of
concern expressed about blasting operations. Generally
viewed as independent by a site's neighbours, the planning
authority and environmental health officer should be in the
position of being able to investigate such concerns
thoroughly. If concern has been expressed, after having
evaluated the situation they should be able to explain the
significance of the vibration received at property in
comparison with site conditions and recognised standards.
If appropriate they may be in a position to enforce
conditions.
see NPPG4 Land for Mineral Working
100. The following can facilitate this role:
- Maintain regular contact with relevant site
personnel and the local community, preferably by means
of a site liaison committee.
- Liaise with the site operator concerning their
complaints procedure and their site monitoring
procedures.
- Establish the procedures to be followed in the
event of complaints received by the local
authority.
101. A complaints procedure should include the
following:
- A log of the complaint in a specific register to
cover:
the date and time that the complaint was
received;
the nature of the complaint;
the name, address and telephone number
of the complainant; and
- subsequent follow-up details.
- The complainant should be contacted as soon as is
practicable so that a meeting to discuss the complaint
can be arranged.
- Have due regard to the fact that site blasting
activities may be wrongly identified as the prime
source of concern. This may result either from the
source of vibration being wrongly identified by the
complainant or from a general dissatisfaction with the
site due primarily to other reasons.
- Discuss the complaint with the site operator to
explore the possibility of minimising all vibration
irrespective of whether or not the site conditions are
being met.
- Inspect site records to ensure compliance with all
blasting conditions. In the event of non-compliance,
discuss with the operator the methods by which he
intends to conform in future. Consider the necessity
for enforcement action.
Arrange to monitor subsequent blast event or
series of events as appropriate. In some cases it will
be adequate to view the operators results of vibration
monitoring. In other cases local authority staff may
wish to attend the monitoring to check results. Some
local authorities have the necessary equipment and
skills to carry out monitoring themselves, others get
professional assistance when needed. It is a matter for
the planning authority to decide what action to take.
In the event of unattended monitoring it is
advantageous if the instruments used can generate a
time history of any vibration event. - After monitoring, immediately show the results to
the complainant and relate all results to the relevant
site conditions, the relevant British Standards and
Government guidelines, and every day occurrences.
- A written explanation of the situation may be an
appropriate form of reassurance.
- In the case of persistent complaints consider the
involvement of complainants by means of a regular log
of perceived events which will be discussed upon
completion with the site operator.
102. The correct monitoring and recording of
vibration levels from blasting activities is an essential
part of maintaining good public relations and in ensuring
an operator's compliance with blasting conditions. The onus
for carrying out such monitoring should fall on the
operator, with the results being made available to the
planning authority. Conditions are not the appropriate
mechanism to outline the detailed requirements for a scheme
of monitoring. Instead a condition should specify that a
scheme of monitoring should be submitted for the approval
of the planning authority. Detailed requirements for a
scheme of monitoring can be agreed as part of a Section 75
Agreement. Any planning agreements should comply with SODD
Circular 12/1996.
environmental impact assessment
103. The Environmental Assessment Directive (85/337/EC)
has been amended by Directive 97/11/EC which has been
transposed into Scottish planning law by the Environmental
Impact Assessment (Scotland) Regulations 1999 (SEDD
Circular 15/1999). Under the new regulations an
Environmental Impact Assessment will be mandatory for
proposed quarries and opencast mining where the surface
area of the site exceeds 25 hectares. Smaller sites will
continue to be considered for Environmental Impact
Assessment under Schedule 2. It also states that changes or
extensions to Schedule 2 projects already authorised which
may have significant adverse effects on the environment
are, themselves, considered to be Schedule 2 projects.
Guidance on 'Review of Old Mineral Permissions and
Environmental Impact Assessment' can be found in SODD
Circular 25/1998.
see PAN 58 Environmental Impact Assessment and SODD
Circular 25/1998
104. The effects of blasting could be among the issues
to be addressed in the assessment. The planning authority
may wish to specify that the assessment includes blasting
trails in order to establish the actual ground vibration
and air overpressure levels and their environmental impact.
However, in some instances it may not be appropriate to
carry out full scale test blasting. In such cases data from
a comparable surface mineral working may be helpful in
understanding the effects from blasting.
105. The planning authority may also wish to specify
that the assessment addresses the impact of ground
vibration and air overpressure on wildlife. Bodies such as
Scottish Natural Heritage, Scottish Wildlife Trust and the
Royal Society for the Protection of Birds can be valuable
sources of information and advice on wildlife. Planning
authorities and operators should be aware of the protection
provided by the European Community Habitats and Bird
Directives.
see NPPG 14 Natural Heritage and SOEnvD Circular 6/1995
Habitats and Birds Directive
development plans
106. Development plans should provide clear guidance to
mineral operators and the public as to the consideration
that will be relevant in assessing planning applications.
