| Description | Planning Advice Note PAN 55 THE PRIVATE FINANCE INITIATIVE AND THE PLANNING PROCESS |
|---|
| ISBN | n/a (Web Only) |
|---|
| Official Print Publication Date | |
|---|
| Website Publication Date | March 01, 1999 |
|---|
Planning Advice Note PAN 55
THE PRIVATE FINANCE INITIATIVE AND THE PLANNING
PROCESS
introduction
1. The Private Finance Initiative (PFI) aims to promote
efficient cost-effective public sector procurement of
services from the private sector. The services are procured
by a legal contract between a public sector agency (the
sponsor) and a private sector supplier (the supplier). The
supplier will be chosen through a competition organised by
the sponsor.
2. The effectiveness of PFI is dependent on the
innovation of the supplier which is encouraged by
competition. Bidders in PFI competitions are therefore
encouraged to find the best cost-effective solution and are
not restricted to a single pre-determined option. This will
normally mean that bidders come forward with different
technical solutions for the provision of the assets
required for service delivery, for example a new road, a
new or re-furbished school, a prison, or a sewage treatment
works.
3. The procurement of a PFI service by legal contract is
often referred to as a DBFO (design, build, finance and
operate) contract. This reflects the contract requirements
for the supplier to provide and finance the capital
equipment, buildings and other infrastructure required to
supply the service. It is important to note that the PFI
contract is not solely for the supply of the capital
assets, but also for the supply of services arising from
the use of those assets by skilled operators and other
employees or sub-contractors of the supplier.
4. The provision of the physical capital assets by the
private sector to meet the requirements of the PFI
contract, must be supplied in accordance with EC
Directives, UK legislation and policy requirements,
including the land use planning system.
5. This note provides guidance on the promotion and
implementation of a PFI project within the land use
planning system. The contents of the note will be relevant
to all participants in a PFI project, in particular the
sponsor (including where the sponsor is also the planning
authority), the planning authority and the private sector
bidder. The particular considerations which apply where the
sponsor is also the planning authority are dealt with in a
separate section (paragraphs 22 to 26).
general guidance
Establishing the Principle
6. PFI projects involving the development of land will
normally require to secure planning permission and this
process will generally be more straightforward if the
project accords with both National Planning Policy
Guidelines (NPPGs) and the development plan for the area
concerned. As with any major project, where a PFI proposal
diverges significantly from structure plan policy, or
contravenes national planning policies, the planning
authority should notify the application to the Secretary of
State. Where the local authority is a party to the proposal
or has an interest in it, there will often be a requirement
to notify the Secretary of State (see paragraph 23).
7. Section 25 of the Town and Country Planning
(Scotland) Act 1997 states that where regard is to be had
to the development plan in considering a planning
application, the provisions of the plan shall be the
primary consideration in arriving at a decision. It is
therefore important that, wherever possible, public sector
sponsors should actively engage with the development plan
preparation process to seek to ensure that structure and
local plans make appropriate provision for the projects
they intend to pursue. Even if the sponsor is not in a
position to be site specific, it is important to establish
the principle of development and appropriate planning
parameters.
Project Management
8. The responsibility for integrating the planning
requirements with the other aspects of the project rests
with the sponsor. It is fundamental to the achievement of a
successful contract that the main planning issues are
identified by the sponsor at the outset alongside all the
other key components - technical, legal, financial and
operational. Sponsors should ensure that they have
appropriate planning expertise within their project team,
be it internal resources or professional consultancy
support. Within the planning authority, individual officers
may be unfamiliar with the PFI procurement process.
However, the active involvement of planning authorities is
integral to the success of the project. It is important
that they are kept informed throughout the process, that
they are involved in the business case process, and that
their involvement is recognised as a critical strand of the
initial project appraisal.
Planning Permission: Outline and
Detailed
9. Establishing appropriate planning parameters for the
project and, where appropriate, securing outline planning
consent, will normally be the responsibility of the
sponsor. Obtaining detailed planning permission should
normally be the responsibility of the supplier, who in most
cases will be better placed to submit planning applications
having identified his proposed best option and having the
necessary supporting information.
10. Where the principle of the land use proposed has not
already been established in the development plan, it may be
appropriate for the sponsor to obtain outline planning
permission, leaving the supplier to secure detailed
consent. In certain circumstances the sponsor may consider
it appropriate to obtain full planning permission before
commencing the procurement process. This may be relevant
where there is effectively only one possible design option
(e.g. with a road proposal). The financial risks to the
sponsor of such action will need to be taken into
consideration. It will also be important to establish that
this would not unduly limit the scope for private sector
innovation or the cost-effective provision of services.
Generally, it will be more appropriate for the process of
obtaining full planning consent to be carried out by the
supplier.
