| Description | Circular 25/1998 |
|---|
| ISBN | n/a (Web Only) |
|---|
| Official Print Publication Date | |
|---|
| Website Publication Date | November 30, 1998 |
|---|
Circular 25/1998
REVIEW OF OLD MINERAL PERMISSIONS AND ENVIRONMENTAL
IMPACT ASSESSMENT
NOTES FOR GUIDANCE
The Chief Executive Local Authorities
Copy to: The Director of Planning
Our ref: PGJ/5/7
November 1998
Planning Series:
National Planning Policy Guidelines (NPPGs) provide
statements of Government policy on nationally important
land use and other planning matters, supported where
appropriate by a locational framework.
Circulars, which also provide statements of Government
policy, contain guidance on policy implementation through
legislative or procedural change.
Planning Advice Notes (PANs) provide advice on good
practice and other relevant information.
Statements of Government policy contained in NPPGs and
Circulars may, so far as relevant, be material
considerations to be taken into account in development plan
preparation and development control.
INTRODUCTION
1. The Court of Appeal ruled in the Wensley Quarries
case (RvNorth Yorkshire County Council
exparte Brown and Cartwright) that the
determination of applications for new planning conditions
under Schedule2 of the Planning and Compensation Act 1991
(in Scotland, these provisions were subsequently
incorporated into the Town and Country Planning (Scotland)
Act 1997 ("the Act") at PartII of Schedule8), constitutes
"development consent" for the purposes of the 1985 EEC
Directive on Environmental Assessment
(Directive85/337/EEC). The effect of this ruling is that
English MPAs must
consider the need for EA in all such cases and
require (under Article5 of the Directive) EA for
those projects likely to have significant environmental
effects before development consent can be granted. Where EA
is needed it must be carried out before new conditions can
be determined.
2. North Yorkshire County Council (NYCC) have obtained
leave from the House of Lords to appeal against the
decision of the Court of Appeal. At the time of preparation
of this guidance the House of Lords had not heard the
appeal. The Court of Appeal judgement is not legally
binding in Scotland. However, because of the identical
legislative framework and the equal applicability of the EC
Directive, it must be assumed that the ruling is of similar
relevance to Scotland.
3. The Secretary of State is therefore drafting, on a
contingent basis, regulations under Section2(2) of the
European Communities Act 1972 to adapt the review
procedures in the Act to enable requirement of EA in
appropriate cases. Any such regulations can only apply to
applications for determination of conditions made on or
after the regulations come into force. The Secretary of
State will be consulting on draft regulations as soon as
possible. In the meantime the following approach should be
adopted in relation to current applications and
appeals.
4. The Secretary of State cannot give an authoritative
interpretation of the law; that is a matter for the Courts.
However, it is hoped that this guidance will be of use to
authorities and the minerals industry in the preparation
and consideration of applications for the determination of
conditions under Schedules8, 9 and10 of the Act made in the
period before the new regulations come into force.
WHAT IS THE PROBLEM?
5. The Appeal Court emphasised that its conclusion was
specific to the statutory scheme under consideration (the
review of IDO permissions under Schedule8 of the Act).
However, the Secretary of State considers that its
reasoning must apply also to Old Mineral Permission (OMP)
reviews under Schedule9 as these follow a virtually
identical process to IDOs, and to Periodic Reviews under
Schedule10.
6. It was common ground between the parties before the
Court of Appeal that the EEC Directive had direct effect;
iethat the provisions of the Directive apply regardless of
whether they have been transposed into UK domestic law.
However, in the Secretary of State's view the Directive can
have direct effect only to require authorities and him to
use the powers they already enjoy under the legislation in
such a way as to give effect to the Directive, in so far as
it is possible.
7. A particular difficulty arises from the structure of
the present statutory schemes. In most schemes for the
award of development consent if a developer fails to supply
information, and the competent authority refuses to grant
development consent, the consequence is that the developer
cannot proceed with the project. In the case of reviews of
old mineral permissions, however, failure by an authority
to determine an application for conditions results in the
confirmation of the conditions proposed by the developer
(see paragraph14(6)(b) of Schedule8; and paragraph9(8) of
Schedule9): in other words development consent for the
project is granted.
8. Similar, though slightly different, difficulties
would arise were the Secretary of State to refuse to
determine an appeal unless the developer supplied the
information required by Article5 of the Directive. The
consequence would be that the appeal would remain pending,
and the original conditions, if any, would continue to
apply.
DEALING WITH THE PROBLEM- A VOLUNTARY
APPROACH
9. Projects which require EA under the Directive
(ieSchedule1 projects, and Schedule2 projects likely to
have significant effects on the environment), must be made
subject to an environmental assessment before development
consent is given. In the context of old mineral
permissions, the Secretary of State takes the view that in
determining whether a project is likely to have significant
effects on the environment, it is that part of the project
which remains to be carried out that is relevant. It
follows, therefore, that an EA must supply information
about the effects of the whole of the mining operation yet
to be carried out.
10. However, Schedules8, 9 and10 of the Act do not
contain any explicit power for an authority to require EA
before determining an application for new conditions and,
conversely, provide that where an authority fails to
determine such an application within 3months (or such
longer period as the applicant may agree in writing) the
conditions submitted by the applicant are deemed to be
approved. Similarly, whilst the 3month time limit does not
apply to the Secretary of State's determination of appeals,
the Secretary of State has no explicit power to require
EA.
11.