This will include policies to ensure protection of the
environment. Standards should therefore be identified which
are judged necessary to control the environmental effects
of blasting. Mineral operators should be guided by this as
to the need to mitigate blasting disturbance and
incorporate appropriate controls within any proposals for
mineral extraction.
see NPPG4 Land for Mineral Working
107. In preparing their development plans, planning
authorities should have regard to the need to protect
communities and areas prized for their environmental,
historic, recreational or amenity value from the
environmental effects of blasting. In drawing up policies
in their development plans, planning authorities will wish
to consider the advice in this Annex on the steps that
might reasonably be taken to control blasting and also the
approach to setting blasting controls that will be
incorporated in planning conditions. Where the planning
authority proposes to include development plan policies
that go beyond the British Standards a fully reasoned
justification should be provided.
implementation and review
108. This Annex provides the basic framework for the
consideration of blasting at surface mineral development
proposals and for the monitoring and control of
operations.
109. The Annex has been based on the best information
currently available. It may need updating in the future to
reflect changes in technology and environmental standards,
and in the light of any future relevant research
findings.
110. This advice for controlling the environmental
effects of blasting should at all times be considered in
the light of the requirements of the appropriate
legislation, specifically The Quarry Regulations 1999 must
always take precedence.
note
Enquiries about the contents of this PAN should be
addressed to Ben Train, Scottish Executive, Development
Department, Planning Services Division, Room 2H, Victoria
Quay, Edinburgh, EH6 6QQ, (0131 244 7532) or by e-mail
ben.train@scotland.gov.uk
Further copies, together with other PANs, can be obtained
by contacting Lynn Jameson at the same address. (Tel: 0131
244 7543, e-mail:
lynn.jameson@scotland.gov.uk)
NPPGs and Circulars are available from Planning Division
(Tel: 0131 244 7067, e-mail:
planningdivision@scotland.gov.uk)
This PAN, along with other planning series documents is
accessible within the Scottish Executive web-site at
www.scotland.gov.uk/planning
summary: good practice on blasting
Planning authorities should:
- Provide guidance in development plans to mineral
developers on the appropriate development control
criteria for blasting that will be used in determining
planning applications for mineral development.
- Consider the need to agree or specify planning
conditions relating to:
- The allowable level of ground vibration to meet the
95% confidence level monitored over an appropriate
period;
- A scheme by which air overpressure is controlled;
- A scheme of vibration monitoring so that compliance
with set limits can be demonstrated; and
- The unacceptable days and times of blasting
operations.
- Consider the need for an Environmental Impact
Assessment and whether blasting should be amongst the
issues it addresses.
- Maintain regular contact with relevant site
personnel and the local community, preferably by means
of a site liaison committee.
- Liaise with the site operators concerning their
complaints procedure and their site monitoring
procedures.
- Establish the procedures to be followed when the
local authority receives complaints.
- Ensure monitoring and recording of vibration levels
from blasting activities to maintaining good public
relations and ensure an operator's compliance with
blasting conditions. Where a planning authority has no
access to monitoring equipment they may consider
attendance at monitoring by the site operator.
Mineral operators should:
- Ensure that the blast area is accurately surveyed
and recorded according to The Quarries Regulations
1999.
- Ensure that the correct design relationship exists
between burden, spacing, and hole diameter.
- When bench blasting choose the correct burden with
due regard to the local geological conditions and the
face survey information.
- Drill accurately in order to maintain the intended
blast pattern and keep subdrilling to the minimum
required.
- Ensure there is an adequate dust collection system
for each drill rig.
- Bag and remove all collected dust from the
immediate blast zone.
- Make maximum use of existing free faces.
- If necessary, revise the intended blast design
following inspection of the survey data.
- Ensure that the maximum amount of explosive on any
one delay interval, the maximum instantaneous charge,
is optimised by considering:
- reducing the number of holes per detonator delay
interval
- reducing the instantaneous charge by in-hole delay
techniques
- reducing the bench height or hole depth
- reducing the borehole diameter
- Ensure that the optimum blast ratio is maintained
in any changes of blast design.
- Ensure that the detonator delay sequence optimises
the internal free faces developed during the detonation
sequence, particularly in multiple row blasting and in
corners.
- When practicable ensure that the direction of
detonation is away from the nearest vibration sensitive
location.
- Have due regard for any local weaknesses in the
strata, including back break from any previous shot,
clay joints, and fissured ground.
- If loading explosives through fissured or broken
ground, or through cavities of any kind, consider only
the use of pre-packaged explosives and/or check the
hole depth regularly during loading.
- Whenever possible the use of unconfined charges
should be avoided; also consider prohibiting surface
lines of detonating cord and secondary blasting.
- All surface detonators and explosives should be
adequately covered with suitable material.
- Stemming material should be of sufficient quantity
and quality to confine adequately all explosives upon
detonation. A coarse stemming material such as angular
chippings should be considered for use. Drill fines
should not be used.
- Consider bottom initiation in preference to top
initiation.
- Misfire procedures should have due regard to
under-burdened charges.
- If air overpressure levels are a problem give
consideration to a reduction in the area to be blasted.
Blast at regular times, ideally on the hour. - Regularly monitor the ground and airborne vibration
generated by blasting events so the information can be
employed in any necessary modification of future blast
designs.
- Maintain good public relations with those who live
and work near the blasting site.
