| Description | Circular 4/1998 |
|---|
| ISBN | n/a |
|---|
| Official Print Publication Date | |
|---|
| Website Publication Date | January 01, 1997 |
|---|
Contents |
Listen
Circular 4/1998
COMPLETION OF DEVELOPMENT
Completion of Whole Development
53. A condition requiring that the whole of the
development permitted be completed is likely to be
difficult to enforce. If a development forming a single
indivisible whole, such as a single dwellinghouse, is left
half-finished, it may be possible to secure completion by a
completion notice under section61 of the Act. If, however,
the reason for failure to complete is financial
difficulties experienced by the developer, neither a
completion notice nor the enforcement of conditions would
be likely to succeed. In such circumstances, the only
practical step open to the planning authority, if they wish
to secure the completion of the development, would be to
carry it out themselves following acquisition of the land.
If a large development, such as an estate of houses is left
half-complete, this may be due to market changes (for
example, a shift in demand from four-bedroom to two-bedroom
houses) and it would clearly not be desirable to compel the
erection of houses of a type for which there was no demand.
Conditions requiring the completion of the whole of a
development should, therefore, not normally be imposed.
Completion of Elements of a Development
54. Conditions may be needed, however, to secure that a
particular element in a scheme is provided by a particular
stage or before the scheme is brought into use, or to
secure the provision of an element of a kind a developer
might otherwise be tempted to defer or omit. Thus it may be
desirable to require that a new access to the site should
be constructed before any other development is carried out;
or, where an office scheme includes a car park, that the
car park is completed before the offices are occupied; or,
where the scheme includes both offices and housing, that
the offices should not be occupied before the houses are
complete. The approach adopted must, of course, be
reasonable. Taking the last example, it could well be
unacceptable to require that the houses should be completed
before the offices are begun; this would be likely to be an
unjustifiable interference with the way the development is
carried out. Or, to take another example, it could well be
unacceptable to demand that all the requirements of a
landscape condition should be complied with before a
building is occupied; this could involve the building lying
empty for many months, since such a condition will often
provide for a considerable maintenance period so that trees
can become established.
PHASING
55. Conditions may also be imposed to ensure that
development proceeds in a certain sequence where some
circumstances of the proposal, for example the manner of
infrastructure provision, makes this necessary. A condition
delaying development over a substantial period is a severe
restriction on the benefit of the permission granted. If
land is available for a particular purpose, its
commencement should not be delayed by condition because the
authority have adopted a system of rationing the release of
land for development.
TRAFFIC AND TRANSPORT
56. The Government is planning to publish a White Paper
in 1998 setting out its new integrated transport policy.
This will aim, for example, to offer genuine choice to the
travelling public by promoting more integrated public
transport systems and to address the problems of congestion
and transport related pollution. New planning guidance and
advice flowing from the new policy will be issued in due
course and it is likely that this will have implications
for the level of parking provision which it would be
appropriate to prescribe in planning conditions. Subsequent
paragraphs need to be read against this general
background.
Parking, Public Transport, Walking and
Cycling
57. Developments often generate extra traffic, usually
in the form of haulage or delivery vehicles or cars of
residents, visitors or employees. Unless this demand is
minimal (as it might be, for example, in the case of some
very small firms) and unlikely to cause obstruction, space
may need to be provided for off-street parking. Any
conditions specifying the number of parking spaces should
be consistent with the development plan as well as
transport policies for the area. They also need to be
reasonable in relation to the size and nature of the
development and to satisfy the tests referred to in
paragraph12.
58. Normally a parking site separate from the road will
be needed. In this case, conditions should ensure, where
necessary, that space is provided for the turning of
vehicles so that they do not have to reverse on to the
road. Where the authority decides that it is appropriate to
require the provision of car parking spaces on other land
under the control of the applicant, the development must be
readily accessible from the car park.
59. In certain circumstances, developers may enter into
a planning agreement with the planning authority to provide
off-site parking or to contribute to other transport
measures directly related to the development, for example
to assist public transport or walking and cycling. The
provisions of such agreements should reflect Government
policy as set out in SODD Circular12/1996.
Access
60. Where a service road is needed as part of a large
development for which outline permission is to be granted,
it may be necessary to impose a condition requiring all
access to the main road to be by means of the service road.
If such a condition is not imposed at outline stage it may
not be possible to secure the objective at a later stage
(see paragraph42). Similarly, if it is desired that there
should be no direct access on to a main road, or that
access must be taken from a particular side road, a
condition to that effect should be imposed on the outline
permission, as without such a condition these restrictions
could not normally be introduced when details are being
considered.