The Secretary of State therefore strongly advises
that the best approach for both the industry and
authorities is voluntarily to apply the principles of the
Environmental Assessment (Scotland) Regulation
1988. That is, where the authority indicate that
the project is one which they believe should be subject to
EA, the applicants should voluntarily carry out EA and
submit an Environmental Statement (ES) within a reasonable
timescale
and agree an extension of time for the
authority's determination of their application once the ES
has been submitted. Similarly, the Secretary of State
expects appellants to respond positively to requests where
he considers EA necessary in relation to appeals where one
has not been carried out previously.
12. Where an authority indicates that they do not
consider EA necessary they should proceed to determine the
application in the normal way. The Secretary of State will
adopt a similar approach in respect of appeals.
13. The Secretary of State hopes that the minerals
industry will co-operate fully with a voluntary approach,
not least in view of the forthcoming general application of
the requirement for the need for EA to be considered when
the 1997 Amending Directive on EA (Directive97/11/EC) takes
effect in the UK on 14March 1999.
14.
However, failing a fully voluntary approach, the
Secretary of State considers that the following procedures
can, and should be adopted.
15. Authorities must consider in relation to each
application whether the project for which consent is sought
is likely to have significant effects on the environment.
If so, and the application does not contain the information
required by Article5 of the Directive, authorities must
request that information from developers.
SCHEDULE 8 OF THE 1997 ACT
16. Although there is no express statutory basis for
such requests under the Act the Secretary of State
considers that there is an implicit power to require any
additional information necessary to determine an
application. Authorities should accompany their requests
with an invitation to the applicant to agree an extension
of time. However, even where an extension of time is
agreed, an authority cannot wait indefinitely for
information to be provided, because to do so would be to
prolong indefinitely the continuance of the existing
conditions. Accordingly, if the information required to
make an environmental assessment is not provided within a
reasonable period, or the applicant refuses to agree an
extension of time the MPA should impose the conditions
necessary to protect the environment on a precautionary
basis by considering the possible effects of the project,
assuming the worst case applies, and formulating conditions
accordingly.
SCHEDULES 9 AND 10 OF THE ACT
17. In relation to applications, the Secretary of State
takes the view that the powers in paragraph9(9) of
Schedule9 or paragraph6(8) of Schedule10 are sufficiently
wide to request the necessary information. Where these
powers are used, it may not be necessary to agree an
extension of time, because time runs from the date on which
the authority receives the information requested. However,
again, if the information required to make an environmental
assessment is not provided within a reasonable period, or
the applicant refuses to agree an extension of time (if
required) the authority should impose the conditions
necessary to protect the environment on a precautionary
basis.
18. In relation to sites classified as dormant sites
under Schedule9 of the Act, it should be remembered that
because working cannot lawfully recommence until new
conditions have been determined, a request for
environmental information under paragraph9(9) would prevent
reactivation of the site until the necessary information
had been supplied and new conditions determined.
APPEALS
19. In the case of appeals, the Secretary of State
considers that there is an implicit power for him to
request additional information necessary to determine the
appeal.
20. The Secretary of State would not expect it to be
necessary to require EA in every case. But where no
consideration has been given to the need for EA at the
application stage, he will wish to assess whether EA would
be appropriate before determining the appeal. Where the
Secretary of State considers that EA is necessary he will
request the appellant, within a reasonable timescale, to
provide the information required by Article5. This will be
dependent on the complexity of the case, but is not likely
to be less than 4months.
21. If the required information were not provided by the
appellant within a reasonable timescale, the Secretary of
State considers that it would be open to him to conclude
that the appellant was responsible for undue delay within
paragraph18(3) of Schedule8 of the Act; and, after giving
the requisite notice, to dismiss the appeal or determine
the appeal in accordance with the precautionary
principle.
REFERENCE OF APPLICATIONS TO SECRETARY OF
STATE
22. In the case of applications referred to the
Secretary of State under paragraph19 of Schedule8, or under
paragraph13 to Schedule9 or paragraph8 to Schedule10, he
considers that there is an implicit power under the Act for
him to require information, whether in respect of EA or
anything else, and that he is entitled to request the
information required by Article5 of the Directive. Where
the Secretary of State considers that EA is necessary
before determining an application that has been referred to
him, he will ask the appellant to supply that information.
If the appellant refuse to supply the information, or
refuses to do so within a reasonable timescale, he will
determine the application in accordance with the
precautionary principle.
CONDITIONS, APPLICATIONS AND APPEALS ALREADY
DETERMINED WITHOUT CONSIDERATION OF THE NEED FOR
EA
23. Minerals review cases which have already been
determined under the Act, and which are outside the
judicial review time limits, cannot be subject to judicial
review without the leave of the Court. Those cases which
are still within the judicial review time limits may be
open to judicial review, as may any cases determined
without consideration of the need for EA in future.
Interested parties should always seek their own legal
advice about the course to be followed in particular
cases.
COMPENSATION
24. The compensation regimes for reviews of mineral
planning permissions under the Act are unaffected by the
Wensley Quarries judgement and have not changed. Should
consideration of environmental information result in
conditions which incur a compensation liability it remains
payable by the authority.
FURTHER COPIES AND ENQUIRIES
25. General enquiries about this Circular should be
addressed to IanMitchell, The Scottish Office Development
Department, Planning Division, 2-H32, Victoria Quay,
Edinburgh, EH66QQ (Telephone0131-244-7062). Further copies
and a list of current planning Circulars may be obtained
from MissKelly Wood at the same address
(Telephone0131-244-7066).