Liaising with the Planning Authority
11. The sponsor should approach the planning authority
at an early stage to secure its assistance in identifying
the key planning issues which are likely to be pertinent
for the particular project, along with general planning and
timing constraints. It will be good practice at the outset
to agree a basis for liaison between the two parties. Such
an agreement might cover the scope and terms of any
development brief, the procedures for access and
information exchange between the sponsor, bidders and the
planning authority, the provision of opportunities for the
planning authority to comment on bid submissions at each
stage of the bid process, and the subsequent monitoring of
the PFI project after the contract has been signed and
planning permission granted.
12. For projects which may be candidates for
environmental assessment in terms of the EC Directive on
Environmental Assessment (85/337/EC) as amended by
Directive 97/11/EC, the sponsor should seek an opinion from
the planning authority (under Regulation 7 of the EA
Regulations) as to whether it would be likely to have
significant effects on the environment. The Town and
Country Planning Environmental Impact Assessment (Scotland)
Regulations 1999 will bring the amended directive into
force and will supersede the Environmental Assessment
(Scotland) Regulations 1988 .
13. Good communication between the relevant parties is
essential throughout the process of securing planning
permission and will ensure that all are working towards
appropriate outputs. It is important to identify critical
dates and agree a protocol and timetable at the outset. The
timetable should include a reasonable allocation of time
for consultation. To maintain consistency and
confidentiality, contact should be between named officials
throughout the process, although the involvement of these
officials should not compromise the function of the
planning authority in any way.
14. Given the significant size of many PFI projects, it
will often be necessary for the planning authority to
involve a wide range of interests within the authority to
establish a corporate approach to the project from the
beginning. The authority may also require to consult a wide
range of other interests, particularly for projects which
require an Environmental Statement, and it may be necessary
to raise any wider strategic issues within inter-authority
liaison arrangements. Where environmental assessment is
required, the time needed should be factored into the
project planning and also the four month period for
determining the planning application. For larger projects,
there may be an advantage in establishing a working group
of representatives of the various interested parties to
ensure close liaison and effective management of the
process. However, any such arrangements must not prejudice
the planning authority's formal assessment of any resulting
application.
Managing the Bidding Process
15. It is important to allow bidders freedom to submit
imaginative, value-for-money proposals. However, effort may
be wasted and the scope for efficiency savings may be lost
or reduced if the subsequent procedures to obtain consent
for the selected scheme take too long or are unsuccessful.
The risk of this happening can be reduced by making certain
that all of the essential planning requirements are
sufficiently clear at the outset, to ensure that only
projects capable of development into satisfactory solutions
are taken forward by bidders. Input from the planning
authority to the preparation of the development brief may
help to ensure that bidders have a good understanding of
the planning parameters (see paragraphs 17-21).
16. Bidding for PFI projects can be expensive and
innovative ideas developed during the tender period have a
high commercial value. If meaningful discussions are to
take place between the sponsor, the planning authority and
bidders during the course of the competition, it is
important that these are recognised to be commercial - in
confidence. A balance must be achieved between maintaining
confidentiality with each bidder whilst treating each
even-handedly. In the case of one bidder requesting a
certain set of information, it is good practice to send the
same information to all other bidders.
Development Brief
17. Defining the appropriate level of prescription may
be difficult at the start of project. In many cases, the
best approach may be for the sponsor to agree a development
brief with the planning authority. This will help ensure
that there is one coherent development brief and not two or
more, possibly with conflicting requirements. The brief
would highlight the relevant aspects of the development
plan for the area and identify constraints or requirements
in relation to such issues as land uses, densities,
building heights, design principles, transport arrangements
and open space and playing field provision.
18. At the outset it may be necessary for the sponsor to
prepare an introductory document outlining the background
to the PFI project and identifying the planning issues
which may need to be addressed. If the sponsor does not
have in-house skills suitable for preparing this document,
it may be appropriate to engage consultants to assist. In
the light of this initial document and subsequent meetings
with the planning authority, a development brief can then
be agreed for presentation to potential bidders at the
pre-qualification stage. The parties may wish to make
provision for the development brief to be considered by the
authority's Planning Committee for support in principle
without prejudice to its determination of any future
planning application.
19. Short-listed bidders will be able to use the brief
to design and cost their scheme without drawing it up in
detail. Where there are clear value-for-money alternatives
proposed by bidders, then these can be viewed in relation
to the requirements of the development brief. The preferred
bidder, assuming it has followed the development brief
principles, can have greater confidence that planning
approval will be obtained, although no guarantee can be
given .
20. The preparation of the development brief for a PFI
project and the ensuing stages of amendment, bid evaluation
and project monitoring will take place through agreed
procedures between the sponsor and the planning authority
(see paragraph 11). This provides the interface between the
market competition of PFI bidders and the public interests
represented by the planning process.
21. These procedures need to be kept as simple as
possible to reduce the preparatory costs for all parties -
the sponsor, the planning authority and the bidders.
However, to proceed without adequate preparation and
agreement on the terms of a development brief at the start
may entail higher costs for all parties at a later stage.