61. A condition may require the provision or improvement
of a service road or means of access even if such works are
not included in the application, provided that they can be
undertaken on the site in respect of which the application
is made, or on other land which is under the control of the
applicant, and relates to the proposed development. The
condition should be framed so as to require the laying out
or improvement of the means of access on the relevant
section of the service road on defined land before the
relevant buildings are occupied.
62. In considering the imposition of conditions
concerning "access", planning authorities should bear in
mind the definition of "road" in section277 of the Town and
Country Planning (Scotland) Act 1997 which refers to the
definition in section151 of the Roads (Scotland) Act
1984:
"any way (other than a waterway) over which there is a
public right of passage (by whatever means) and whether
subject to a toll or not and includes the road's verge, and
any bridge (whether permanent or temporary) over which, or
tunnel through which, the road passes and any reference to
a road includes a part thereof."
Roads fall into 2particular categories- "public roads"
and "private roads", defined in section151 of the Roads
(Scotland) Act 1984. The former are those included in a
list of public roads kept by the roads authority and such
roads are managed and maintained by the authority. Private
roads are those over which the public has a right of
passage but whose maintenance is not the responsibility of
a roads authority. Such roads are maintainable privately
but they are not private in any other way. They are not
included in the list of public roads but there is provision
in the 1984 Act under which they can be added to the roads
authority's list provided they are of adoptable standard.
There is sometimes confusion as to what is a private road
and that term is often associated in the public mind with,
for example, driveways up to private houses. These are not
"roads" in terms of the Roads (Scotland) Act as there is no
public right of passage over them (anyone using them does
so on the sufferance of the owner) and they are, in fact,
private accesses. Planning authorities should ensure that
prospective developers are fully aware of the significant
difference between a private access and a private road.
"Private road" marked on a plan indicates that the public
will have a right of passage over the land comprising the
road: the developer will be required to seek from the roads
authority a separate written consent to build such a road
and it must be constructed to the standard required by that
authority.
Lorry Routing
63. Planning conditions are not an appropriate means of
controlling the right of passage over public roads.
Although negatively worded conditions which control such
matters might sometimes be capable of being validly imposed
on planning permissions, such conditions are likely to be
very difficult to enforce effectively. It may be possible
to encourage drivers to follow preferred routes by posting
site notices to that effect, or by requiring them to use a
particular entrance to (or exit from) the site. But where
it is judged essential to prevent traffic from using
particular routes, the appropriate mechanism for doing so
is by means of an Order under section1 of the Road Traffic
Regulation Act 1984.
Cession of Land
64. Conditions may not require the cession of land to
other parties, such as the roads authority.
DEVELOPMENT OF CONTAMINATED SITES
Contaminated Land
65. Land formerly used for many purposes, including
industry and waste disposal can be contaminated by
substances that pose immediate or long-term hazards to the
environment or to health, or which may damage buildings
erected on such sites. Contaminants may also escape from
the site to cause air and surface or groundwater pollution
and pollution of nearby land. The emission of gas or
leachate from a landfill site may be particularly
hazardous. In these circumstances, appropriate conditions
may be imposed in order to ensure that the development
proposed for the site will not expose future users or
occupiers of the site, buildings and services, or the wider
environment to risks associated with the contaminants
present. Planning authorities should, however, base any
such conditions on a site-specific assessment of the
environmental risks which might affect, or be affected by,
the particular proposed development. Conditions should not
duplicate the effect of other legislative controls. The
contaminated land should be remediated to a standard which
is suitable for the proposed use.
66. If it is known or strongly suspected that a site is
contaminated to an extent which would adversely affect the
proposed development or infringe statutory requirements, an
investigation of the hazards by the developer and proposals
for remedial action will normally be required before the
application can be determined by the planning authority.
Any subsequent planning permission may need to include
planning conditions requiring certain remedial measures to
be carried out.
67. In cases where there is only a suspicion that the
site might be contaminated, or where the evidence suggests
that there may be only slight contamination, planning
permission may be granted subject to conditions that
development will not be permitted to start until a site
investigation and assessment have been carried out and that
the development itself will incorporate any remedial
measures shown to be necessary.
68. Conditions might also be imposed requiring the
developer to draw to the attention of the planning
authority the presence of significant unsuspected
contamination encountered during redevelopment. The
planning authority may then require the developer to take
further remediation action under public health duties.
Further guidance on contaminated land is contained in
NPPG10-
Planning and Waste Management. PAN33-
Development of Contaminated Land and PAN51-
Planning and Environment Protection. A new regime
for identifying and remediating contaminated land is being
introduced through the provision of the Environmental
Protection Act 1990, as amended by the Environment Act
1995. This uses a risk-based approach in identifying
contaminated land and applies the polluter pays and
'suitable for use' principles. The role of the planning
system in addressing contamination will continue alongside
the new regime.