- Always attempt to minimise the resulting
environmental effects of blasting operations and
recognise the fact that the perception of blasting
events occurs at levels of vibration well below those
necessary for the possible onset of the most cosmetic
of damage; but nevertheless at levels that can concern
neighbours.
- Be aware that relatively small changes in blast
design can produce noticeable differences in
environmental emissions and that it is very often in
response to changes in these emissions rather than
their absolute value that complaints may be made.
glossary of technical terms
Air Overpressure: A pressure wave in the atmosphere
produced by the detonation of explosives. Consists of both
audible (noise) and inaudible (concussion) energy.
Bench blasting: A method of blasting in quarries and
opencast sites by means of steps or benches with holes
positioned parallel to the bench face.
Blasting nets: Nets manufactured usually from heavy
section steel mesh which are placed over the blasting area
in an attempt to reduce flyrock.
Buffer blasting: The practice of firing a second shot
before completely excavating the previous shot. This is
usually an attempt to reduce flyrock.
Burden: The distance measured at right angles between a
row of holes and the free face, or between rows of
holes.
Concussion: The inaudible energy within the air
overpressure generated by the detonation of explosives.
dB: Decibel, a unit of measure on a logarithmic scale
used to quantify pressure fluctuations such as those
associated with air overpressure.
dB(A): Decibels measured within an A weighted frequency
curve that differentiates between sounds of different
frequency in a similar way to the human ear.
Deck loading: Dividing the borehole to be charged with
explosives into two or more sections usually to reduce the
instantaneous explosive charge. The space between the
separate charges or decks is filled with stemming
material.
Drill fines: Material displaced from the borehole during
drilling.
Flyrock: The projection of material from the blast site
to any area beyond the designated danger zone.
Free face: A rock surface bounded by air.
Frequency: The number of cycles per second of a
vibration usually expressed in units of Hertz, Hz.
Maximum Instantaneous Charge Weight: The maximum amount
of explosive detonated at any one precise time.
Three Mutually Perpendicular Directions : The three
dimensions which particles oscillate in; longitudinal,
vertical and transverse. See paragraph 16.
Peak Particle Velocity: A measure of ground vibration
magnitude which is the maximum rate of change of ground
displacement with time, usually measured in
millimetres/second.
Secondary blasting: The blasting of rock which has not
been adequately fragmented by the primary blast. Also
called plaster blasting.
Stemming: An inert material used to confine or separate
explosives loaded into a borehole, typically stone
chippings.
Toe: The bottom of a borehole
Toe burden: The distance between the blasthole and the
free face measured at the floor of the bench.
Vibration sensitive building: Any building occupied by a
person or persons either on a regular or irregular basis as
a form of dwelling, workplace, meeting place, etc.
bibliography
Legislation:
Environmental Protection Act 1990
Health and Safety, The Quarry (Explosives)
Regulations 1988, SI No. 1930
Health and Safety, The Quarries and Miscellaneous
Health and Safety Provisions Regulations 1995, SI No. 2036
Health and Safety, The Quarry Regulations 1999, SI
No. 2024. (Came into force on 1 January 2000)
National Planning Policy Guidelines
(NPPGs):
NPPG 4 Land for Mineral Working
NPPG 14 Natural Heritage
NPPG 16 Opencast Coal and Related Minerals
Planning Advice Notes (PANs):
PAN 50 Controlling the Environmental Effects
of Surface Mineral Workings
PAN 50 Annex A The Control of Noise at Surface
Mineral Workings
PAN 50 Annex B The Control of Dust at Surface Mineral
Workings
PAN 50 Annex C The Control of Traffic at Surface
Mineral Workings
PAN 56 Planning and Noise
PAN 58 Environmental Impact Assessment
British Standards and Guidance:
British Standard 7385: Part 1, 1990, Evaluation and
measurement for vibration in buildings. Guide for
measurement of vibration and evaluation their effects on
buildings
British Standard 7385: Part 2, 1993, Evaluation and
measurement for vibration in buildings. Guide to damage
levels from groundborne vibration
British Standard 6472, 1992, Guide to evaluation of
human exposure to vibration in buildings (1Hz to 80 Hz)
British Standard 5228: Part 3, 1997, Noise and
vibration control on construction sites, Part 3.Code of
practice applicable to surface coal extraction by opencast
methods.
Circulars:
SODD Circular 26/1994 The Environmental
Assessment (Scotland) Amended Regulation 1994
SOEnvD Circular 6/1995 Habitats and Birds Directive
SODD Circular 12/1996 Planning Agreements
SODD Circular 34/1996 Annex L Illustrative Guide to
Conditions
SODD Circular 4/1998 The Use of Conditions in
Planning Permissions
SODD Circular 25/1998 Review of Old Mineral
Permissions and Environmental Impact Assessment
SEDD Circular 15/1999 The Environmental Impact
Assessment (Scotland) Regulations 1999
Other Relevant Publications:
The Environmental Effects of Production Blasting from
Surface Mineral Workings. (Vibrock Ltd, in association with
University of Leeds, Department of Mining and Mineral
Engineering and Swift Research Partners, 1998, The
Stationery Office, ISBN 0 11 753412 9) This contains a full
bibliography of blasting related publications.