The balance of effort and resources from sponsor and
planning authority should be discussed at an early stage so
that all parties are aware of their roles and
responsibilities as the project proceeds through its
various stages.
local authority projects
22. In circumstances where a local authority is a PFI
project sponsor, careful consideration will have to be
given to the matter of securing planning permission for the
proposed development. In many cases the authority is likely
to wish to establish at least the principle of planning
permission for the development to minimise the risk to the
PFI contractors that permission may not be forthcoming.
Where the sponsor body is also the planning authority, care
must be taken not to compromise the function of that
authority. It is essential that the roles of sponsor and
planning authority are kept separate.
23. Where the planning authority has an interest in a
PFI project, the following requirements have to be taken
into account in relation to referral of such proposals to
the Secretary of State. The Town and Country Planning
(Development by Planning Authorities) (Scotland)
Regulations 1981 (the NID regulations) make provision for
cases where a local authority require planning permission
for a development which they themselves propose to carry
out in the area in respect of which they are the planning
authority. The regulations specify requirements regarding
advertisement of the intention to develop, consultation
prior to advertisement and the circumstances in which a
notice of intention to develop must be served on the
Secretary of State. Local authorities should consider
carefully regulation 7 which specifies that, where planning
permission is deemed to have been granted the permission
"shall enure only for the benefit of the planning authority
carrying out the development and not for the benefit of the
land". Legal advice should be taken as to whether a PFI
contractor would be able to proceed with the development on
the basis of the deemed planning permission or would also
require to seek planning permission.
24. Attention is also drawn to paragraph 13 of SODD
Circular 4/1997 on the Notification of Planning
Applications which explains that "[the NID] regulations do
not make provision for procedure analogous to applications
for outline planning permission"; i.e. NIDs cannot be
advertised as outline proposals. This may render the NID
procedures inappropriate for development proposals for
which the local authority is looking to contractors to
undertake the detailed design of the scheme.
25. Alternatively, if a local authority is of the view
that a particular PFI project is to be carried out by
someone other than themselves - i.e. it is not a case where
the authority requires planning permission for a
development which they propose to carry out - then the NID
procedures would not be available to them. In such
circumstances it would be open to the authority's planning
department to require a planning application of another
department (e.g. the education department for a PFI schools
project or the roads department for a PFI road project), or
a third party agent. Such an application would be handled
under normal planning procedures and the authority would be
obliged to consider the terms of the Town and Country
Planning (Notification of Applications) (Scotland)
Direction 1997 which is incorporated in SODD Circular
4/1997. Article 16 of the Schedule to the Direction refers
to "development in which planning authorities have an
interest" and thus brings such development within the
notification procedures.
26. This means that a planning authority must notify the
Secretary of State if it proposes to grant planning
permission for development:
- in which it has a financial interest; or
- which is to be located on land in which it has an
interest;
in circumstances where the NID regulations do not apply,
and the proposed development does not accord with the
adopted or approved local plan for the area, or has been
the subject of a substantial body of objections.
summary
27. PFI projects are subject to the normal requirements
of the UK planning system. The public sector agency
sponsoring a PFI project is responsible for defining the
framework in which the PFI project will be taken forward
and within which planning issues will require to be
addressed.
28. PFI places particular pressures on the planning
process. Sponsors should actively engage with the process
to seek to ensure that development plans make appropriate
provision for the projects they intend to pursue. They also
require to pay close attention to the procedural
requirements of the planning system and approach the
planning authority as early in the project development
process as possible.
29. The sponsor is responsible for securing the
establishment of appropriate planning parameters for the
project and, where appropriate, outline planning consent.
Obtaining detailed planning permission should normally be
the responsibility of the supplier. Sponsors should only
submit an application for full planning permission where
there is only one suitable scheme or it is impracticable to
defer until after the tender competition.
30. The preparation of a development brief can be of
assistance in defining the planning parameters for a PFI
project.
note
31. Enquiries about the contents of this planning advice
note should be addressed to Graeme Purves, The Scottish
Office, Planning Services Division, Room 2-H91, Victoria
Quay, Edinburgh, EH6 6QQ (0131 244 7533) or by e-mail to
graeme.purves@scotland.gov.uk.
Further copies, together with other PANs, may be obtained
by telephoning 0131 244 7538. A copy of this PAN is also
available on the Scottish Office web site at
www.scotland.gov.uk.
bibliography
SO Circulars
SODD 4/1997: Notification of Planning Applications
Legislation
Town and Country Planning (Scotland) Act 1997
Town and Country Planning (Development by Planning
Authorities) (Scotland) Regulations 1981
Town and Country Planning (Notification of
Applications) (Scotland) Direction 1997
Town and Country Planning Environmental Impact
Assessment (Scotland) Regulations 1999
Environmental Assessment (Scotland) Regulations 1988
EC Directive on Environmental Assessment (85/337/EC)
as amended by Directive 97/11/EC