ENVIRONMENTAL ASSESSMENT
69. For projects subject to environmental assessment,
conditions attached to a grant of planning permission may
incorporate monitoring and mitigation measures proposed in
an environmental statement where such conditions meet the
criteria summarised in paragraph12. It may be appropriate
to impose conditions on the grant of planning permission
and in the light of the environmental assessment, to
require a scheme of mitigation covering matters of planning
concern to be submitted to and approved in writing by the
planning authority before any development is undertaken.
Again conditions should not duplicate the effect of other
legislative controls. In particular, planning authorities
should not seek to substitute their own judgement on
pollution control issues for that of the bodies with the
relevant expertise and the statutory responsibility for
that control.
NOISE
70. Noise can have a significant effect on the
environment and on the quality of life enjoyed by
individuals and communities. The planning system should
ensure that, wherever practicable, noise-sensitive
developments are separated from major sources of noise and
that new development involving noisy activities should, if
possible, be sited away from noise-sensitive land uses.
Where it is not possible to achieve such a separation of
land uses, planning authorities should consider whether it
is practicable to control or reduce noise levels, or to
mitigate the impact of noise, through the use of conditions
or planning agreements. (See SDD Circular16/1973.)
NATURE CONSERVATION AND LANDSCAPE
71. Nature conservation and landscape quality can be
important material considerations in determining many
planning applications. Planning authorities should not,
however, refuse permission if development can be permitted
subject to conditions that will prevent damaging impacts on
particular species, wildlife habitats or important physical
features. Moreover, for some types of development, such as
mineral workings, conditions can be used to provide, on
completion of operations, a natural heritage asset.
Conditions can also be used, for example, to require areas
to be fenced or bunded off to protect them, to restrict
operations or uses at or to particular times of the year,
to safeguard particular views or to reinforce particular
landscape features. The views of Scottish Natural Heritage
(SNH) will be particularly important in assessing the
impact of development on the natural heritage of an area
and in framing appropriate conditions.
72. Planning authorities should bear in mind that a
number of areas valued for their landscape quality or
nature conservation interest are afforded statutory
protection. National Scenic Areas provide the national
designation for landscape. For habitats, as well as
national designations (primarily Sites of Special
Scientific Interest), European Community Directives on
nature conservation, most notably through Special Areas of
Conservation under the Habitats Directive and Special
Protection Areas under the Wild Birds Directive, are being
implemented. A number of sites have also been designated
under the Ramsar Convention on Wetlands of International
Importance. Conditions affecting such areas will need to be
consistent with the provisions applicable for their
protection. Scottish Office Environment Department
Circulars13/1991 and 6/1995 are particularly important
sources of information and guidance.
73. Where the primary concern relates to land management
or access to natural heritage resources, planning
authorities should consider whether mechanisms other than
those provided under planning legislation might provide the
best means of securing their objectives. Countryside
Management Agreements under the Countryside (Scotland) Act
1967 as amended by the Natural Heritage (Scotland) Act 1991
provide a mechanism for securing appropriate management of
natural heritage assets. Access or Public Path Creation
Agreements under the 1967 Act can be used to secure
appropriate access for enjoyment of the natural
heritage.
DESIGN AND LANDSCAPE
74. The appearance of a proposed development and its
relationship to its surroundings are material
considerations in planning decisions. While planning
authorities should not attempt to use conditions simply to
impose matters of taste, there will be circumstances where
it is important to secure a high quality of design in a
proposal if this is to make a positive contribution to a
site and its surroundings and show consideration for its
local context. This could involve, for example, specifying
in conditions the use of particular design features such as
materials or finishes. The appearance and treatment of the
spaces between and around buildings is also of great
importance. Similarly, planning authorities may wish to use
conditions to ensure that important vistas are preserved or
that landscape features are provided to improve the overall
setting of a development.
75. Landscape design may raise special considerations.
The treatment of open space can vary greatly and the
objective should be to ensure that the intended design
quality is achieved in practice. It is, therefore,
especially important for the authority to give some advance
indication of the essential characteristics of an
acceptable landscape scheme- always bearing in mind that
such requirements should not be unreasonable. It is of
equal importance to ensure that the design proposals are
reflected in the quality of works and materials in the
final product. The design and implementation stages of
landscape treatment may, therefore, be addressed more
successfully by separate conditions, occurring as they do
at different stages and under variable circumstances. The
visual impact of a development will often need to be
assessed as a whole and this may well involve considering
details of landscape design together with other reserved
matters.
Enforcement of Landscaping Requirements
76. To ensure that a landscape design scheme is
prepared, conditions may require that no development should
take place until the scheme is approved, so long as this
requirement is reasonable. Enforcing compliance with
landscape schemes can pose problems, since work on
landscaping can rarely proceed until building operations
are nearing completion. Only on permissions for a change of
use would it be acceptable to provide that the development
permitted should not proceed until the landscaping had been
substantially completed. Where permission is being granted
for a substantial estate of houses, it might be appropriate
to frame the relevant condition to allow for landscape
works to be phased in accordance with a programme or
timetable to be agreed between the developer and the
planning authority and submitted for approval as part of
the landscape design proposals. Alternatively, the erection
of the last few houses might be prohibited until planting
had been completed in accordance with the landscape scheme.
In relation to a permission for an industrial or office
building, it would be possible to impose a condition
prohibiting or restricting occupation of the building until
such works had been completed.
TREES
77. Section159 of the Act places an express duty on the
planning authority, when granting planning permission, to
ensure whenever appropriate that adequate conditions are
imposed to secure the preservation or planting of trees,
and that any necessary tree preservation orders are made
under section160 of the Act. When granting outline planning
permission, the authority may consider it appropriate to
impose a condition requiring the submission of particular
details relating to trees to be retained on the site, such
as their location in relation to the proposed development
and their general state of health and stability. When
granting detailed planning permission, conditions may be
used to secure the protection of trees to be retained, for
example by requiring the erection of fencing around trees
during the course of development or restricting works which
are likely to adversely affect them. The long-term
protection of trees, however, should be secured by tree
preservation orders rather than by condition. Such orders
may also be expedient for the temporary protection of
existing trees until details of the reserved matters are
submitted and it becomes clear whether there is a need to
retain the trees.
78. The planting and establishment of new trees may need
work over several months or years and the authority may
wish to ensure that they obtain details of those
responsible for the management and maintenance of certain
planted areas during that period of time. Where
appropriate, a condition may require not just initial
planting, but also that trees shall be maintained over a
specified period of years and that any which die or are
removed within that time shall be replaced.
SITES OF ARCHAEOLOGICAL INTEREST
Archaeological Sites
79. Monuments scheduled as of national importance by the
Secretary of State are protected by PartI of the Ancient
Monuments and Archaeological Areas Act 1979. Where its
provisions apply, their effect should not be duplicated by
planning conditions (see paragraphs19-21), although
authorities granting planning permission in such
circumstances are advised to draw the attention of the
applicant to the relevant provisions of the 1979 Act.
80. Where, however, planning permission is being granted
for development which might affect the setting of a
scheduled monument or a non-scheduled monument or its
setting, the planning authority may wish to impose
conditions designed to protect the monument or its setting;
to secure the provision of archaeological excavation and
recording prior to development commencing; or, if the
expectation of significant archaeological deposits is low,
to ensure arrangements are made for a watching brief before
and during the construction period. Further advice on
archaeology and planning conditions is given in NPPG 5
Archaeology and Planning and Planning Advice
Note42
Archaeology.
MAINTENANCE CONDITIONS
81. A condition may be imposed, where appropriate,
requiring some feature of a development to be retained- car
parking spaces off the road, for example, or an area of
open space in a housing scheme. A condition requiring
something to be maintained, in the sense of being kept in
good repair or in a prescribed manner, should be imposed
only when the planning authority are fully satisfied that
the requirement is both relevant to the development which
is being permitted, reasonable in its effects and
sufficiently precise in its terms to be readily
enforceable. Maintenance conditions should not normally be
imposed when granting permission for the erection of
buildings, or for works other than works of a continuing
nature such as minerals extraction.
CONDITIONS REQUIRING A FINANCIAL OR OTHER
CONSIDERATION FOR THE GRANT OF PERMISSION
82. As a general proposition no payment of money or
other consideration can be required when granting a
permission or any other kind of consent required by a
statute, except where there is specific statutory
authority. Conditions requiring, for instance, the cession
of land for road improvements or for open space, or
requiring the developer to contribute money towards the
provision of facilities not directly related to the
proposed development, should accordingly not be attached to
planning permissions. There may, however, be certain
circumstances whereby the general proposition should not
apply. The appropriateness of conditions involving
financial or other considerations is dependent on the
particular circumstances of the development for which the
planning authority intends to grant planning permission and
whether, in particular, the proposed conditions satisfy the
criteria in paragraph12. Thus conditions, involving
financial considerations, but which meet the tests in
paragraph12 need not necessarily be
ultra vires. Planning authorities should also bear
in mind the advice in SODD Circular12/1996 on
Planning Agreements.
CONDITIONS ALTERING THE NATURE OF THE
DEVELOPMENT
Modifying Proposed Development
83. If some feature of a proposed development, or the
lack of it, is unacceptable in planning terms, the best
course will often be for the applicant to be invited to
modify the application. If the modification is substantial,
of course, a fresh application will be needed. It may
however, depending on the case, be quicker and easier for
the planning authority to impose a condition modifying the
development permitted in some way. The precise course of
action will normally emerge during discussion with the
applicant. It would thus be legitimate to require by
condition that a factory proposal, for example, should
include necessary car parking facilities, but wrong to
grant permission for a development consisting of houses and
shops subject to a condition that houses be substituted for
the shops. Whether a modification would amount to
substantial difference will depend upon the circumstances
of the case. A useful test will be whether it would so
change the proposal that: (i) those who have shown an
interest in it would wish to comment on the modification;
and (ii) those who, although they had a right to object to
the original application and chose not to do so, would be
prejudiced if they were not now given an opportunity to
comment. A condition modifying the development, however,
cannot be imposed if it would make the development
permitted substantially different from that comprised in
the application.
REGULATION AFTER DEVELOPMENT
84. Conditions which will remain in force after the
development has been carried out always need particular
care. They can place onerous and permanent restrictions on
what can be done with the premises affected and they
should, therefore, not be imposed without scrupulous
weighing of where the balance of advantage lies. The
following paragraphs give more detailed guidance.
Restrictions on Use or Permitted
Development
85. Exceptionally, conditions may be imposed to restrict
further development which would normally be permitted by
the Town and Country Planning (General Permitted
Development) (Scotland) Order 1992, or to restrict changes
of use which would not be regarded as development whether
because the change is not a "material" change within the
terms of section26(1) of the Act, or by reason of
section26(2) and the provisions of The Town and Country
Planning (Use Classes) (Scotland) Order 1997. Changes of
use can be restricted either by prohibiting any change from
the use permitted or by precluding specific alternative
uses. It should be noted, however, that a condition
restricting changes of use will not restrict ancillary or
incidental activities unless it so specifies. Similarly, a
general condition which restricts the use of land does not
remove permitted development rights for that use unless the
condition specifically removes those rights as well.
Presumption Against Such Restrictions
86. Both the General Permitted Development Order and the
Use Classes Order, however, are designed to give or confirm
a freedom from detailed control which will be acceptable in
the great majority of cases. Accordingly, save in
exceptional circumstances, conditions should not be imposed
which restrict either permitted development rights granted
by the General Permitted Development Order or future
changes of use which the Use Classes Order would otherwise
allow. The Secretary of State would regard such conditions
as unreasonable unless there were clear evidence that the
uses excluded would have serious adverse effects on amenity
or the environment, that there was no other forms of
control and that the condition would serve a clear planning
purpose.
87. To illustrate some exceptional circumstances, it may
be possible to justify imposing a condition restricting
permitted development rights allowed by Class7 of the
General Permitted Development Order so as to preserve an
exceptionally attractive open plan estate free of fences,
or under Class1 of the General Permitted Development Order
so as to avoid over-development by extensions to
dwellinghouses in an area of housing at unusually high
density. Similarly, changes of use may be restricted so as
to prevent the use of large retail premises as a food or
convenience goods supermarket, where such a use may
generate an unacceptable level of additional traffic or
have a damaging effect on the vitality of a nearby town
centre. Conditions may also limit the storage of hazardous
substances in a warehouse.
Specific Conditions Better than General
Ones
88. Because of the general presumption against such
restrictions on permitted development or on changes of use
which are not development, it will always be necessary to
look carefully at the planning reasons for any restriction
and to ensure that the condition imposed is no more onerous
than can be justified (see paragraph87 above). It would not
be right to use a condition restricting uses where an
alternative, more specific, condition would achieve the
same end. For example, where it is necessary to restrict
the volume of noise emitted from an industrial site and a
condition addressing the problem expressly can be used,
that condition should be imposed, rather than one
restricting the permitted uses. Scrupulous care in the
giving of proper, adequate and intelligible reasons for
imposing conditions (see paragraph9) can help authorities
to ensure that the conditions they impose are not more
onerous than is necessary to achieve their objective.
Restrictions on Use
89. It will be preferable if a condition designed to
restrict changes of use can be drafted so as to prohibit a
change to a particular unacceptable use or uses (provided
the list does not become too long), rather than in terms
which prevent any change of use at all. However, in certain
cases a condition confining the use only to the use
permitted may be necessary. In appropriate circumstances,
it might be reasonable to impose a condition limiting the
intensification of use of small office or industrial
buildings where intensification beyond a certain point
would generate traffic and/or parking problems. Conditions
designed to prevent the primary use of an office building
being changed to use as shops are unnecessary, as this
would involve a material change of use amounting to
development of land which would require planning
permission.
Ancillary Uses
90. Conditions are sometimes imposed restricting
ancillary or incidental activities which would not normally
be material changes of use involving development.
Conditions of this kind can be burdensome to some
technologically advanced industries. They may have a need
for higher than normal levels of ancillary office, research
or storage uses, or for short-term changes in uses or the
balance of uses. Such conditions should, therefore, not
normally be imposed on permissions for manufacturing or
service industry, except where they are designed to
preclude or regulate activities giving rise to hazard,
noise or offensive emissions.
CONDITIONS RESTRICTING THE OCCUPANCY OF
BUILDINGS AND LAND
Occupancy: General Considerations
91. Since planning controls are concerned with the use
of land rather than the identity of the user, the question
of who is to occupy premises for which permission is to be
granted will normally be irrelevant. Conditions restricting
occupancy to a particular occupier or class of occupier
should only be used when special planning grounds can be
demonstrated and where the alternative would normally be
refusal of permission.
Personal Permissions
92. Unless the permission otherwise provides, planning
permission runs with the land and it is seldom desirable to
provide otherwise. There are occasions relating, for
example, to strong compassionate or other personal grounds,
where the planning authority is minded to grant permission
for the use of a building or land for some purpose which
would not normally be allowed. In such a case the
permission may be made subject to a condition that it shall
enure only for the benefit of a named person- usually the
applicant. A permission personal to a company is generally
inappropriate. Conditions of this type will scarcely ever
be justified in the case of a permission for the erection
of a permanent building.
General Undesirability of Commercial and
Industrial Occupancy Conditions
93. Conditions are sometimes imposed to confine the
occupation of commercial or industrial premises to local
firms. Such conditions can act- undesirably- to protect
local businesses against fair competition and may hinder
the movement of industry in response to economic demand. If
a service, or the employment it generates, is needed in an
area, there is no planning reason why it should be provided
by one firm rather than another. Commercial and industrial
buildings in an area of open countryside will not become
more acceptable because their occupancy is restricted, nor
will the expansion of a local firm necessarily lead to less
pressure for further development (eg housing) than the
arrival of a firm from outside. The Secretary of State
therefore regards such conditions as undesirable in
principle.
Conditions Governing Size of Unit Occupied
94. Conditions requiring that a large commercial or
industrial building should be occupied either only as a
single unit or, alternatively, only in suites not exceeding
a certain area or floorspace, represent a significant
interference with property rights which is likely to
inhibit or delay the productive use of the buildings
affected. Such conditions should, therefore, normally be
avoided.
Domestic Occupancy Conditions
95. Subject to the advice about affordable housing
(paragraph96), staff accommodation (paragraph98-99),
agricultural and forestry dwellings (paragraphs100-102) and
seasonal use (paragraphs111-113), if the development of a
site for housing is an acceptable use of the land, there
will seldom be any good reason on land use planning grounds
to restrict the occupancy of those houses to a particular
type of person (eg those already living or working in the
area). To impose such a condition would be to draw an
artificial and unwarranted distinction between new houses
or new conversions and existing houses that are not subject
to such restrictions on occupancy or sale. It may deter
housebuilders from providing homes for which there is a
local demand and building societies from providing mortgage
finance. It may also impose hardship on owners who
subsequently need to sell. It involves too detailed and
onerous an application of development control and too great
an interference in the rights of individual ownership. Such
conditions should, therefore, not be imposed save in the
most exceptional cases where there are clear and specific
circumstances that warrant allowing an individual house (or
extension) on a site where development would not normally
be permitted.
Affordable Housing
96. The community's need for a mix of housing types-
including affordable housing- is capable of being a
material planning consideration. It follows that there may
be circumstances in which it will be acceptable to use
conditions to ensure that some of the housing built is
occupied only by people falling within particular
categories of need. Such conditions would normally only be
necessary where a different planning decision might have
been taken if the proposed development did not provide for
affordable housing and should make clear the nature of the
restriction by referring to criteria set out in the
relevant development plan policy. Conditions should not
normally be used to control matters such as tenure, price
or ownership. Guidance on affordable housing is contained
in NPPG 3:
Land for Housing.
"Granny Annexes"
97. Some extensions to dwellings are intended for use as
"granny annexes". It is possible that a "granny annex"
which provides independent living accommodation, could
subsequently be let or sold off separately from the main
dwelling. Where there are sound planning reasons why the
creation of an additional dwelling would be unacceptable,
it may be appropriate to impose a planning condition to the
effect that the extension permitted shall be used solely as
accommodation ancillary to the main dwellinghouse. The same
is true for separate buildings (often conversions of
outbuildings) intended for use as "granny annexes". In
these cases it is even more likely that a separate unit of
accommodation will be created.
Staff Accommodation
98. The above considerations may equally apply to staff
accommodation. Where an existing house is within the
curtilage of another building and the two are in the same
occupation, any proposal to occupy the two buildings
separately is likely to amount to a material change of use,
so that planning permission would be required for such a
proposal even in the absence of a condition. Planning
authorities should normally consider applications for such
development sympathetically since, if the need for such a
dwelling (for the accommodation of an employee, for
example) disappears, there will generally be no
justification for requiring the building to stand empty or
to be demolished.
99. Conditions tying the occupation of dwellings to that
of separate buildings (eg requiring a house to be occupied
only by a person employed by a nearby garage) should be
avoided. However, exceptionally, such conditions may be
appropriate where there are sound planning reasons to
justify them, eg where a dwelling has been allowed on a
site where permission would not normally be granted. To
grant an unconditional permission would mean that the
dwelling could be sold off for general use which may be
contrary to development plan policy for the locality. To
ensure that the dwelling remains available to meet the
identified need, it may therefore be acceptable to grant
permission subject to a condition that ties the occupation
of the new house to the existing business.
Agricultural and Forestry Dwellings
100. In many parts of Scotland planning policies impose
strict controls on new residential development in the open
countryside. There may, however, be circumstances where
permission is granted to allow a house to be built to
accommodate a worker engaged in
bona fide agricultural or forestry employment on a
site where residential development would not normally be
permitted. In these circumstances, it will often be
necessary to impose an agricultural or forestry worker
occupancy condition.
101. Planning authorities will wish to take care to
frame agricultural occupancy conditions in such a way as to
ensure that their purpose is clear. In particular, they
will wish to ensure that the condition does not have the
effect of preventing future occupation by retired
agricultural workers or the dependants of the agricultural
occupant.
102. Where an agricultural occupancy condition has been
imposed, it will not be appropriate to remove it on a
subsequent application unless it is shown that
circumstances have materially changed and that the
agricultural need which justified the approval of the house
in the first instance no longer exists.
Retail Development
103. Out-of-centre retail developments, including retail
parks, can change their composition over time. If such a
change would create a development that the planning
authority would have refused on the grounds of impact on
vitality and viability of an existing town centre, it may
be sensible to consider the use of planning conditions to
ensure that these developments do not subsequently change
their character unacceptably. Any conditions imposed should
apply only to the main ranges of goods (eg food and
convenience goods, hardware, electrical goods, furniture
and carpets) and should not seek to control details of
particular products to be sold. For further guidance see
NPPG 8:
Retailing.
TEMPORARY PERMISSIONS
104. Section41(1)(b) of the Act gives power to impose
conditions requiring that a use be discontinued or that
buildings or works be removed at the end of a specified
period. Where permission is granted for the development of
the operational land of a statutory undertaker, however,
this power does not apply except with the undertaker's
consent (see section219 of the Act). Conditions of this
kind are sometimes confused with conditions which impose a
time-limit for the implementation of a permission
(paragraphs45 to 49) but they are quite distinct and
different considerations arise in relation to them.
Principles Applying to Temporary
Permissions
105. In other cases, in deciding whether a temporary
permission is appropriate, three main factors should be
taken into account. Firstly, it will rarely be necessary to
give a temporary permission to an applicant who wishes to
carry out development which conforms with the provision of
the development plan. Secondly, it is undesirable to impose
a condition requiring the demolition after a stated period
of a building that is clearly intended to be permanent.
Lastly, the material considerations to which regard must be
had in granting any permission are not limited or made
different by a decision to make the permission a temporary
one. Thus, the reason for granting a temporary permission
can never be that a time-limit is necessary because of the
effect of the development on the amenity of the area. Where
such objections to a development arise they should, if
necessary, be met instead by conditions whose requirements
will safeguard amenity. If it is not possible to devise
such conditions and the damage to amenity cannot be
accepted, then the proper course is to refuse permission.
These considerations mean that a temporary permission will
normally only be appropriate either where the applicant
himself proposes temporary development or when a trial run
is needed in order to assess the effect of the development
on the area.
Short-Term Buildings or Uses
106. Where, therefore, a proposal relates to a building
or use which the applicant is expected to retain or
continue only for a limited period, whether because he has
specifically volunteered that intention or because it is
expected that the planning circumstances will change in a
particular way at the end of that period, then a temporary
permission may be justified. For example, permission might
reasonably be granted on an application for erection of a
temporary building to last seven years on land which will
be required for road improvements eight or more years
hence, although an application to erect a permanent
building on the land would normally be refused.
Trial Runs
107. Again, where an application is made for permanent
permission for a use which may be a "bad neighbour" to
existing uses nearby but there is insufficient evidence to
enable the authority to be sure of its character or effect,
it might be appropriate to grant a temporary permission in
order to give the development a trial run, provided that
such a permission would be reasonable having regard to the
capital expenditure necessary to carry out the development.
However, a temporary permission would not be justified
merely because, for example, a building is to be made of
wood rather than brick. Nor would a temporary permission be
justified on the grounds that, although a particular use,
such as a hostel or playgroup, would be acceptable in a
certain location, the character of its management may
change. In certain circumstances it may be possible to
grant temporary permission for the provision of a caravan
or other temporary accommodation, where there is some
evidence to support the grant of planning permission for an
agricultural or forestry dwelling but it is inconclusive,
perhaps because there is doubt about the sustainability of
the proposed enterprise. This allows time for such
prospects to be clarified.
108. A second temporary permission should not normally
be granted. A trial period should be set that is
sufficiently long for it to be clear by the end of the
permission whether permanent permission or a refusal is the
right answer. Usually a second temporary permission will
only be justified where road or redevelopment proposals
have been postponed or in cases of hardship where temporary
instead of personal permission has been granted for a
change of use.
Restoration of Sites
109. If the temporary permission is for development
consisting of, or including, the carrying out of
operations, it is important to make provision by condition
for the removal of any buildings and works permitted- not
merely for the cessation of the use- and for the
reinstatement of the land when the permission expires.
Where the permission is for temporary use of land as a
caravan site, conditions may include a requirement to
remove at the expiry of the permission any buildings or
structures, such as toilet blocks, erected under Class17 of
the General Permitted Development Order.
ACCESS FOR DISABLED PEOPLE
110. Where a building is new or is being altered, it is
usually sufficient to rely on building regulations to
ensure adequate access for disabled people. However, some
new development does not require building regulation
approval, eg development affecting the setting of buildings
(layout of estates, pedestrianisation etc) rather than the
buildings themselves. Where there is a clear planning need,
it may be appropriate to impose a condition to ensure
adequate access for disabled people.
SEASONAL USE
Seasonal Occupancy Conditions
111. Occasionally it may be acceptable to limit the use
of land for a particular purpose to certain seasons of the
year. For example, where planning permission is being
granted for a caravan site, the planning authority may
think it necessary to impose a condition to ensure that
during the winter months the caravans are not occupied and
are removed for storage to a particular part of the site or
away from the site altogether. Where such a condition is
imposed, particular care should be taken to see that the
condition allows a reasonable period of use of the caravans
in each year. A similar approach may be taken where it is
necessary to prevent the permanent residential use of
holiday chalets, which by the character of their
construction or design are unsuitable for continuous
occupation. Seasonal occupancy conditions may also be
appropriate to protect the local environment, or example,
where the site is near a fragile habitat which requires
peace and quiet to allow seasonal breeding or winter
feeding to take place.
Holiday Occupancy Conditions
112. In recent years there has been an increased demand
for self-catering holiday accommodation- whether new
buildings (including mobile homes) or converted properties-
which may be constructed to a standard that would equally
support permanent residence in some comfort. But this
accommodation may also be located in areas in which the
provision of permanent housing would be contrary to
national policies on development in the countryside or not
in accordance with development plan policies, or both. The
Secretary of State considers that the planning system
should respond to these changes without compromising
policies to safeguard the countryside.
113. There may be circumstances where it will be
reasonable for the planning authority to grant planning
permission for holiday accommodation as an exception to
these policies, with a condition specifying its use as
holiday accommodation only. For example, conversions of
redundant buildings into holiday accommodation where
conversion to residential dwellings would not be permitted
may reduce the pressure on other housing in rural areas. A
holiday occupancy condition would seem more appropriate in
those circumstances than a seasonal occupancy condition.
But authorities should continue to use seasonal occupancy
conditions to prevent the permanent residential use of
accommodation which by the character of its construction or
design is unsuitable for continuous occupation,
particularly in the winter months.
Contents |